# Data centres in Kolkata and East India: New Town, Salt Lake and Bhubaneswar (2026)

> Kolkata had 22 MW of operational data centre capacity in H1 2026, mostly in New Town, per Cushman & Wakefield. West Bengal’s 2021 policy term ran to September 2026.

URL: https://invariant-ai.com/blog/data-centres-in-kolkata  
Published: 2026-11-21 · Publisher: Invariant · Region: Kolkata, West Bengal, India

Kolkata had 22 MW of operational data centre capacity across six facilities in H1 2026, the smallest of the seven city markets in Cushman & Wakefield’s count. New Town holds 18 MW and Salt Lake 4 MW, with 13 MW under construction and 71 MW planned; demand comes mainly from government and small and medium enterprises. West Bengal’s Data Centre Policy 2021 classed data centre organisations as essential services and treated their electricity as industrial. It was valid for five years from September 2021, and in May 2026 the state BJP president said the new government was formulating a new data centre policy. Odisha’s 2022 policy is another incentive regime in the region.

## Key points

- Kolkata had 22 MW operational, 13 MW under construction and 71 MW planned in H1 2026, with 19.4% colocation vacancy, according to Cushman & Wakefield.
- In Kolkata, New Town holds 18 MW and Salt Lake 4 MW. Cushman & Wakefield reports a cable landing station under construction at Tajpur.
- West Bengal Data Centre Policy 2021 (notified 6 September 2021): essential services classification, 100% stamp duty exemption, 5-year electricity duty waiver, FAR 3.0 plus 1.0 purchasable.
- The central government named West Bengal, with Andhra Pradesh, Madhya Pradesh and Chhattisgarh, among states coming up as new data centre investment destinations.

## Kolkata data centre market: key facts (H1 2026)

| Item | Figure and period |
| --- | --- |
| Operational capacity | 22 MW in 6 data centres, about 2% of India’s operational capacity (Cushman & Wakefield, H1 2026) |
| Under construction and planned | 13 MW under construction; 71 MW planned |
| Colocation vacancy | 19.4% |
| Sub-markets | New Town 18 MW; Salt Lake 4 MW |
| Cables | Cushman & Wakefield reports a cable landing station under construction at Tajpur |
| State policy | West Bengal Data Centre Policy 2021, valid five years from 6 September 2021 or until replaced; new policy being formulated (May 2026 statement) |
| Physical risk note | Seismic Zone III |

Sources: ([Cushman & Wakefield](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b)) ([Government of West Bengal (via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/)) ([Business Standard](https://www.business-standard.com/politics/bengal-govt-working-on-land-data-centre-policies-bengal-bjp-president-126052501625_1.html)) ([Bureau of Indian Standards](https://law.resource.org/pub/in/bis/S03/is.1893.1.2002.pdf))

Cushman & Wakefield attributes Kolkata’s demand primarily to government and small and medium enterprises, and says the under-construction Tajpur cable landing station is attracting large operators. ([Cushman & Wakefield](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b))

## Kolkata data centre sub-markets and operators

New Town holds most of Kolkata’s data centre capacity (18 MW of 22 MW), with Salt Lake at 4 MW, according to Cushman & Wakefield. W.Media reported in February 2025 that NTT Global Data Centers had inaugurated its Kolkata data centre. In August 2026 the government told the Rajya Sabha that the data centre industry is expanding in states including West Bengal, Andhra Pradesh, Madhya Pradesh and Chhattisgarh. ([Cushman & Wakefield](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b)) ([W.Media](https://w.media/ntt-global-data-centers-inaugurates-kolkata-dc/)) ([Press Information Bureau (MeitY)](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2298108))

## West Bengal Data Centre Policy 2021 and its replacement

- The West Bengal Data Centre Policy 2021 was issued under Notification No. 490-Estt/ITE-18011/2/2021 dated 6 September 2021, operative for five years or until replaced.
- 100% stamp duty and registration fee exemption; electricity duty waiver for five years from commercial operation; data centre electricity treated as industrial.
- Dual power grid networks; FAR of 3.0 plus 1.0 purchasable and up to 60% ground coverage; self-certification under notified Acts.
- Clause 5.3: data centre organisations classified as essential services.

Sources: ([Government of West Bengal (via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/))

The 2021 policy’s five-year term ran to September 2026. In May 2026 the West Bengal BJP president, Samik Bhattacharya, said the new government was formulating a new data centre policy, as reported by Business Standard. Until it is notified, check with the IT and Electronics Department and Webel which terms apply to a new project. ([Government of West Bengal (via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/)) ([Business Standard](https://www.business-standard.com/politics/bengal-govt-working-on-land-data-centre-policies-bengal-bjp-president-126052501625_1.html))

## East India beyond Kolkata: Odisha and Bhubaneswar

Odisha’s State Data Centre Policy 2022, with OCAC as nodal agency, offers a capital subsidy of 20% of fixed capital investment (excluding land) up to Rs 25 crore per unit. It also gives a 100% stamp duty exemption on the first transaction, electricity duty and inspection fee exemption for 10 years up to 5 MVA, a 30% power bill subsidy for 5 years up to Rs 2 crore, net SGST reimbursement for 7 years, and reimbursement of transmission and wheeling charges on captive renewable power. Yotta lists Bhubaneswar among its planned edge data centre cities. ([Invest Odisha](https://investodisha.gov.in/datacentre-policy)) ([Yotta](https://yotta.com/data-center-in-india/))

## Site risks for data centres in Kolkata

- Seismic: Kolkata is Zone III (zone factor 0.16) under IS 1893 (Part 1):2002 as amended in 2005.
- Flood: check drainage and plot elevation on low-lying land.
- Airport: AAI height clearance applies within 20 km of the aerodrome reference point for visual flight rules airports, or 56 km for instrument flight rules airports.

Sources: ([Bureau of Indian Standards](https://law.resource.org/pub/in/bis/S03/is.1893.1.2002.pdf)) ([Airports Authority of India](https://nocas2.aai.aero/nocas/FAQ.html))

Invariant checks the evidence behind a site’s power (the DISCOM or transmission connection, the open access route, the nearest substations and what else is queued on them), screens seismic zone, flood history, groundwater status and airport height limits, and lists the central and state approvals the project needs with the authority behind each one. In Kolkata the policy status and the substation serving New Town are the first two checks.

## More on data centres in India

**Start here:** [Data centres in India: capacity, cities, policy, power](https://invariant-ai.com/blog/data-centres-in-india) · [How to find a data centre site in India](https://invariant-ai.com/blog/find-data-centre-site-india) · [Data centre companies in India](https://invariant-ai.com/blog/data-centre-companies-india)

**Build and approvals:** [Approvals for a data centre in India](https://invariant-ai.com/blog/data-centre-approvals-india) · [How to set up a data centre in India](https://invariant-ai.com/blog/how-to-set-up-data-centre-india) · [Data centre cost per MW in India](https://invariant-ai.com/blog/data-centre-cost-per-mw-india) · [Site due diligence in India](https://invariant-ai.com/blog/data-centre-site-due-diligence-india) · [Data centre land and powered land in India](https://invariant-ai.com/blog/data-centre-land-india) · [Seismic zones, flood and cyclone risk](https://invariant-ai.com/blog/data-centre-seismic-flood-risk-india) · [Water and groundwater NOC for data centres](https://invariant-ai.com/blog/data-centre-water-india) · [DPDP Act and data localisation](https://invariant-ai.com/blog/dpdp-data-localisation-data-centres-india) · [Infrastructure status, tax holiday and DC SEZs](https://invariant-ai.com/blog/data-centre-incentives-india-central)

**Power:** [Power for data centres in India](https://invariant-ai.com/blog/power-for-data-centres-india) · [Grid connection: DISCOM, STU and CTU paths](https://invariant-ai.com/blog/data-centre-grid-connection-india) · [Green energy open access for data centres](https://invariant-ai.com/blog/green-energy-open-access-data-centres-india) · [Open access charges by state](https://invariant-ai.com/blog/open-access-charges-by-state-india) · [India data centre power demand to 2032](https://invariant-ai.com/blog/data-centre-power-demand-india) · [Power studies for Indian data centre sites](https://invariant-ai.com/blog/power-study-data-centre-india) · [Diesel generators and backup power rules](https://invariant-ai.com/blog/data-centre-backup-power-dg-sets-india)

**Policy by state:** [National data centre policy](https://invariant-ai.com/blog/national-data-centre-policy-india) · [State data centre policies compared](https://invariant-ai.com/blog/data-centre-policy-india-state-comparison) · [Maharashtra data centre policy](https://invariant-ai.com/blog/maharashtra-data-centre-policy) · [Uttar Pradesh data centre policy](https://invariant-ai.com/blog/uttar-pradesh-data-centre-policy) · [Tamil Nadu data centre policy](https://invariant-ai.com/blog/tamil-nadu-data-centre-policy) · [Telangana data centre policy](https://invariant-ai.com/blog/telangana-data-centre-policy) · [Gujarat data centre policy](https://invariant-ai.com/blog/gujarat-data-centre-policy) · [Karnataka data centre policy](https://invariant-ai.com/blog/karnataka-data-centre-policy) · [Andhra Pradesh data centre policy](https://invariant-ai.com/blog/andhra-pradesh-data-centre-policy) · [Haryana data centre policy](https://invariant-ai.com/blog/haryana-data-centre-policy) · [Rajasthan data centre policy](https://invariant-ai.com/blog/rajasthan-data-centre-policy) · [Odisha data centre policy](https://invariant-ai.com/blog/odisha-data-centre-policy) · [West Bengal data centre policy](https://invariant-ai.com/blog/west-bengal-data-centre-policy) · [Madhya Pradesh data centre policy](https://invariant-ai.com/blog/madhya-pradesh-data-centre-policy)

**Cities:** [Data centres in Mumbai and Navi Mumbai](https://invariant-ai.com/blog/data-centres-in-mumbai) · [Data centres in Chennai](https://invariant-ai.com/blog/data-centres-in-chennai) · [Data centres in Hyderabad](https://invariant-ai.com/blog/data-centres-in-hyderabad) · [Data centres in Noida and Delhi NCR](https://invariant-ai.com/blog/data-centres-in-noida) · [Data centres in Bengaluru](https://invariant-ai.com/blog/data-centres-in-bengaluru) · [Data centres in Pune](https://invariant-ai.com/blog/data-centres-in-pune) · [Data centres in Visakhapatnam](https://invariant-ai.com/blog/data-centres-in-visakhapatnam) · [Data centres in Gujarat: GIFT City, Ahmedabad, Jamnagar](https://invariant-ai.com/blog/data-centres-in-gujarat) · [Data centres in Kolkata and East India](https://invariant-ai.com/blog/data-centres-in-kolkata)

**Compare and invest:** [Mumbai vs Chennai vs Hyderabad](https://invariant-ai.com/blog/mumbai-vs-chennai-vs-hyderabad-data-centres) · [India vs Singapore vs Johor](https://invariant-ai.com/blog/india-vs-singapore-vs-johor-data-centres) · [AI data centres and IndiaAI GPUs](https://invariant-ai.com/blog/ai-data-centres-india) · [Data centre investment in India](https://invariant-ai.com/blog/data-centre-investment-india)

## Questions

### How much data centre capacity does Kolkata have?

Kolkata had 22 MW of operational data centre capacity in H1 2026 across six facilities, according to Cushman & Wakefield, with 13 MW under construction and 71 MW planned. ([Cushman & Wakefield](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b))

### Where are the data centres in Kolkata?

Kolkata’s data centres are in New Town (18 MW) and Salt Lake (4 MW), according to Cushman & Wakefield. ([Cushman & Wakefield](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b))

### Is the West Bengal data centre policy still valid?

The West Bengal Data Centre Policy 2021 was valid for five years from 6 September 2021 or until replaced, so its term ran to September 2026. In May 2026 the state BJP president said the new government was formulating a new policy; confirm current terms before relying on them. ([Government of West Bengal (via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/)) ([Business Standard](https://www.business-standard.com/politics/bengal-govt-working-on-land-data-centre-policies-bengal-bjp-president-126052501625_1.html))

### Is Kolkata a good place for a data center?

Kolkata is a small market, with 22 MW operational in H1 2026 and demand driven mainly by government and small and medium enterprises, according to Cushman & Wakefield. Large loads will want confirmed policy terms and a named substation first. ([Cushman & Wakefield](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b))

### Are data centres essential services in West Bengal?

Under the West Bengal Data Centre Policy 2021, yes: Clause 5.3 classifies data centre organisations under essential services. The policy’s five-year term ran to September 2026, so check whether any replacement policy keeps this. ([Government of West Bengal (via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/))

## Sources

- Cushman & Wakefield: [India Data Centre Market Overview H1 2026](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b)
- Government of West Bengal (via wbxpress): [West Bengal Data Centre Policy 2021 (Notification 490-Estt/ITE-18011/2/2021)](https://wbxpress.com/west-bengal-data-centre-policy-2021/)
- Business Standard: [Bengal govt working on land, data centre policies](https://www.business-standard.com/politics/bengal-govt-working-on-land-data-centre-policies-bengal-bjp-president-126052501625_1.html)
- Bureau of Indian Standards: [IS 1893 (Part 1):2002, criteria for earthquake resistant design, Annex E zone factors](https://law.resource.org/pub/in/bis/S03/is.1893.1.2002.pdf)
- W.Media: [NTT Global Data Centers inaugurates Kolkata data center](https://w.media/ntt-global-data-centers-inaugurates-kolkata-dc/)
- Press Information Bureau (MeitY): [Data centre capacity and power demand: reply in the Rajya Sabha](https://www.pib.gov.in/PressReleasePage.aspx?PRID=2298108)
- Invest Odisha: [Odisha State Data Centre Policy 2022](https://investodisha.gov.in/datacentre-policy)
- Yotta: [Data centers in India](https://yotta.com/data-center-in-india/)
- Airports Authority of India: [NOCAS frequently asked questions (height clearance under GSR 751(E))](https://nocas2.aai.aero/nocas/FAQ.html)

## Related

- [Data centres in India: capacity, cities, companies, policy and power (2026)](https://invariant-ai.com/blog/data-centres-in-india)
- [West Bengal data centre policy 2021: incentives, essential services and status](https://invariant-ai.com/blog/west-bengal-data-centre-policy)
- [Odisha data centre policy 2022: capital subsidy, power subsidy and SGST refund](https://invariant-ai.com/blog/odisha-data-centre-policy)
- [Power for data centres in India: grid supply, open access and tariffs by state](https://invariant-ai.com/blog/power-for-data-centres-india)

---

[Email your India data centre project requirements](mailto:pranav@invariant-ai.com) · [Book a call](https://cal.com/pranav-goswami/website-30min)