  "title": "Richland Parish compute, generation and interconnection milestones",
  "publisher": "Invariant",
  "checked_on": "2026-11-24",
  "sources": {
    "evest-sec": {
      "title": "Entergy 2026 third-quarter Form 10-Q, Additional Generation and Transmission Resources",
      "publisher": "Entergy Louisiana / SEC",
      "url": "https://www.sec.gov/Archives/edgar/data/1427437/000006598426000325/etr-20260930.htm"
    },
    "evest-staff-brief": {
      "title": "November 12, 2026 LPSC staff brief, U-37882. Relief requested and transmission schedule",
      "publisher": "Louisiana Public Service Commission Staff",
      "url": "https://lpscpubvalence.lpsc.louisiana.gov/portal/PSC/ViewFile?fileId=hCRlbfVTXns%3D"
    },
    "evest-procedural-order": {
      "title": "U-37882 procedural order directing the December 16, 2026 consideration schedule",
      "publisher": "Louisiana Public Service Commission",
      "url": "https://lpscpubvalence.lpsc.louisiana.gov/portal/PSC/DocumentDetails?documentId=180141"
    },
    "evest-docket": {
      "title": "U-37882 public docket and certification filing",
      "publisher": "Louisiana Public Service Commission",
      "url": "https://lpscpubvalence.lpsc.louisiana.gov/portal/PSC/DocketDetails?docketId=32728"
    },
    "laidley-order": {
      "title": "U-37425 order dated August 29, 2025 on the original North Louisiana project",
      "publisher": "Louisiana Public Service Commission",
      "url": "https://lpscpubvalence.lpsc.louisiana.gov/portal/PSC/DocumentDetails?documentId=176967"
    },
    "hyperion": {
      "title": "July 13, 2026 Richland Parish expansion announcement",
      "publisher": "Meta",
      "url": "https://about.fb.com/news/2026/07/teachers-local-businesses-win-as-meta-expands-louisiana-data-center/"
    }
  },
  "comparison": [
    {
      "record_date": "2025-08-29",
      "scope": "Original Laidley project",
      "record_type": "Final infrastructure approval order",
      "docket": "U-37425",
      "source_id": "laidley-order"
    },
    {
      "record_date": "2026-03",
      "scope": "Adjacent Evest project",
      "record_type": "Executed electric service agreement as described in Form 10-Q",
      "conditions_reported": [
        "Required government approvals including LPSC approval",
        "Construction of certain serving transmission facilities before obligations commence"
      ],
      "source_id": "evest-sec"
    },
    {
      "record_date": "2026-07-13",
      "scope": "Richland Parish expansion",
      "record_type": "Developer announcement",
      "quantity": 5,
      "unit": "GW",
      "basis": "Compute capacity announced by Meta",
      "source_id": "hyperion"
    },
    {
      "record_date": "2026-11-12",
      "scope": "Adjacent Evest project",
      "record_type": "Generation proposed in open certification application",
      "quantity": 5278,
      "unit": "MW",
      "basis": "Sum of seven proposed generator ratings",
      "group_totals": [
        {
          "group": "Richland Parish",
          "units": 4,
          "rating_mw_per_unit": 754,
          "rating_mw_total": 3016
        },
        {
          "group": "Pointe Coupee Parish",
          "units": 3,
          "rating_mw_per_unit": 754,
          "rating_mw_total": 2262
        }
      ],
      "estimated_in_service_years": [
        2030,
        2031
      ],
      "source_ids": [
        "evest-staff-brief",
        "evest-sec",
        "evest-docket"
      ]
    }
  ],
  "evest_milestone_schedule": [
    {
      "date": "2026-12-16",
      "milestone": "Commission consideration scheduled by its procedural order",
      "type": "Scheduled regulatory consideration",
      "source_id": "evest-procedural-order"
    },
    {
      "date": "2030-08-01",
      "milestone": "Customer interconnection",
      "type": "Utility projected in service",
      "source_id": "evest-staff-brief"
    },
    {
      "date": "2030-12-30",
      "milestone": "Smalling to El Dorado 500 kV line",
      "type": "Utility projected in service",
      "source_id": "evest-staff-brief"
    },
    {
      "date": "2031-12-01",
      "milestone": "West Fork Creek to St. Landry 500 kV line and switching station",
      "type": "Utility projected in service",
      "source_id": "evest-staff-brief"
    }
  ],
  "limitations": "The public records have different scopes and measurement boundaries. The generator ratings cannot be applied as capacity at the customer meter. The listed dates describe specific regulatory or utility milestones, and the first usable facility MW at those dates is not established by this extract."
}