# Data centre incentives in India: infrastructure status, tax holiday and SEZs (2026)

> Central data centre incentives in India: infrastructure status for 5 MW+ IT load since October 2022, a tax holiday to 2047 for cloud services, FDI and SEZ rules.

URL: https://invariant-ai.com/blog/data-centre-incentives-india-central  
Published: 2026-11-21 · Publisher: Invariant · Region: India

India’s data centre tax holiday benefits foreign cloud companies, not Indian operators: from tax year 2026-27 to tax year 2046-47, foreign companies that provide cloud services globally using data centre services procured in India are exempt from Indian tax on that income, while profits of the Indian data centre company and the reseller remain taxable, according to the government backgrounder. Since 11 October 2022, an Indian data centre with a minimum capacity of 5 MW of IT load has also had infrastructure status. The exemption comes from the Finance Act 2026; the Taxation and Other Laws (Amendment) Act 2026, which received assent on 17 August 2026, eased its conditions.

## Key points

- Infrastructure status, notified on 11 October 2022, needs a dedicated or centralised building and a minimum capacity of 5 MW of IT load.
- The tax holiday benefits the foreign cloud company; profits of the Indian data centre company and the reseller remain taxable, according to the government backgrounder.
- The Taxation and Other Laws (Amendment) Act 2026, which received assent on 17 August 2026, drops the notification and approved-scheme conditions and extends the holiday to data centres leased and operated by an Indian company.
- The SEZ land relaxations in effect from 3 June 2025 cover semiconductor and electronic component manufacturing; data centres are not among the listed sectors.

## Central data centre incentives in India at a glance

| Incentive | What it gives | Who qualifies | Status |
| --- | --- | --- | --- |
| Infrastructure status | Easier access to institutional credit at lower rates (PTI report) | Data centre in a dedicated or centralised building, minimum 5 MW of IT load | Notified 11 October 2022 |
| Tax holiday | Exemption on a foreign company’s income from data centre services procured in India | Foreign cloud company that does not own or operate the facility and sells to Indian users through an Indian reseller | Tax years 2026-27 to 2046-47 |
| Safe harbour | 15% margin on cost where the Indian data centre provider is a related entity | Related-party data centre services | Proposed in Budget 2026-27 |
| Foreign investment | 100% under the automatic route | Companies engaged only in the data centre business; investors from listed restricted countries such as China need prior approval | Law-firm reading of the FDI policy |
| SEZ land relaxation | Minimum land requirement cut from 50 hectares to 10 hectares | Semiconductor and electronic component manufacturing units | Data centres not among the listed sectors |

Sources: ([Ministry of Finance, Department of Economic Affairs](https://www.pppinindia.gov.in/report/Harmonised%20Master%20list%20of%20Infrastruture%20sub%20sectors%202022_1685079764.pdf)) ([The Tribune (PTI)](https://www.tribuneindia.com/news/business/infra-status-to-data-centres-with-over-5mw-capacity-441160)) ([PIB, Ministry of Electronics and IT](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2221894)) ([S&R Associates](https://www.snrlaw.in/indian-budget-2026-27-tax-incentives-for-data-centres/)) ([Khaitan & Co](https://www.khaitanco.com/sites/default/files/2024-08/Data%20Centres%20in%20India_%20A%20Legal%20Outlook%20for%20Emerging%20Asset%20-%20Lexology.pdf)) ([Business Standard](https://www.business-standard.com/economy/news/govt-eases-sez-rules-to-promote-chips-electronics-component-manufacturing-125060401259_1.html))

## Infrastructure status for data centres under the Harmonised Master List

The Ministry of Finance added data centres to the Harmonised Master List of Infrastructure Sub-sectors, under Communication, by a notification dated 11 October 2022. The entry covers a "Data Centre housed in a dedicated/centralized building for storage and processing of digital data applications with a minimum capacity of 5 MW of IT load." ([Ministry of Finance, Department of Economic Affairs](https://www.pppinindia.gov.in/report/Harmonised%20Master%20list%20of%20Infrastruture%20sub%20sectors%202022_1685079764.pdf))

According to a PTI report at the time, the move helps data centre companies get easier access to institutional credit at lower rates and attract foreign investment. ([The Tribune (PTI)](https://www.tribuneindia.com/news/business/infra-status-to-data-centres-with-over-5mw-capacity-441160))

## The tax holiday to 2047 for cloud services delivered from India

The Budget of 1 February 2026 proposed a tax holiday till 2047 for foreign companies providing cloud services to customers globally using data centre services from India, with services to Indian customers provided through an Indian reseller entity. It also proposed a safe harbour of 15% on cost where the Indian data centre service provider is a related entity. Electronics and IT Minister Ashwini Vaishnaw said investments of around USD 70 billion were underway and around USD 90 billion had been announced. ([PIB, Ministry of Electronics and IT](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2221894))

The government backgrounder sets the window at tax year 2026-27 to tax year 2046-47 and says profits from domestic activity, including data centre services provided by the resident Indian data centre company and resale by the Indian reseller, remain taxable. ([PIB](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2227953))

The Finance Act 2026, notified on 30 March 2026, exempts a foreign company’s income "by way of procuring data centre services from a specified data centre", if the foreign company is notified by the central government, does not own or operate the physical infrastructure or resources of the data centre, sells to users in India only through an Indian reseller company and furnishes prescribed information. A specified data centre had to be set up under an approved scheme, notified by MeitY, and owned and operated by an Indian company. ([S&R Associates](https://www.snrlaw.in/indian-budget-2026-27-tax-incentives-for-data-centres/))

The Taxation and Other Laws (Amendment) Bill, 2026 passed the Lok Sabha on 6 August and the Rajya Sabha on 10 August 2026, and received the President’s assent on 17 August 2026. It removes the conditions that the foreign company be notified and that the data centre be set up under an approved scheme and notified, and extends the exemption to data centres leased and operated by an Indian company. Check any rules or schemes issued under it before relying on the amended conditions. ([PRS Legislative Research](https://prsindia.org/billtrack/the-taxation-and-other-laws-amendment-bill-2026)) ([Outlook Business (PTI)](https://www.outlookbusiness.com/economy-and-policy/amendment-to-taxation-act-payment-and-settlement-systems-act-get-presidents-assent))

## Foreign investment (FDI) rules for data centres

Khaitan & Co reads India’s FDI policy as allowing 100% foreign investment under the automatic route in Indian companies or LLPs engaged only in the data centre business. If the company is also in other businesses, for example owning fibre assets, the investment conditions for those sectors apply as well. S&R Associates notes that investors from restricted countries (Pakistan, Afghanistan, Nepal, Bhutan, China including Hong Kong, Bangladesh and Myanmar) need prior government approval. ([Khaitan & Co](https://www.khaitanco.com/sites/default/files/2024-08/Data%20Centres%20in%20India_%20A%20Legal%20Outlook%20for%20Emerging%20Asset%20-%20Lexology.pdf)) ([S&R Associates](https://www.snrlaw.in/indian-budget-2026-27-tax-incentives-for-data-centres/))

## SEZ rules, GIFT City and data embassies

The SEZ (Amendment) Rules 2025, in effect from 3 June 2025, cut the minimum land requirement for semiconductor and electronic component manufacturing units in SEZs from 50 hectares to 10 hectares. The sectors listed, such as semiconductors, printed circuit boards, lithium-ion cells and IT hardware components, do not include data centres. ([Business Standard](https://www.business-standard.com/economy/news/govt-eases-sez-rules-to-promote-chips-electronics-component-manufacturing-125060401259_1.html))

In the Budget 2023-24 speech the Finance Minister said that, for countries looking for digital continuity solutions, the government would facilitate data embassies in GIFT IFSC. DD India reports that Gujarat’s 2026 data centre policy document highlights Dholera and GIFT City among the state’s industrial hubs. ([Inc42](https://inc42.com/buzz/union-budget-2023-24-govt-to-facilitate-setting-up-data-embassies-in-ifsc-gift-city/)) ([DD India](https://ddindia.co.in/2026/07/gujarat-launches-data-centre-policy-2026-29-to-attract-investment-build-digital-infrastructure-hub/))

**State incentives:** [State data centre policies compared](https://invariant-ai.com/blog/data-centre-policy-india-state-comparison) · [Gujarat data centre policy](https://invariant-ai.com/blog/gujarat-data-centre-policy) · [Uttar Pradesh data centre policy](https://invariant-ai.com/blog/uttar-pradesh-data-centre-policy) · [Maharashtra data centre policy](https://invariant-ai.com/blog/maharashtra-data-centre-policy)

For a site in India, Invariant checks how it gets power and the evidence behind that path (the distribution or transmission connection, the open access route, the nearest substations), screens seismic zone, flood history, groundwater status and airport height limits, and maps the central and state approvals the project needs, with the authority behind each one.

## More on data centres in India

**Start here:** [Data centres in India: capacity, cities, policy, power](https://invariant-ai.com/blog/data-centres-in-india) · [How to find a data centre site in India](https://invariant-ai.com/blog/find-data-centre-site-india) · [Data centre companies in India](https://invariant-ai.com/blog/data-centre-companies-india)

**Build and approvals:** [Approvals for a data centre in India](https://invariant-ai.com/blog/data-centre-approvals-india) · [How to set up a data centre in India](https://invariant-ai.com/blog/how-to-set-up-data-centre-india) · [Data centre cost per MW in India](https://invariant-ai.com/blog/data-centre-cost-per-mw-india) · [Site due diligence in India](https://invariant-ai.com/blog/data-centre-site-due-diligence-india) · [Data centre land and powered land in India](https://invariant-ai.com/blog/data-centre-land-india) · [Seismic zones, flood and cyclone risk](https://invariant-ai.com/blog/data-centre-seismic-flood-risk-india) · [Water and groundwater NOC for data centres](https://invariant-ai.com/blog/data-centre-water-india) · [DPDP Act and data localisation](https://invariant-ai.com/blog/dpdp-data-localisation-data-centres-india) · [Infrastructure status, tax holiday and DC SEZs](https://invariant-ai.com/blog/data-centre-incentives-india-central)

**Power:** [Power for data centres in India](https://invariant-ai.com/blog/power-for-data-centres-india) · [Grid connection: DISCOM, STU and CTU paths](https://invariant-ai.com/blog/data-centre-grid-connection-india) · [Green energy open access for data centres](https://invariant-ai.com/blog/green-energy-open-access-data-centres-india) · [Open access charges by state](https://invariant-ai.com/blog/open-access-charges-by-state-india) · [India data centre power demand to 2032](https://invariant-ai.com/blog/data-centre-power-demand-india) · [Power studies for Indian data centre sites](https://invariant-ai.com/blog/power-study-data-centre-india) · [Diesel generators and backup power rules](https://invariant-ai.com/blog/data-centre-backup-power-dg-sets-india)

**Policy by state:** [National data centre policy](https://invariant-ai.com/blog/national-data-centre-policy-india) · [State data centre policies compared](https://invariant-ai.com/blog/data-centre-policy-india-state-comparison) · [Maharashtra data centre policy](https://invariant-ai.com/blog/maharashtra-data-centre-policy) · [Uttar Pradesh data centre policy](https://invariant-ai.com/blog/uttar-pradesh-data-centre-policy) · [Tamil Nadu data centre policy](https://invariant-ai.com/blog/tamil-nadu-data-centre-policy) · [Telangana data centre policy](https://invariant-ai.com/blog/telangana-data-centre-policy) · [Gujarat data centre policy](https://invariant-ai.com/blog/gujarat-data-centre-policy) · [Karnataka data centre policy](https://invariant-ai.com/blog/karnataka-data-centre-policy) · [Andhra Pradesh data centre policy](https://invariant-ai.com/blog/andhra-pradesh-data-centre-policy) · [Haryana data centre policy](https://invariant-ai.com/blog/haryana-data-centre-policy) · [Rajasthan data centre policy](https://invariant-ai.com/blog/rajasthan-data-centre-policy) · [Odisha data centre policy](https://invariant-ai.com/blog/odisha-data-centre-policy) · [West Bengal data centre policy](https://invariant-ai.com/blog/west-bengal-data-centre-policy) · [Madhya Pradesh data centre policy](https://invariant-ai.com/blog/madhya-pradesh-data-centre-policy)

**Cities:** [Data centres in Mumbai and Navi Mumbai](https://invariant-ai.com/blog/data-centres-in-mumbai) · [Data centres in Chennai](https://invariant-ai.com/blog/data-centres-in-chennai) · [Data centres in Hyderabad](https://invariant-ai.com/blog/data-centres-in-hyderabad) · [Data centres in Noida and Delhi NCR](https://invariant-ai.com/blog/data-centres-in-noida) · [Data centres in Bengaluru](https://invariant-ai.com/blog/data-centres-in-bengaluru) · [Data centres in Pune](https://invariant-ai.com/blog/data-centres-in-pune) · [Data centres in Visakhapatnam](https://invariant-ai.com/blog/data-centres-in-visakhapatnam) · [Data centres in Gujarat: GIFT City, Ahmedabad, Jamnagar](https://invariant-ai.com/blog/data-centres-in-gujarat) · [Data centres in Kolkata and East India](https://invariant-ai.com/blog/data-centres-in-kolkata)

**Compare and invest:** [Mumbai vs Chennai vs Hyderabad](https://invariant-ai.com/blog/mumbai-vs-chennai-vs-hyderabad-data-centres) · [India vs Singapore vs Johor](https://invariant-ai.com/blog/india-vs-singapore-vs-johor-data-centres) · [AI data centres and IndiaAI GPUs](https://invariant-ai.com/blog/ai-data-centres-india) · [Data centre investment in India](https://invariant-ai.com/blog/data-centre-investment-india)

## Questions

### Do data centres have infrastructure status in India?

Yes, since 11 October 2022, if the data centre is housed in a dedicated or centralised building and has a minimum capacity of 5 MW of IT load. ([Ministry of Finance, Department of Economic Affairs](https://www.pppinindia.gov.in/report/Harmonised%20Master%20list%20of%20Infrastruture%20sub%20sectors%202022_1685079764.pdf))

### What is the data centre tax holiday till 2047?

The tax holiday is an exemption, from tax year 2026-27 to tax year 2046-47, for foreign companies that provide cloud services globally using data centre services procured in India. Indian customers must be served through an Indian reseller. ([PIB](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2227953)) ([S&R Associates](https://www.snrlaw.in/indian-budget-2026-27-tax-incentives-for-data-centres/))

### Does the tax holiday cover an Indian data centre operator’s profits?

No. The government backgrounder says profits of the resident Indian data centre company and the Indian reseller remain taxable as for any other domestic company. ([PIB](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2227953))

### What changed in the August 2026 amendment to the data centre tax holiday?

The amendment removes the notification and approved-scheme conditions and extends the exemption to data centres leased and operated, not only owned and operated, by an Indian company. The Taxation and Other Laws (Amendment) Act 2026 received assent on 17 August 2026. ([PRS Legislative Research](https://prsindia.org/billtrack/the-taxation-and-other-laws-amendment-bill-2026)) ([Outlook Business (PTI)](https://www.outlookbusiness.com/economy-and-policy/amendment-to-taxation-act-payment-and-settlement-systems-act-get-presidents-assent))

### Is 100% FDI allowed in data centres in India?

Law firms read the FDI policy as allowing 100% foreign investment under the automatic route for companies engaged only in the data centre business. Investors from listed restricted countries such as China need prior government approval. ([Khaitan & Co](https://www.khaitanco.com/sites/default/files/2024-08/Data%20Centres%20in%20India_%20A%20Legal%20Outlook%20for%20Emerging%20Asset%20-%20Lexology.pdf)) ([S&R Associates](https://www.snrlaw.in/indian-budget-2026-27-tax-incentives-for-data-centres/))

### Do the 2025 SEZ land relaxations apply to data centres?

No. The SEZ (Amendment) Rules 2025 cut the minimum land requirement from 50 hectares to 10 hectares for semiconductor and electronic component manufacturing units, and data centres are not among the listed sectors. ([Business Standard](https://www.business-standard.com/economy/news/govt-eases-sez-rules-to-promote-chips-electronics-component-manufacturing-125060401259_1.html))

## Sources

- Ministry of Finance, Department of Economic Affairs: [Harmonised Master List of Infrastructure Sub-sectors, notification of 11 October 2022](https://www.pppinindia.gov.in/report/Harmonised%20Master%20list%20of%20Infrastruture%20sub%20sectors%202022_1685079764.pdf)
- The Tribune (PTI): [Infra status to data centres with over 5 MW capacity](https://www.tribuneindia.com/news/business/infra-status-to-data-centres-with-over-5mw-capacity-441160)
- PIB, Ministry of Electronics and IT: [Union Budget 2026-27: tax holiday for cloud services using data centres in India](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2221894)
- PIB: [Backgrounder: tax holiday for cloud and AI infrastructure](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2227953)
- S&R Associates: [Indian Budget 2026-27: tax incentives for data centres](https://www.snrlaw.in/indian-budget-2026-27-tax-incentives-for-data-centres/)
- PRS Legislative Research: [The Taxation and Other Laws (Amendment) Bill, 2026](https://prsindia.org/billtrack/the-taxation-and-other-laws-amendment-bill-2026)
- Outlook Business (PTI): [Amendment to Taxation Act, Payment and Settlement Systems Act get President's assent](https://www.outlookbusiness.com/economy-and-policy/amendment-to-taxation-act-payment-and-settlement-systems-act-get-presidents-assent)
- Khaitan & Co: [Data centres in India: a legal outlook for an emerging asset](https://www.khaitanco.com/sites/default/files/2024-08/Data%20Centres%20in%20India_%20A%20Legal%20Outlook%20for%20Emerging%20Asset%20-%20Lexology.pdf)
- Business Standard: [Government eases SEZ rules to promote chips and electronics component manufacturing](https://www.business-standard.com/economy/news/govt-eases-sez-rules-to-promote-chips-electronics-component-manufacturing-125060401259_1.html)
- Inc42: [Union Budget 2023-24: government to facilitate data embassies in GIFT City](https://inc42.com/buzz/union-budget-2023-24-govt-to-facilitate-setting-up-data-embassies-in-ifsc-gift-city/)
- DD India: [Gujarat launches Data Centre Policy 2026-29](https://ddindia.co.in/2026/07/gujarat-launches-data-centre-policy-2026-29-to-attract-investment-build-digital-infrastructure-hub/)

## Related

- [National data centre policy in India: the 2020 draft and what applies now (2026)](https://invariant-ai.com/blog/national-data-centre-policy-india)
- [Data centre policy in India: state data centre policies compared (2026)](https://invariant-ai.com/blog/data-centre-policy-india-state-comparison)
- [DPDP Act and data localisation: what it means for data centres in India (2026)](https://invariant-ai.com/blog/dpdp-data-localisation-data-centres-india)
- [Data centre investment in India: hyperscaler commitments and deals (2026)](https://invariant-ai.com/blog/data-centre-investment-india)
- [Data centres in India: capacity, cities, companies, policy and power (2026)](https://invariant-ai.com/blog/data-centres-in-india)

---

[Email your India data centre project requirements](mailto:pranav@invariant-ai.com) · [Book a call](https://cal.com/pranav-goswami/website-30min)