# AI data centres in India: gigawatt campuses, IndiaAI GPUs and power (2026)

> AI data centres in India include gigawatt-scale campuses at Visakhapatnam and Jamnagar; IndiaAI Mission compute passed 45,000 GPUs by June 2026. Projects and power.

URL: https://invariant-ai.com/blog/ai-data-centres-india  
Published: 2026-11-21 · Publisher: Invariant · Region: India

India’s largest AI data centre projects are gigawatt-scale campuses, led by Google’s AI hub in Visakhapatnam, where ground was broken in April 2026, and the multi-gigawatt data centres Reliance has begun building at Jamnagar. Reliance is also to build a 168 MW AI-ready data centre to be leased by Meta. OpenAI is TCS HyperVault’s first customer with 100 MW and plans to scale to 1 GW, and CoreWeave plans 240 MW at AdaniConneX in Navi Mumbai. The IndiaAI Mission had more than 38,000 GPUs onboarded at Rs 65 per hour by February 2026 and more than 45,000 in its shared compute capacity by June 2026.

## Key points

- Announced gigawatt-scale AI campuses include Google’s AI hub in Visakhapatnam (about US$15 billion over 2026 to 2030), Reliance at Jamnagar, Digital Connexion in Visakhapatnam, TCS HyperVault and AM Green in Greater Noida (MoU).
- The IndiaAI Mission GPU pool grew from 18,693 (January 2025) to 34,333 (May 2025), 38,000+ at Rs 65 per hour (February 2026) and 45,000+ (June 2026), according to PIB and to Invest India and Cushman & Wakefield.
- Anarock puts an Nvidia H100 GPU cluster at 30 to 60 kW per rack against 8 to 10 kW traditionally. Power per GPU, not floor area, sizes the site.
- SBI’s sector report says MeitY AI cloud tenders have required PUE below 1.35.

## AI data centre campuses announced in India

| Project | Scale | Location | Status and date |
| --- | --- | --- | --- |
| Google AI hub (with AdaniConneX and Nxtra by Airtel) | Gigawatt-scale; about US$15 billion over 2026 to 2030 | Visakhapatnam | Groundbreaking 28 April 2026 |
| Reliance AI data centres | Multi-gigawatt; more than 120 MW expected online in H2 2026 | Jamnagar, Gujarat | Under construction (February 2026); 168 MW AI-ready data centre to be leased by Meta (June 2026) |
| TCS HyperVault | Above 1 GW targeted; OpenAI starting with 100 MW, plans to scale to 1 GW | Not disclosed | OpenAI deal February 2026 |
| Digital Connexion | 1 GW; about US$11 billion by 2030 | Visakhapatnam | MoU November 2025 |
| AM Green | 1 GW | Greater Noida | MoU January 2026; first capacity targeted 2028 |
| CoreWeave at AdaniConneX | 240 MW (3 x 80 MW buildings) | Taloja, Navi Mumbai | First phase expected mid-2028 |
| Yotta D2 | 60 MW, scalable to 250 MW; supercluster of 20,736 NVIDIA Blackwell Ultra GPUs, with added capacity from Navi Mumbai | Greater Noida | Go-live expected by August 2026 |

Sources: ([Google](https://blog.google/intl/en-in/company-news/our-first-ai-hub-in-india-powered-by-a-15-billion-investment/)) ([Adani Group](https://www.adani.com/newsroom/media-releases/google-breaks-ground-on-india-ai-hub-launching-a-national-industrial-ecosystem)) ([TechCrunch](https://techcrunch.com/2026/02/19/reliance-unveils-110b-ai-investment-plan-as-india-ramps-up-tech-ambitions/)) ([TechCrunch](https://techcrunch.com/2026/06/10/meta-signs-first-ai-data-center-deal-in-india-with-reliance/)) ([Cushman & Wakefield](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b)) ([Tata Consultancy Services](https://www.tcs.com/who-we-are/newsroom/press-release/tcs-secures-1bn-investment-from-tpg-accelerate-ai-data-center-business-hypervault)) ([TechCrunch](https://techcrunch.com/2026/02/18/openai-taps-tata-for-100mw-ai-data-center-capacity-in-india-eyes-1gw/)) ([Business Today](https://www.businesstoday.in/latest/corporate/story/reliance-brookfield-digital-realty-jv-to-invest-11-billion-in-andhra-pradesh-to-build-1-gw-data-centre-503905-2025-11-27)) ([Communications Today](https://www.communicationstoday.co.in/uttar-pradesh-signs-mou-with-am-green-group-for-1-gw-ai-data-centre/)) ([CoreWeave](https://www.coreweave.com/news/coreweave-enters-india-expanding-ai-cloud-platform-with-adaniconnex)) ([Yotta](https://yotta.com/press-releases/yotta-to-deploy-20000-nvidia-blackwell-ultra-gpus/))

Announcements are not capacity. Treat MoUs and approvals as intent until there is a power connection agreement and a construction start. Invest India and Cushman & Wakefield’s AI scenario assumes 15% of a 15 GW early-stage pipeline converts, which still yields about 8 GW by 2030. ([Invest India and Cushman & Wakefield](https://static.investindia.gov.in/s3fs-public/2026-10/latest-news-India-Data-Centre-Growth-Story.pdf))

## IndiaAI Mission GPU count, 2025 to 2026

| Date | GPUs in the pool | Price note | Source |
| --- | --- | --- | --- |
| January 2025 | 18,693 (including 12,896 H100) | Under Rs 100 per hour after a 40% government subsidy | PIB release via Principal Scientific Adviser |
| May 2025 | 34,333 (18,417 existing plus 15,916 added) | Seven bidders offered commercials | PIB |
| February 2026 | 38,000+ GPUs and 1,050 TPUs | Rs 65 per hour | PIB |
| June 2026 | 45,000+ | 15 compute service providers empanelled (Lok Sabha figures, August 2026) | Invest India and Cushman & Wakefield citing PIB; Communications Today |
| October 2026 | C-DAC request for empanelment for up to 10,000 AI compute units | Clusters of 4,000, 1,000 or 512 units; each cluster at least 512 units at a single data centre in India | MediaNama |

Sources: ([Office of the Principal Scientific Adviser (PIB release)](https://psa.gov.in/CMS/web/sites/default/files/publication/India%20all%20set%20to%20launch%20its%20own%20safe%20%26%20secure%20indigenous%20AI%20model%20at%20affordable%20cost%20soon%20Shri%20Ashwini%20Vaishnaw.pdf)) ([Press Information Bureau (MeitY)](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2132817)) ([Press Information Bureau](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2225781)) ([Invest India and Cushman & Wakefield](https://static.investindia.gov.in/s3fs-public/2026-10/latest-news-India-Data-Centre-Growth-Story.pdf)) ([Communications Today](https://www.communicationstoday.co.in/indiaai-mission-faces-gap-between-capacity-and-deployed-gpus/)) ([MediaNama](https://www.medianama.com/2026/10/223-meity-ai-compute-providers-gpus-indiaai-mission/))

Yotta committed over 10,000 B300 GPUs to the IndiaAI Mission. The seven bidders named by PIB in May 2025 were Cyfuture India, Ishan Infotech, Locuz Enterprise Solutions, Netmagic IT Services, Sify Digital Services, Vensysco Technologies and Yotta Data Services. ([Yotta](https://yotta.com/press-releases/yotta-to-deploy-20000-nvidia-blackwell-ultra-gpus/)) ([Press Information Bureau (MeitY)](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2132817))

## Power for AI data centres in India

Power per GPU, not floor area, sizes an AI data centre in India. Anarock puts an Nvidia H100 GPU cluster at 30 to 60 kW per rack against 8 to 10 kW traditionally, and SBI notes that air cooling approaches its limits beyond about 15 kW per rack, leading to early adoption of direct-to-chip and immersion cooling. A 100 MW AI hall therefore needs a high-voltage grid connection with a firm energisation date. ([Anarock](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf)) ([SBI CHAKRA Centre of Excellence](https://sbi.bank.in/documents/57189647/58231607/Sector+Report+DataCentre.pdf/f1919592-ee66-b50b-ea20-75fbb27c9bb5?t=1779885206866))

Crisil estimates Visakhapatnam’s data centre capacity could equal about 80% of the city’s current peak demand by FY2030. Reliance says its build-out will be supported by its green energy capacity, including surplus solar power in Gujarat and Andhra Pradesh. ([Deccan Herald](https://www.deccanherald.com/business/india-set-for-five-times-surge-in-its-data-centre-capacity-by-2030-4205631)) ([TechCrunch](https://techcrunch.com/2026/02/19/reliance-unveils-110b-ai-investment-plan-as-india-ramps-up-tech-ambitions/))

**Sizing a GPU cluster:** [How much power a GPU cluster needs](https://invariant-ai.com/blog/gpu-cluster-power-requirements) · [Power for data centres in India](https://invariant-ai.com/blog/power-for-data-centres-india) · [Grid connection: DISCOM, STU and CTU paths](https://invariant-ai.com/blog/data-centre-grid-connection-india)

## More on data centres in India

**Start here:** [Data centres in India: capacity, cities, policy, power](https://invariant-ai.com/blog/data-centres-in-india) · [How to find a data centre site in India](https://invariant-ai.com/blog/find-data-centre-site-india) · [Data centre companies in India](https://invariant-ai.com/blog/data-centre-companies-india)

**Build and approvals:** [Approvals for a data centre in India](https://invariant-ai.com/blog/data-centre-approvals-india) · [How to set up a data centre in India](https://invariant-ai.com/blog/how-to-set-up-data-centre-india) · [Data centre cost per MW in India](https://invariant-ai.com/blog/data-centre-cost-per-mw-india) · [Site due diligence in India](https://invariant-ai.com/blog/data-centre-site-due-diligence-india) · [Data centre land and powered land in India](https://invariant-ai.com/blog/data-centre-land-india) · [Seismic zones, flood and cyclone risk](https://invariant-ai.com/blog/data-centre-seismic-flood-risk-india) · [Water and groundwater NOC for data centres](https://invariant-ai.com/blog/data-centre-water-india) · [DPDP Act and data localisation](https://invariant-ai.com/blog/dpdp-data-localisation-data-centres-india) · [Infrastructure status, tax holiday and DC SEZs](https://invariant-ai.com/blog/data-centre-incentives-india-central)

**Power:** [Power for data centres in India](https://invariant-ai.com/blog/power-for-data-centres-india) · [Grid connection: DISCOM, STU and CTU paths](https://invariant-ai.com/blog/data-centre-grid-connection-india) · [Green energy open access for data centres](https://invariant-ai.com/blog/green-energy-open-access-data-centres-india) · [Open access charges by state](https://invariant-ai.com/blog/open-access-charges-by-state-india) · [India data centre power demand to 2032](https://invariant-ai.com/blog/data-centre-power-demand-india) · [Power studies for Indian data centre sites](https://invariant-ai.com/blog/power-study-data-centre-india) · [Diesel generators and backup power rules](https://invariant-ai.com/blog/data-centre-backup-power-dg-sets-india)

**Policy by state:** [National data centre policy](https://invariant-ai.com/blog/national-data-centre-policy-india) · [State data centre policies compared](https://invariant-ai.com/blog/data-centre-policy-india-state-comparison) · [Maharashtra data centre policy](https://invariant-ai.com/blog/maharashtra-data-centre-policy) · [Uttar Pradesh data centre policy](https://invariant-ai.com/blog/uttar-pradesh-data-centre-policy) · [Tamil Nadu data centre policy](https://invariant-ai.com/blog/tamil-nadu-data-centre-policy) · [Telangana data centre policy](https://invariant-ai.com/blog/telangana-data-centre-policy) · [Gujarat data centre policy](https://invariant-ai.com/blog/gujarat-data-centre-policy) · [Karnataka data centre policy](https://invariant-ai.com/blog/karnataka-data-centre-policy) · [Andhra Pradesh data centre policy](https://invariant-ai.com/blog/andhra-pradesh-data-centre-policy) · [Haryana data centre policy](https://invariant-ai.com/blog/haryana-data-centre-policy) · [Rajasthan data centre policy](https://invariant-ai.com/blog/rajasthan-data-centre-policy) · [Odisha data centre policy](https://invariant-ai.com/blog/odisha-data-centre-policy) · [West Bengal data centre policy](https://invariant-ai.com/blog/west-bengal-data-centre-policy) · [Madhya Pradesh data centre policy](https://invariant-ai.com/blog/madhya-pradesh-data-centre-policy)

**Cities:** [Data centres in Mumbai and Navi Mumbai](https://invariant-ai.com/blog/data-centres-in-mumbai) · [Data centres in Chennai](https://invariant-ai.com/blog/data-centres-in-chennai) · [Data centres in Hyderabad](https://invariant-ai.com/blog/data-centres-in-hyderabad) · [Data centres in Noida and Delhi NCR](https://invariant-ai.com/blog/data-centres-in-noida) · [Data centres in Bengaluru](https://invariant-ai.com/blog/data-centres-in-bengaluru) · [Data centres in Pune](https://invariant-ai.com/blog/data-centres-in-pune) · [Data centres in Visakhapatnam](https://invariant-ai.com/blog/data-centres-in-visakhapatnam) · [Data centres in Gujarat: GIFT City, Ahmedabad, Jamnagar](https://invariant-ai.com/blog/data-centres-in-gujarat) · [Data centres in Kolkata and East India](https://invariant-ai.com/blog/data-centres-in-kolkata)

**Compare and invest:** [Mumbai vs Chennai vs Hyderabad](https://invariant-ai.com/blog/mumbai-vs-chennai-vs-hyderabad-data-centres) · [India vs Singapore vs Johor](https://invariant-ai.com/blog/india-vs-singapore-vs-johor-data-centres) · [AI data centres and IndiaAI GPUs](https://invariant-ai.com/blog/ai-data-centres-india) · [Data centre investment in India](https://invariant-ai.com/blog/data-centre-investment-india)

## Questions

### How many AI data centres are being built in India?

AI projects of 240 MW or more announced since 2025 include Google and Digital Connexion in Visakhapatnam, Reliance at Jamnagar and CoreWeave at AdaniConneX in Navi Mumbai. TCS HyperVault aims for capacity above 1 GW, and AM Green signed an MoU with Uttar Pradesh for a 1 GW AI data centre in Greater Noida. ([Google](https://blog.google/intl/en-in/company-news/our-first-ai-hub-in-india-powered-by-a-15-billion-investment/)) ([TechCrunch](https://techcrunch.com/2026/02/19/reliance-unveils-110b-ai-investment-plan-as-india-ramps-up-tech-ambitions/)) ([Tata Consultancy Services](https://www.tcs.com/who-we-are/newsroom/press-release/tcs-secures-1bn-investment-from-tpg-accelerate-ai-data-center-business-hypervault)) ([Business Today](https://www.businesstoday.in/latest/corporate/story/reliance-brookfield-digital-realty-jv-to-invest-11-billion-in-andhra-pradesh-to-build-1-gw-data-centre-503905-2025-11-27)) ([Communications Today](https://www.communicationstoday.co.in/uttar-pradesh-signs-mou-with-am-green-group-for-1-gw-ai-data-centre/)) ([CoreWeave](https://www.coreweave.com/news/coreweave-enters-india-expanding-ai-cloud-platform-with-adaniconnex))

### How many GPUs does the IndiaAI Mission have?

More than 45,000 GPUs in shared compute capacity by June 2026, according to Invest India and Cushman & Wakefield citing PIB. PIB reported more than 38,000 GPUs at Rs 65 per hour in February 2026. ([Press Information Bureau](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2225781)) ([Invest India and Cushman & Wakefield](https://static.investindia.gov.in/s3fs-public/2026-10/latest-news-India-Data-Centre-Growth-Story.pdf))

### How much does IndiaAI Mission GPU compute cost per hour?

Rs 65 per hour in February 2026, according to PIB. In January 2025 the price was under Rs 100 per hour after a 40% government subsidy. ([Press Information Bureau](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2225781)) ([Office of the Principal Scientific Adviser (PIB release)](https://psa.gov.in/CMS/web/sites/default/files/publication/India%20all%20set%20to%20launch%20its%20own%20safe%20%26%20secure%20indigenous%20AI%20model%20at%20affordable%20cost%20soon%20Shri%20Ashwini%20Vaishnaw.pdf))

### Which gigawatt-scale AI data centres are under construction in India?

Google broke ground on its gigawatt-scale AI hub in Visakhapatnam on 28 April 2026, and Reliance says it has begun building multi-gigawatt data centres at Jamnagar. ([Adani Group](https://www.adani.com/newsroom/media-releases/google-breaks-ground-on-india-ai-hub-launching-a-national-industrial-ecosystem)) ([TechCrunch](https://techcrunch.com/2026/02/19/reliance-unveils-110b-ai-investment-plan-as-india-ramps-up-tech-ambitions/))

### How much power does an AI data centre need in India?

Far more per rack than a conventional data centre: Anarock puts an Nvidia H100 GPU cluster at 30 to 60 kW per rack against 8 to 10 kW traditionally. A 100 MW AI hall needs a high-voltage grid connection with a firm energisation date. ([Anarock](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf))

## Sources

- Google: [Our first AI hub in India, powered by a $15 billion investment](https://blog.google/intl/en-in/company-news/our-first-ai-hub-in-india-powered-by-a-15-billion-investment/)
- Adani Group: [Google breaks ground on India AI hub](https://www.adani.com/newsroom/media-releases/google-breaks-ground-on-india-ai-hub-launching-a-national-industrial-ecosystem)
- TechCrunch: [Reliance unveils $110B AI investment plan](https://techcrunch.com/2026/02/19/reliance-unveils-110b-ai-investment-plan-as-india-ramps-up-tech-ambitions/)
- TechCrunch: [Meta signs first AI data center deal in India with Reliance](https://techcrunch.com/2026/06/10/meta-signs-first-ai-data-center-deal-in-india-with-reliance/)
- Cushman & Wakefield: [India Data Centre Market Overview H1 2026](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b)
- Tata Consultancy Services: [TCS secures investment from TPG to accelerate AI data center business HyperVault](https://www.tcs.com/who-we-are/newsroom/press-release/tcs-secures-1bn-investment-from-tpg-accelerate-ai-data-center-business-hypervault)
- TechCrunch: [OpenAI taps Tata for 100 MW AI data center capacity in India, eyes 1 GW](https://techcrunch.com/2026/02/18/openai-taps-tata-for-100mw-ai-data-center-capacity-in-india-eyes-1gw/)
- Business Today: [Reliance, Brookfield, Digital Realty JV to invest $11 billion in Andhra Pradesh for 1 GW data centre](https://www.businesstoday.in/latest/corporate/story/reliance-brookfield-digital-realty-jv-to-invest-11-billion-in-andhra-pradesh-to-build-1-gw-data-centre-503905-2025-11-27)
- Communications Today: [Uttar Pradesh signs MoU with AM Green Group for 1 GW AI data centre](https://www.communicationstoday.co.in/uttar-pradesh-signs-mou-with-am-green-group-for-1-gw-ai-data-centre/)
- CoreWeave: [CoreWeave enters India with AdaniConneX](https://www.coreweave.com/news/coreweave-enters-india-expanding-ai-cloud-platform-with-adaniconnex)
- Yotta: [Yotta to deploy 20,000+ NVIDIA Blackwell Ultra GPUs](https://yotta.com/press-releases/yotta-to-deploy-20000-nvidia-blackwell-ultra-gpus/)
- Invest India and Cushman & Wakefield: [India's Data Centre Growth Story (October 2026)](https://static.investindia.gov.in/s3fs-public/2026-10/latest-news-India-Data-Centre-Growth-Story.pdf)
- Office of the Principal Scientific Adviser (PIB release): [India all set to launch its own AI model; 18,693 GPUs offered (January 2025)](https://psa.gov.in/CMS/web/sites/default/files/publication/India%20all%20set%20to%20launch%20its%20own%20safe%20%26%20secure%20indigenous%20AI%20model%20at%20affordable%20cost%20soon%20Shri%20Ashwini%20Vaishnaw.pdf)
- Press Information Bureau (MeitY): [India’s common compute capacity crosses 34,000 GPUs](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2132817)
- Press Information Bureau: [Democratising AI in India](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2225781)
- Communications Today: [IndiaAI Mission faces gap between capacity and deployed GPUs](https://www.communicationstoday.co.in/indiaai-mission-faces-gap-between-capacity-and-deployed-gpus/)
- MediaNama: [MeitY seeks AI compute providers for up to 10,000 GPUs under IndiaAI Mission](https://www.medianama.com/2026/10/223-meity-ai-compute-providers-gpus-indiaai-mission/)
- Anarock: [Data Centre: The Blueprint of the Digital Fortress in India (2026)](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf)
- SBI CHAKRA Centre of Excellence: [Data Centres in India: sector report (April 2026)](https://sbi.bank.in/documents/57189647/58231607/Sector+Report+DataCentre.pdf/f1919592-ee66-b50b-ea20-75fbb27c9bb5?t=1779885206866)
- Deccan Herald: [India set for five times surge in its data centre capacity by 2030 (Crisil Ratings)](https://www.deccanherald.com/business/india-set-for-five-times-surge-in-its-data-centre-capacity-by-2030-4205631)

## Related

- [Data centres in India: capacity, cities, companies, policy and power (2026)](https://invariant-ai.com/blog/data-centres-in-india)
- [Data centres in Visakhapatnam: Google’s AI hub, gigawatt campuses and risks (2026)](https://invariant-ai.com/blog/data-centres-in-visakhapatnam)
- [Power for data centres in India: grid supply, open access and tariffs by state](https://invariant-ai.com/blog/power-for-data-centres-india)
- [How much power does a GPU cluster need? H100, B200 and GB200 NVL72 in MW](https://invariant-ai.com/blog/gpu-cluster-power-requirements)
- [Data centre investment in India: hyperscaler commitments and deals (2026)](https://invariant-ai.com/blog/data-centre-investment-india)

---

[Email your India data centre project requirements](mailto:pranav@invariant-ai.com) · [Book a call](https://cal.com/pranav-goswami/website-30min)