  "title": "100 MW data center design and delivery records for Inyokern and Ellendale",
  "checked_on": "2026-11-23",
  "method": "Transcribe the capacity scope and project stage separately using the cited filings. Land figures describe the applicant’s design. Ellendale milestones reflect issuer reports. The examples do not establish availability for a new customer.",
  "projects": [
    {
      "name": "RB Inyokern Data Center",
      "location": "Inyokern, Kern County, California",
      "docket": "26-SPPE-01",
      "status_at_check": "proposed; environmental review",
      "observations": [
        {
          "record": "inyokern-application",
          "stage": "applicant design",
          "total_electrical_demand_mw_approx": 99,
          "aggregate_it_load_mw_approx": 70,
          "building_square_feet_approx": 238000,
          "data_halls": 6,
          "site_acres_approx": 50,
          "on_site_development_acres_approx": 38.18
        },
        {
          "record": "inyokern-review",
          "stage": "agency review notice",
          "docketed_on": "2026-11-19",
          "maximum_emergency_generation_mw": 99,
          "agency_reported_use": "Emergency backup during utility outages"
        }
      ]
    },
    {
      "name": "Polaris Forge 1",
      "location": "Ellendale, North Dakota",
      "observations": [
        {
          "record": "apld-annual",
          "stage": "reported operational",
          "effective_month": "2025-10",
          "scope": "first building",
          "critical_it_mw_approx": 100
        },
        {
          "record": "apld-annual",
          "stage": "reported contracted",
          "as_of_date": "2026-05-31",
          "scope": "campus across three buildings",
          "critical_it_mw_approx": 400
        },
        {
          "record": "apld-quarter",
          "stage": "reported ready for service",
          "effective_date": "2026-07-01",
          "scope": "Building 2 first phase",
          "incremental_critical_it_mw": 75,
          "campus_live_critical_it_mw": 175
        },
        {
          "record": "apld-quarter",
          "stage": "reported ready for service",
          "effective_date": "2026-10-01",
          "scope": "Building 2 second phase",
          "incremental_critical_it_mw": 75,
          "campus_live_critical_it_mw": 250
        }
      ]
    }
  ],
  "sources": [
    {
      "id": "inyokern-application",
      "title": "RB Inyokern Data Center application, sections 1.2.2 and 1.4",
      "url": "https://efiling.energy.ca.gov/GetDocument.aspx?DocumentContentId=107049&tn=269893",
      "publisher": "R&L Capital via California Energy Commission",
      "locator": "Executive summary, pp. 8 and 13–16, sections 1.2.2 and 1.4"
    },
    {
      "id": "inyokern-review",
      "title": "RB Inyokern revised environmental review notice, docket 26-SPPE-01, TN 273731",
      "url": "https://efiling.energy.ca.gov/GetDocument.aspx?DocumentContentId=121554&tn=273731",
      "publisher": "California Energy Commission",
      "locator": "Revised notice dated November 18 and docketed November 19, 2026, first and second pages of notice"
    },
    {
      "id": "apld-annual",
      "title": "Applied Digital annual filing for May 2026, Polaris Forge 1",
      "url": "https://www.sec.gov/Archives/edgar/data/1144879/000114487926000048/apld-20260531.htm",
      "publisher": "Applied Digital via SEC EDGAR",
      "locator": "Item 1, Business, Polaris Forge 1 and contracted lease portfolio"
    },
    {
      "id": "apld-quarter",
      "title": "Applied Digital October 2026 quarterly release, Polaris Forge 1 delivery",
      "url": "https://www.sec.gov/Archives/edgar/data/1144879/000114487926000057/apldq127earningsrelease.htm",
      "publisher": "Applied Digital via SEC EDGAR",
      "locator": "Recent Highlights, Subsequent to the Quarter, and Business Update"
    }
  ]
}