  "title": "Data center on-site power delivery evidence for Aggreko, Bloom and McCloud",
  "checked_on": "2026-11-24",
  "method": "Record each milestone and capacity figure with the scope the source gives it. A null means the reviewed source leaves the figure undisclosed. For procurement, validate net capacity and acceptance at the buyer's electrical delivery point.",
  "cases": [
    {
      "provider": "Aggreko",
      "project": "Temporary commissioning power for a hyperscale data center",
      "location": "South Bend, Indiana",
      "evidence_stage": "Provider reports deployment and completed operating period",
      "reported_total_temporary_power_mw": 60,
      "reported_mobilization_notice_months": 1,
      "reported_operating_period_months": 6,
      "reported_uptime_percent": 99.1,
      "tested_net_mw_at_facility_intake": null,
      "first_50_mw_acceptance_date": null,
      "source_ids": ["aggreko-south-bend"]
    },
    {
      "provider": "Bloom Energy",
      "project": "First fuel cell deployment reported for Oracle",
      "location": null,
      "evidence_stage": "Provider reports a working system delivered in 2025",
      "operational_delivery_year": 2025,
      "announced_deployment_schedule_days": 90,
      "reported_deployment_days": 55,
      "schedule_start_date": null,
      "first_system_mw": null,
      "tested_net_mw_at_facility_intake": null,
      "source_ids": ["bloom-oracle-delivery"]
    },
    {
      "provider": "El Paso Electric and ERock",
      "project": "McCloud bridge generation facility for Wurldwide",
      "location": "El Paso, Texas",
      "evidence_stage": "Administrative proposal for decision and provider-reported construction",
      "proposed_net_peak_generation_mw_approx": 366,
      "proposed_continuous_bridge_mw": 225,
      "proposed_bridge_load_factor_percent_approx": 95,
      "utility_expected_construction_completion_month": "2027-05",
      "utility_expected_continuous_power_delivery_month": "2027-06",
      "provider_completion_target": "mid-2027",
      "provider_construction_update_on": "2026-11-12",
      "commission_notice_on": "2026-11-24",
      "commission_meeting_scheduled_for": "2026-12-03",
      "verified_commercial_operation_date": null,
      "source_ids": ["mccloud-proposal", "mccloud-erock-q3", "mccloud-meeting-notice"]
    }
  ],
  "sources": [
    {
      "id": "aggreko-south-bend",
      "publisher": "Aggreko",
      "url": "https://www.aggreko.com/en-us/case-studies/data-centres/temporary-power-enabling-hyperscale-data-center-commissioning",
      "locator": "Overview and Impact"
    },
    {
      "id": "bloom-oracle-delivery",
      "publisher": "Bloom Energy",
      "url": "https://www.bloomenergy.com/news/bloom-energy-and-oracle-expand-strategic-partnership-to-deploy-up-to-2-8-gw-to-accelerate-ai-infrastructure-build-out/",
      "locator": "April 13, 2026 announcement, paragraph on the initial delivery in 2025"
    },
    {
      "id": "mccloud-proposal",
      "publisher": "Texas State Office of Administrative Hearings",
      "url": "https://interchange.puc.texas.gov/Documents/59076_176_1686197.PDF#page=50",
      "locator": "September 23, 2026 Proposal for Decision, Findings 9, 16 and 22, printed pages 44 and 45"
    },
    {
      "id": "mccloud-erock-q3",
      "publisher": "ERock via SEC EDGAR",
      "url": "https://www.sec.gov/Archives/edgar/data/2110029/000119312526456998/eroc-ex99_1.htm",
      "locator": "November 12, 2026 results, Business Highlights and Management Commentary"
    },
    {
      "id": "mccloud-meeting-notice",
      "publisher": "Public Utility Commission of Texas",
      "url": "https://interchange.puc.texas.gov/Documents/59076_191_1705118.PDF#page=2",
      "locator": "Docket 59076 item 191, Office of Policy and Docket Management memorandum"
    }
  ]
}