Building a data centre in India costs ₹35 crore to ₹75 crore per MW of IT load according to SBI’s April 2026 sector report, which gives ₹35 to 45 crore for large facilities, ₹50 to 55 crore for an air-cooled Tier III build and up to ₹75 crore for AI with immersion cooling or Tier IV. Cushman & Wakefield benchmarks US$7.4 million per MW, about 23% below Malaysia and 26% below Australia, and assumes US$9.0 million per MW for incremental AI capacity in its projections. Anarock prices land separately, at ₹3 crore to ₹60 crore per acre across its size bands, and reports long-tenor debt at about 9.5 to 10.5%.

## Key points

- Cushman & Wakefield: US$7.4 million per MW, about 23% below Malaysia and 26% below Australia; it assumes US$9.0 million per MW for incremental AI capacity.
- SBI (April 2026): ₹50 to 55 crore per MW for air-cooled Tier III, up to ₹75 crore for AI with immersion cooling or Tier IV, ₹35 to 45 crore for large facilities.
- Anarock: ₹40 to 45 crore per MW (low) to ₹65 to 70 crore per MW (high) for a greenfield Tier III N+1 build.
- In Mumbai, wholesale colocation of 5 MW and above rented at about ₹6,000 to 7,500 per kW per month in H1 2025, according to Cushman & Wakefield.

## Data centre construction cost per MW in India: published benchmarks

| Publisher | Benchmark | Scope stated |
| --- | --- | --- |
| Cushman & Wakefield, in Invest India’s October 2026 report | US$7.4 million per MW; US$9.0 million per MW assumed for incremental AI capacity | Construction cost benchmark; AI figure is a projection assumption |
| SBI (April 2026) | ₹50 to 55 crore per MW | Standard Tier III, non-AI, air-cooled |
| SBI (April 2026) | Up to ₹75 crore per MW | AI workloads with immersion cooling, or Tier IV |
| SBI (April 2026) | ₹35 to 45 crore per MW | Larger data centres |
| Anarock (2026) | ₹40 to 45 crore per MW to ₹65 to 70 crore per MW (US$4.8 to 8.4 million) | Total greenfield Tier III N+1 |

Sources: ([Invest India and Cushman & Wakefield](https://static.investindia.gov.in/s3fs-public/2026-10/latest-news-India-Data-Centre-Growth-Story.pdf)) ([SBI CHAKRA](https://sbi.bank.in/documents/57189647/58231607/Sector+Report+DataCentre.pdf/f1919592-ee66-b50b-ea20-75fbb27c9bb5?t=1779885206866)) ([Anarock](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf))

Anarock prices land separately, per acre. Crisil puts Indian development costs about one fifth below several competing Asia Pacific markets. ([Anarock](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf)) ([Deccan Herald](https://www.deccanherald.com/business/india-set-for-five-times-surge-in-its-data-centre-capacity-by-2030-4205631))

A cross-check from the sector level: ICRA expected third-party capacity to grow from 1,250 MW in FY2025 to 2,400 to 2,500 MW by FY2028 with an investment pipeline of ₹90,000 crore, which works out (our calculation) to roughly ₹72 to 78 crore per MW added. ([ICRA](https://www.icra.in/CommonService/OpenMediaS3?Key=540ab708-7459-44fd-9680-82d127a4906a))

## What drives data centre cost per MW in India

- Cooling and density: Anarock maps precision air conditioning (CRAC/CRAH, the most common in India) to 3 to 10 kW per rack, in-row cooling to 15 to 25 kW, rear-door heat exchangers to 20 to 40 kW and direct liquid cooling to 40 to 100 kW or more; it puts an Nvidia H100 GPU cluster at 30 to 60 kW per rack.
- Tier and cooling: SBI puts an air-cooled Tier III build at ₹50 to 55 crore per MW and AI with immersion cooling or Tier IV at up to ₹75 crore.
- Efficiency targets: SBI reports leading Indian operators at PUE 1.4 to 1.5 and MeitY AI cloud tenders since 2024 requiring below 1.35, which pushes design toward more efficient cooling.
- Power infrastructure: Anarock puts DG, UPS, HT supply and switchgear at ₹14 to 22 crore per MW, its largest single line. Ask the discom or transmission utility who pays for the dedicated line, bay and substation.

Sources: ([Anarock](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf)) ([SBI CHAKRA](https://sbi.bank.in/documents/57189647/58231607/Sector+Report+DataCentre.pdf/f1919592-ee66-b50b-ea20-75fbb27c9bb5?t=1779885206866))

**Power cost and connection:** [Grid connection: DISCOM, STU and CTU paths](https://invariant-ai.com/blog/data-centre-grid-connection-india) · [Open access charges by state](https://invariant-ai.com/blog/open-access-charges-by-state-india) · [Power for data centres in India](https://invariant-ai.com/blog/power-for-data-centres-india)

## Data centre land cost in India

| Facility size | Typical land | Land price per acre |
| --- | --- | --- |
| 5 to 10 MW | 2 to 5 acres | ₹35 to 60 crore (Mumbai suburbs); ₹4 to 10 crore (secondary cities) |
| 10 to 30 MW | 5 to 15 acres | ₹5 to 20 crore |
| 30 to 100 MW | 15 to 50 acres | ₹4 to 12 crore |
| 100 to 500 MW | 50 to 200 acres | ₹3 to 10 crore |

Sources: ([Anarock](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf))

Recent transactions sit inside these bands: Zee Business reported in June 2026 that Amazon Data Services bought 10.6 acres from Lodha for ₹125.13 crore, about ₹11.8 crore per acre (our calculation). ([Zee Business](https://www.zeebiz.com/hindi/real-estate/amazon-data-services-india-has-acquired-approximately-42955-sq-meters-of-non-agricultural-land-from-lodha-developers-256535))

**Land:** [Data centre land and powered land in India](https://invariant-ai.com/blog/data-centre-land-india)

## Colocation rents in India by city

Cushman & Wakefield’s H1 2025 report publishes rents in ₹ per kW per month, assuming standard 5 to 7 kVA racks; its H1 2026 report does not include a rent table. ([Cushman & Wakefield](https://assets.cushmanwakefield.com/-/media/cw/apac/india/insights/indiadatacentreupdateh12025v4.pdf?rev=4a5dd53b2388421ea3935afb03302def)) ([Cushman & Wakefield](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b))

| City | Under 250 kW | 250 kW to 1 MW | 1 to 5 MW | 5 MW and above |
| --- | --- | --- | --- | --- |
| Mumbai | 8,000 to 12,000 | 7,000 to 10,000 | 6,500 to 8,000 | 6,000 to 7,500 |
| Chennai | 8,000 to 9,000 | 7,500 to 8,500 | 7,000 to 8,000 | 6,000 to 7,000 |
| Hyderabad | 7,500 to 9,500 | 7,000 to 8,500 | 6,500 to 7,500 | 6,000 to 7,000 |
| Delhi NCR | 7,500 to 9,500 | 7,000 to 8,500 | 6,500 to 7,500 | 6,000 to 7,000 |
| Bengaluru | 7,500 to 9,000 | 7,000 to 8,500 | 7,000 to 8,000 | 6,500 to 7,000 |
| Pune | 7,000 to 8,500 | 6,500 to 8,000 | 6,000 to 7,000 | 6,000 to 6,500 |

Sources: ([Cushman & Wakefield](https://assets.cushmanwakefield.com/-/media/cw/apac/india/insights/indiadatacentreupdateh12025v4.pdf?rev=4a5dd53b2388421ea3935afb03302def))

Crisil says Indian rents are 30 to 35% below peer markets and that contract tenors have lengthened to 15 to 20 years from 10 to 12 years. ([Deccan Herald](https://www.deccanherald.com/business/india-set-for-five-times-surge-in-its-data-centre-capacity-by-2030-4205631))

## Financing and state incentives

Data centres in India with at least 5 MW of IT load have had infrastructure status since 11 October 2022, which eases access to long-term credit; Anarock reports debt at about 9.5 to 10.5% for up to 12 years. State policies cut the effective cost further through capital subsidy, stamp duty exemption and electricity duty exemption: Uttar Pradesh’s 2026 policy, for example, exempts 100% of stamp duty on land bought or leased from a government authority and gives a 25% land subsidy on sector rates in the Paschimanchal region, which includes Gautam Buddha Nagar (Noida). ([Ministry of Finance, Department of Economic Affairs](https://www.pppinindia.gov.in/report/Harmonised%20Master%20list%20of%20Infrastruture%20sub%20sectors%202022_1685079764.pdf)) ([Anarock](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf)) ([Government of Uttar Pradesh](https://uplc.up.gov.in/downloadmedia/siteContent/202608230935077722DC-policy-2026-English_230826.pdf))

**Incentives:** [Infrastructure status, tax holiday and DC SEZs](https://invariant-ai.com/blog/data-centre-incentives-india-central) · [State data centre policies compared](https://invariant-ai.com/blog/data-centre-policy-india-state-comparison)

## How Invariant helps

Cost estimates move most with the power connection and the site. Invariant checks how a site gets power and what the connection depends on, screens seismic, flood, groundwater and airport height risk, and maps the approvals, so the capex model starts from the actual site. Send the state, the MW and the date you need power.

## More on data centres in India

**Start here:** [Data centres in India: capacity, cities, policy, power](https://invariant-ai.com/blog/data-centres-in-india) · [How to find a data centre site in India](https://invariant-ai.com/blog/find-data-centre-site-india) · [Data centre companies in India](https://invariant-ai.com/blog/data-centre-companies-india)

**Build and approvals:** [Approvals for a data centre in India](https://invariant-ai.com/blog/data-centre-approvals-india) · [How to set up a data centre in India](https://invariant-ai.com/blog/how-to-set-up-data-centre-india) · [Data centre cost per MW in India](https://invariant-ai.com/blog/data-centre-cost-per-mw-india) · [Site due diligence in India](https://invariant-ai.com/blog/data-centre-site-due-diligence-india) · [Data centre land and powered land in India](https://invariant-ai.com/blog/data-centre-land-india) · [Seismic zones, flood and cyclone risk](https://invariant-ai.com/blog/data-centre-seismic-flood-risk-india) · [Water and groundwater NOC for data centres](https://invariant-ai.com/blog/data-centre-water-india) · [DPDP Act and data localisation](https://invariant-ai.com/blog/dpdp-data-localisation-data-centres-india) · [Infrastructure status, tax holiday and DC SEZs](https://invariant-ai.com/blog/data-centre-incentives-india-central)

**Power:** [Power for data centres in India](https://invariant-ai.com/blog/power-for-data-centres-india) · [Grid connection: DISCOM, STU and CTU paths](https://invariant-ai.com/blog/data-centre-grid-connection-india) · [Green energy open access for data centres](https://invariant-ai.com/blog/green-energy-open-access-data-centres-india) · [Open access charges by state](https://invariant-ai.com/blog/open-access-charges-by-state-india) · [India data centre power demand to 2032](https://invariant-ai.com/blog/data-centre-power-demand-india) · [Power studies for Indian data centre sites](https://invariant-ai.com/blog/power-study-data-centre-india) · [Diesel generators and backup power rules](https://invariant-ai.com/blog/data-centre-backup-power-dg-sets-india)

**Policy by state:** [National data centre policy](https://invariant-ai.com/blog/national-data-centre-policy-india) · [State data centre policies compared](https://invariant-ai.com/blog/data-centre-policy-india-state-comparison) · [Maharashtra data centre policy](https://invariant-ai.com/blog/maharashtra-data-centre-policy) · [Uttar Pradesh data centre policy](https://invariant-ai.com/blog/uttar-pradesh-data-centre-policy) · [Tamil Nadu data centre policy](https://invariant-ai.com/blog/tamil-nadu-data-centre-policy) · [Telangana data centre policy](https://invariant-ai.com/blog/telangana-data-centre-policy) · [Gujarat data centre policy](https://invariant-ai.com/blog/gujarat-data-centre-policy) · [Karnataka data centre policy](https://invariant-ai.com/blog/karnataka-data-centre-policy) · [Andhra Pradesh data centre policy](https://invariant-ai.com/blog/andhra-pradesh-data-centre-policy) · [Haryana data centre policy](https://invariant-ai.com/blog/haryana-data-centre-policy) · [Rajasthan data centre policy](https://invariant-ai.com/blog/rajasthan-data-centre-policy) · [Odisha data centre policy](https://invariant-ai.com/blog/odisha-data-centre-policy) · [West Bengal data centre policy](https://invariant-ai.com/blog/west-bengal-data-centre-policy) · [Madhya Pradesh data centre policy](https://invariant-ai.com/blog/madhya-pradesh-data-centre-policy)

**Cities:** [Data centres in Mumbai and Navi Mumbai](https://invariant-ai.com/blog/data-centres-in-mumbai) · [Data centres in Chennai](https://invariant-ai.com/blog/data-centres-in-chennai) · [Data centres in Hyderabad](https://invariant-ai.com/blog/data-centres-in-hyderabad) · [Data centres in Noida and Delhi NCR](https://invariant-ai.com/blog/data-centres-in-noida) · [Data centres in Bengaluru](https://invariant-ai.com/blog/data-centres-in-bengaluru) · [Data centres in Pune](https://invariant-ai.com/blog/data-centres-in-pune) · [Data centres in Visakhapatnam](https://invariant-ai.com/blog/data-centres-in-visakhapatnam) · [Data centres in Gujarat: GIFT City, Ahmedabad, Jamnagar](https://invariant-ai.com/blog/data-centres-in-gujarat) · [Data centres in Kolkata and East India](https://invariant-ai.com/blog/data-centres-in-kolkata)

**Compare and invest:** [Mumbai vs Chennai vs Hyderabad](https://invariant-ai.com/blog/mumbai-vs-chennai-vs-hyderabad-data-centres) · [India vs Singapore vs Johor](https://invariant-ai.com/blog/india-vs-singapore-vs-johor-data-centres) · [AI data centres and IndiaAI GPUs](https://invariant-ai.com/blog/ai-data-centres-india) · [Data centre investment in India](https://invariant-ai.com/blog/data-centre-investment-india)

## Questions

### How much does it cost to build a data center in India per MW?

Building a data centre in India costs about US$7.4 million per MW on Cushman & Wakefield’s benchmark. SBI’s April 2026 sector report puts air-cooled Tier III at ₹50 to 55 crore per MW and AI with immersion cooling or Tier IV at up to ₹75 crore. Anarock prices land separately. ([Invest India and Cushman & Wakefield](https://static.investindia.gov.in/s3fs-public/2026-10/latest-news-India-Data-Centre-Growth-Story.pdf)) ([SBI CHAKRA](https://sbi.bank.in/documents/57189647/58231607/Sector+Report+DataCentre.pdf/f1919592-ee66-b50b-ea20-75fbb27c9bb5?t=1779885206866)) ([Anarock](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf))

### What is the cost of setting up a data centre in India?

SBI’s figures run from ₹35 to 45 crore per MW for large facilities to up to ₹75 crore for AI or Tier IV, and Anarock’s greenfield Tier III N+1 total runs from ₹40 to 45 crore to ₹65 to 70 crore per MW. Anarock prices land separately at ₹3 to 60 crore per acre across its size bands. ([Anarock](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf)) ([SBI CHAKRA](https://sbi.bank.in/documents/57189647/58231607/Sector+Report+DataCentre.pdf/f1919592-ee66-b50b-ea20-75fbb27c9bb5?t=1779885206866))

### How much does it cost to build a small data centre in India?

The published benchmarks are per MW and assume purpose-built facilities. Anarock’s smallest land band is 5 to 10 MW on 2 to 5 acres; at Tier III build costs of ₹50 to 55 crore per MW, even a 5 MW facility is a ₹250 crore plus project before land (our calculation). ([Anarock](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf)) ([SBI CHAKRA](https://sbi.bank.in/documents/57189647/58231607/Sector+Report+DataCentre.pdf/f1919592-ee66-b50b-ea20-75fbb27c9bb5?t=1779885206866))

### Is it cheaper to build a data centre in India than in Malaysia?

Cushman & Wakefield’s 2026 benchmark of US$7.4 million per MW is about 23% below Malaysia and 26% below Australia for a comparable specification. ([Invest India and Cushman & Wakefield](https://static.investindia.gov.in/s3fs-public/2026-10/latest-news-India-Data-Centre-Growth-Story.pdf))

### What is the colocation price per kW in India?

In H1 2025 Cushman & Wakefield quoted Mumbai colocation at ₹6,000 to 7,500 per kW per month for 5 MW and above, and ₹8,000 to 12,000 for deals under 250 kW. ([Cushman & Wakefield](https://assets.cushmanwakefield.com/-/media/cw/apac/india/insights/indiadatacentreupdateh12025v4.pdf?rev=4a5dd53b2388421ea3935afb03302def))

## Sources

- Invest India and Cushman & Wakefield: [India's Data Centre Growth Story (October 2026)](https://static.investindia.gov.in/s3fs-public/2026-10/latest-news-India-Data-Centre-Growth-Story.pdf)
- SBI CHAKRA: [Data Centres in India, sector report (April 2026)](https://sbi.bank.in/documents/57189647/58231607/Sector+Report+DataCentre.pdf/f1919592-ee66-b50b-ea20-75fbb27c9bb5?t=1779885206866)
- Anarock: [Data Centre: The Blueprint of the Digital Fortress in India (2026)](https://websitemedia.anarock.com/media/Data_centre_The_blueprint_of_the_digital_fortress_in_India_2026_b36407b0b2.pdf)
- Deccan Herald: [India set for five times surge in its data centre capacity by 2030 (Crisil Ratings, 3 November 2026)](https://www.deccanherald.com/business/india-set-for-five-times-surge-in-its-data-centre-capacity-by-2030-4205631)
- ICRA: [Third-party data centre capacity to double by FY2028](https://www.icra.in/CommonService/OpenMediaS3?Key=540ab708-7459-44fd-9680-82d127a4906a)
- Zee Business: [Amazon Data Services India acquires land from Lodha Developers](https://www.zeebiz.com/hindi/real-estate/amazon-data-services-india-has-acquired-approximately-42955-sq-meters-of-non-agricultural-land-from-lodha-developers-256535)
- Cushman & Wakefield: [India Data Centre Market Overview H1 2025 (rent tables)](https://assets.cushmanwakefield.com/-/media/cw/apac/india/insights/indiadatacentreupdateh12025v4.pdf?rev=4a5dd53b2388421ea3935afb03302def)
- Cushman & Wakefield: [India Data Centre Market Overview H1 2026](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b)
- Ministry of Finance, Department of Economic Affairs: [Harmonised Master List of Infrastructure Sub-sectors, notification of 11 October 2022](https://www.pppinindia.gov.in/report/Harmonised%20Master%20list%20of%20Infrastruture%20sub%20sectors%202022_1685079764.pdf)
- Government of Uttar Pradesh: [Uttar Pradesh Data Center Policy 2026 (G.O. dated 9 July 2026)](https://uplc.up.gov.in/downloadmedia/siteContent/202608230935077722DC-policy-2026-English_230826.pdf)

## Related

- [Data centre land in India: acres per MW, land prices and powered land (2026)](https://invariant-ai.com/blog/data-centre-land-india)
- [How to set up a data centre in India: from entity to energisation (2026)](https://invariant-ai.com/blog/how-to-set-up-data-centre-india)
- [Data centre investment in India: hyperscaler commitments and deals (2026)](https://invariant-ai.com/blog/data-centre-investment-india)
- [Data centre incentives in India: infrastructure status, tax holiday and SEZs (2026)](https://invariant-ai.com/blog/data-centre-incentives-india-central)
- [India vs Singapore vs Johor for data centres: power, policy and cost (2026)](https://invariant-ai.com/blog/india-vs-singapore-vs-johor-data-centres)

---

[Email your India data centre project requirements](mailto:pranav@invariant-ai.com) · [Book a call](https://cal.com/pranav-goswami/website-30min)