  "title": "Aiken data center transmission and energization evidence",
  "public_docket": "South Carolina PSC 2024-61-E",
  "retrieved_date": "2026-11-22",
  "location": "Aiken County, South Carolina",
  "source_documents": {
    "application": {
      "url": "https://dms.psc.sc.gov/Attachments/Matter/22620ad8-27bf-451b-8cea-29459466abaa",
      "document_sha256": "6277a21e52227e6ad9fb5966581946210e06daed886749b86dff68ce4f6e64d2",
      "pdf_pages": [
        3,
        4,
        5
      ]
    },
    "certificate": {
      "url": "https://dms.psc.sc.gov/Attachments/Order/f3daf477-c6ef-432a-bcaf-3893bcd510ca",
      "document_sha256": "963733624ce5a70296337069d58e1c0a242681154e9862a6384dbb74db10d2a0",
      "pdf_pages": [
        1,
        9,
        12,
        13,
        22,
        23,
        24
      ]
    },
    "status_report": {
      "url": "https://dms.psc.sc.gov/Attachments/Matters/7b7241a9-d728-45d6-b6a9-fc1f30c0b1bf.pdf",
      "document_sha256": "412203e1af8df9228e3cfa48816753957e63a49833bb3fab084165409f40c170",
      "pdf_pages": [
        1
      ]
    }
  },
  "scope": "Public application, certificate, and April 2, 2026 utility status report. Scope, planned milestones, and reported energization are recorded separately.",
  "service_request": {
    "agreement_entered_month_as_reported": "2023-09",
    "peak_facility_demand_mw_as_planned": 200,
    "peak_facility_demand_qualifier": "Up to 200 MW",
    "source": "application",
    "original_target_in_service_as_reported": "Fall 2025 for Central’s project as stated in the application"
  },
  "certificate": {
    "order_number": "2024-498",
    "issued_date": "2024-07-23",
    "initial_voltage_option_kv": 115,
    "selected_voltage_kv": 230,
    "selection_basis_as_reported": "Santee Cooper concluded the 115 kV option required substantial facility upgrades. Testimony in the order described 230 kV service as more timely and cost-effective for the customer.",
    "source": "certificate"
  },
  "transmission_scope": [
    {
      "responsible_party": "Santee Cooper",
      "from": "Aiken No. 3 substation",
      "to": "Mt. Zion switching station",
      "voltage_kv": 230,
      "lines_as_planned": 2,
      "distance_miles_as_described": 16.2,
      "distance_basis": "Length stated for the Aiken No. 3 to Mt. Zion buildout, primarily along existing rights of way.",
      "source": "certificate"
    },
    {
      "responsible_party": "Central Electric Power Cooperative",
      "from": "Mt. Zion switching station",
      "to": "Two customer-owned substations",
      "voltage_kv": 230,
      "lines_as_planned": 2,
      "distance_miles_as_described": 1.5,
      "distance_basis": "Combined line length for Central’s two feeders, as described in the order.",
      "source": "certificate"
    }
  ],
  "events_as_of_april_status_filing": [
    {
      "event_type": "Utility reported construction complete for specified transmission scope",
      "date": "2025-12-09",
      "date_basis": "Date of letter cited in the April report, rather than exact date construction concluded.",
      "source": "status_report"
    },
    {
      "event_type": "Customer Substation #1 energized",
      "date": "2025-12-15",
      "date_basis": "Actual date reported by Santee Cooper in its April 2, 2026 filing.",
      "source": "status_report"
    },
    {
      "event_type": "Revised requested window for Customer Substation #2",
      "date": "2026-04-02",
      "date_basis": "Filing date. The customer requested delay to May or June 2026.",
      "window_as_reported": "2026-05/2026-06",
      "actual_energization_date_as_established_by_selected_records": null,
      "source": "status_report"
    }
  ],
  "days_from_certificate_to_first_reported_energization": 510,
  "first_substation_energization_mw_as_established_by_selected_records": null
}