  "title": "Data center marketplace power and purchase screening examples",
  "checked_on": "2026-11-25",
  "scope": "Six selected public marketed examples chosen to illustrate power delivery stages and transaction filters. The review records what each source reports and does not estimate the prevalence of differences across any marketplace.",
  "screen": {
    "transaction": "purchase",
    "existing_gross_utility_mw": 10,
    "requires_current_offer_for_sale": true
  },
  "results": {
    "examples": 6,
    "examples_with_at_least_10_mw_in_headline_or_summary_field": 5,
    "examples_marketed_for_purchase_with_at_least_10_mw_reported_existing_service": 1
  },
  "records": [
    {
      "listing": "North Carolina AI campus",
      "provider": "Invariant",
      "published_search_mw": 18,
      "published_field": "Headline MW reported live",
      "reported_existing_utility_mw": 18,
      "reported_critical_it_mw": null,
      "offer_as_published": "Marketed for sale; confirm current status",
      "phase_detail": "Seller reports 18 MW in service and billed. Additional capacity is reported for 2028.",
      "buy_now_screen": "Potential lead. Verify uncommitted MW at the meter, assignability and current availability before underwriting delivery.",
      "source_url": "https://invariant-ai.com/blog/north-carolina-18-mw-ai-campus-207-acres-for-sale"
    },
    {
      "listing": "Upstate South Carolina powered shell",
      "provider": "Baxtel",
      "published_search_mw": 20,
      "published_field": "Available Power",
      "reported_existing_utility_mw": 3,
      "reported_critical_it_mw": null,
      "offer_as_published": "Marketed for sale or lease",
      "phase_detail": "3 MW reported live. The 20+ MW figure comes from a verbal prescreen. The listing says a formal study has yet to be commissioned.",
      "buy_now_screen": "Below 10 MW of reported existing service. Request a formal utility study for the expansion.",
      "source_url": "https://baxtel.com/listings/upstate-south-carolina-3-mw-powered-shell"
    },
    {
      "listing": "Hickory colocation facility",
      "provider": "Vocom",
      "published_search_mw": 15,
      "published_field": "Building headline MW",
      "reported_existing_utility_mw": 3,
      "reported_critical_it_mw": null,
      "offer_as_published": "Marketed for sale, long-term lease or colocation",
      "phase_detail": "3 MW reported live. The 15 MW figure depends on a 44 kV transformer build-out.",
      "buy_now_screen": "Below 10 MW of reported existing service. Confirm current tenant commitments and transformer delivery before counting the expansion.",
      "source_url": "https://www.vocom.ai/buy-a-data-center"
    },
    {
      "listing": "Kansas City powered shell",
      "provider": "Baxtel",
      "published_search_mw": 26,
      "published_field": "Available Power",
      "reported_existing_utility_mw": null,
      "reported_critical_it_mw": null,
      "offer_as_published": "Marketed for lease only",
      "phase_detail": "6 MW reported committed, with building step-down due in Q1 2027. About 20 MW more depends on a second substation, with 2028 the earliest stated timing.",
      "buy_now_screen": "For lease only. Keep separate from purchase results and verify the first phase for a lease review.",
      "source_url": "https://baxtel.com/listings/kansas-city-6-mw-shell"
    },
    {
      "listing": "Providence data center",
      "provider": "Baxtel",
      "published_search_mw": 9,
      "published_field": "Available Power",
      "reported_existing_utility_mw": 5,
      "reported_critical_it_mw": 3.6,
      "offer_as_published": "Pending; listing unavailable when checked",
      "phase_detail": "5 MW total utility and about 3.6 MW critical IT reported, based on a historical 1.4 PUE. The longer expansion would bring utility service to about 18.5 MW.",
      "buy_now_screen": "Pending and below 10 MW of reported existing utility service.",
      "source_url": "https://baxtel.com/listings/providence-6-6-mw-tier-iii-data-center"
    },
    {
      "listing": "Eastern North Dakota campus",
      "provider": "Vocom",
      "published_search_mw": 230,
      "published_field": "Maximum marketed campus MW",
      "reported_existing_utility_mw": null,
      "reported_critical_it_mw": null,
      "offer_as_published": "Marketed as a sale of the site-holding entity",
      "phase_detail": "100 MW feed line described as ready, with delivery expected in 2027 subject to signing a utility contract. The next 100 MW is in study.",
      "buy_now_screen": "Development lead. Request the signed utility contract, the first delivery schedule and the remaining work at the point of service.",
      "source_url": "https://www.vocom.ai/buy-a-data-center"
    }
  ],
  "evidence_boundary": "As-marketed facts, not an independent utility service or deal-status verification. Null values mean the review did not establish that field from the published listing."
}