# FAA height limits near airports: what a data center site needs to check

> FAA Part 77 for data center sites: when notice is required for buildings, stacks and cranes near airports, the 200 ft and 100:1 tests, and how to check a site.

URL: https://invariant-ai.com/blog/faa-height-limits-data-center-site  
Published: 2026-11-20 · Publisher: Invariant · Region: United States

A data center near an airport may need to file FAA Form 7460-1 before construction. Under 14 CFR Part 77, notice is required for any structure over 200 feet above ground, and for lower structures that would break an imaginary slope from a nearby public-use airport, for example 100 to 1 for 20,000 feet from a runway longer than 3,200 feet. Cranes count. Generator stacks and cooling equipment can count. The FAA’s Notice Criteria Tool tells you from a coordinate and a height.

## Key points

- Most data center buildings are well under 200 feet, so the slope tests near airports are what usually apply.
- Construction cranes often need their own filing.
- File at least 45 days before construction; a determination of hazard can stop or change the design.
- Heliports and private airstrips can matter too.

## The Part 77 tests

| Test | Applies to |
| --- | --- |
| Over 200 ft above ground level | Any structure anywhere |
| 100:1 slope for 20,000 ft | Public-use airports with a runway over 3,200 ft |
| 50:1 slope for 10,000 ft | Public-use airports with shorter runways |
| 25:1 slope for 5,000 ft | Public-use heliports |

Sources: ([Electronic Code of Federal Regulations](https://www.ecfr.gov/current/title-14/chapter-I/subchapter-E/part-77))

If a test is met, notice goes to the FAA on Form 7460-1 at least 45 days before construction starts. The FAA then issues a determination of no hazard, sometimes with marking and lighting conditions. ([Electronic Code of Federal Regulations](https://www.ecfr.gov/current/title-14/chapter-I/subchapter-E/part-77))

## How to check a site

Enter the coordinate, ground elevation and the tallest point (roof, stack, crane) into the FAA’s Notice Criteria Tool. It returns whether notice is required. ([FAA Obstruction Evaluation / Airport Airspace Analysis](https://oeaaa.faa.gov/oeaaa/external/gisTools/gisAction.jsp))

In our feasibility screen we list airports and heliports nearby, run the tool at a typical building and crane height for the campus size, and flag any site where height will shape the design.

## More due diligence guides

**Site due diligence guides:** [Site due diligence: the two-step process](https://invariant-ai.com/blog/data-center-site-due-diligence) · [Step 1: site feasibility screen](https://invariant-ai.com/blog/data-center-site-feasibility-study) · [Step 2: utility-grade power study](https://invariant-ai.com/blog/utility-grade-power-study) · [What a power flow study is](https://invariant-ai.com/blog/data-center-power-flow-study) · [N-1 contingency analysis](https://invariant-ai.com/blog/n-1-contingency-analysis-data-center) · [How to check substation capacity](https://invariant-ai.com/blog/data-center-substation-capacity-check) · [Utility load study cost and timeline](https://invariant-ai.com/blog/utility-load-study-cost-and-timeline) · [Distance to substation and transmission](https://invariant-ai.com/blog/distance-to-transmission-line-data-center) · [Flood zone screening](https://invariant-ai.com/blog/data-center-flood-zone-screening) · [Seismic risk screening](https://invariant-ai.com/blog/data-center-seismic-risk-screening) · [Wetlands, species and Phase I ESA](https://invariant-ai.com/blog/data-center-environmental-site-screening) · [Power due diligence for investors and lenders](https://invariant-ai.com/blog/data-center-power-due-diligence-investors) · [For landowners: a power study before you sell](https://invariant-ai.com/blog/power-study-before-selling-land-to-data-center)

**More on site selection:** [Five rungs of power evidence](https://invariant-ai.com/blog/power-evidence-data-center-site-verification) · [Will-serve letter vs load study vs ESA](https://invariant-ai.com/blog/utility-will-serve-letter-load-study-esa) · [Moratorium screening](https://invariant-ai.com/blog/data-center-moratorium-local-opposition-site-screening) · [Site selection checklist](https://invariant-ai.com/blog/data-center-site-selection-checklist) · [Texas: SB 6 and Batch Zero](https://invariant-ai.com/blog/texas-data-center-large-load-interconnection-2026) · [Find a data center site in the US](https://invariant-ai.com/blog/find-data-center-site-us) · [Site selection services](https://invariant-ai.com/blog/data-center-site-selection-services) · [Capacity for neoclouds and AI labs](https://invariant-ai.com/blog/ai-compute-capacity-for-neoclouds) · [Power check for AI tenants](https://invariant-ai.com/blog/provider-power-check-for-ai-tenants)

## Questions

### Does a data center need FAA approval?

Only if it meets a Part 77 notice test: over 200 feet above ground, or breaking an airport slope surface. Then it files Form 7460-1 and needs a determination of no hazard. ([Electronic Code of Federal Regulations](https://www.ecfr.gov/current/title-14/chapter-I/subchapter-E/part-77))

### Do construction cranes need FAA notice?

Yes, if the crane meets a Part 77 notice test. Cranes are often taller than the finished building. ([Electronic Code of Federal Regulations](https://www.ecfr.gov/current/title-14/chapter-I/subchapter-E/part-77))

### How far from an airport does Part 77 apply?

Up to 20,000 feet from a runway longer than 3,200 feet at a public-use airport, on a 100 to 1 slope, plus the 200 foot test anywhere. ([Electronic Code of Federal Regulations](https://www.ecfr.gov/current/title-14/chapter-I/subchapter-E/part-77))

### Is airspace part of Invariant’s screen?

Yes, alongside power, flood, seismic, wetlands, zoning and the parcel.

## Sources

- FAA Obstruction Evaluation / Airport Airspace Analysis: [Notice Criteria Tool](https://oeaaa.faa.gov/oeaaa/external/gisTools/gisAction.jsp)
- Electronic Code of Federal Regulations: [14 CFR Part 77: Safe, efficient use, and preservation of the navigable airspace](https://www.ecfr.gov/current/title-14/chapter-I/subchapter-E/part-77)

## Related

- [Data center site feasibility study: power, flood, seismic and zoning screen in 24 hours](https://invariant-ai.com/blog/data-center-site-feasibility-study)
- [Data center environmental screening: wetlands, endangered species and Phase I ESA](https://invariant-ai.com/blog/data-center-environmental-site-screening)
- [Data center site due diligence: feasibility screen first, then a utility-grade power study](https://invariant-ai.com/blog/data-center-site-due-diligence)

---

Site screens and power studies: pranav@invariant-ai.com, (628) 220-8972, https://cal.com/pranav-goswami/website-30min