# Geoforge alternatives for data center power screening

> Compare Geoforge, Paces, PVcase, GridCARE and Invariant. Use 49 PJM upgrade records to test the dates and assumptions behind a data center power forecast.

URL: https://invariant-ai.com/blog/geoforge-alternatives-data-center-power  
Published: 2026-11-22 · Updated: 2026-11-23 · Publisher: Invariant · Region: United States

Start with Invariant for a power study tied to the proposed campus, its load ramp and the dates each phase needs service. Compare Geoforge for candidate connections and modeled offtake, Paces for portfolio screening, PVcase Prospect for grid constraints and GridCARE for utility programs that evaluate flexible load. Give each provider the same test. Ask which facility limits service, when the relevant upgrade enters service and how a delay changes the first phase.

## Key points

- In one PJM plan, the same 765 kV line segment had a June 2030 required date and an October 2031 projected date, a gap of 517 days.
- AEP Ohio used separate service estimates for different groups of studied customers. One group needed an additional regional upgrade.
- A usable power forecast names the connection, the case year, the limiting element and the work required for each load phase.

## Which Geoforge alternative fits your site search?

The table summarizes public product descriptions. Use the Ohio example below to test what a provider can explain about its output for your location.

| Tool | What the provider documents | What to ask in the demo |
| --- | --- | --- |
| Geoforge | Site reports with potential connections, modeled offtake by year and scenario, queue context and an energization estimate. It also offers deeper power-flow studies. | Ask which grid case and upgrade records drive the range for the first phase. Request the basis for any competing load in that case. ([Geoforge](https://geoforge.ai/)) ([Geoforge](https://geoforge.ai/report/power)) |
| Paces | Regional capacity screening, project-level connection evaluation and support through interconnection studies. | Ask how capacity layer results carry into a study of your site, and which grid, land or permitting issue changes the shortlist. ([Paces](https://www.paces.com/post/the-power-development-funnel-from-siting-to-interconnection)) |
| PVcase Prospect | Modeled injection and withdrawal, with limiting elements for different scenarios. The published documentation distinguishes base-case and contingency coverage by market. | Check the available scenarios for your region and whether the constraint is already present before your load is added. ([PVcase](https://help.pvcase.com/hc/en-us/articles/47268175189907-Constraint-scenarios)) |
| GridCARE | Utility work on grid capacity for flexible loads. National Grid describes its use in New York and work with UK Electricity Transmission. | Confirm the serving utility is involved and get the MW, hours, operating limits and dispatch conditions for any flexible service. ([National Grid](https://www.nationalgrid.com/document/601726/download)) |
| Invariant | The published site-study workflow covers AC power flow, contingency analysis, candidate connections, and indicative costs and timing. | Request the case vintage, phased results and limiting facilities. Ask which assumptions can be rerun as utility evidence changes. ([Invariant](https://invariant-ai.com/blog/utility-grade-power-study)) |

## An Ohio power forecast can contain several valid dates

AEP Ohio’s November 2025 study letter covered about 13 GW of new data center load. It found that the studied projects needed regional transmission work under the scenarios evaluated. Its initial estimate was Q4 2031 for Clusters 1 and 3 with the regional project and applicable parallel upgrades in service. Cluster 2 had a 2033 planning estimate and needed another regional solution. A buyer needs the customer’s actual service plan to determine which work applies. ([AEP Ohio](https://www.aepohio.com/lib/docs/ratesandtariffs/ohio/AEP-Ohio_DCT_Load_Study_Letter_25.11.7.pdf#page=3))

PJM cross-references the first regional proposal, 2025W1-570, to upgrade package b4068. In the March 2026 assessment, b4068.2, the AEP portion of the Greentown to Teddy 765 kV line, had a required date of June 1, 2030 and a projected date of October 31, 2031. The first is the planning need date. The second is the forecast in that report. A particular customer’s electric service date has its own evidence. ([PJM](https://www.pjm.com/pjmfiles/pub/planning/project-queues/TC2/PHASE_2/AG2-329/AG2-329_imp_PHASE_2.htm)) ([PJM](https://www.pjm.com/-/media/DotCom/planning/rtep-dev/baseline-reports/2025-rtep-baseline-assessment.pdf#page=23)) ([AEP Ohio](https://www.aepohio.com/lib/docs/ratesandtariffs/ohio/AEP-Ohio_DCT_Load_Study_Letter_25.11.7.pdf#page=3))

| What a report might show | Date in the public record | How to use it |
| --- | --- | --- |
| Planning need for b4068.2 | June 1, 2030 | Keep it as the date the reliability plan requires the work. ([PJM](https://www.pjm.com/-/media/DotCom/planning/rtep-dev/baseline-reports/2025-rtep-baseline-assessment.pdf#page=23)) |
| Projected in-service date for b4068.2 | October 31, 2031 | Use it as a dated component forecast and check the latest schedule. ([PJM](https://www.pjm.com/-/media/DotCom/planning/rtep-dev/baseline-reports/2025-rtep-baseline-assessment.pdf#page=23)) |
| AEP Ohio Cluster 2 service planning estimate | 2033 | Check the second regional dependency, local work and actual customer schedule. ([AEP Ohio](https://www.aepohio.com/lib/docs/ratesandtariffs/ohio/AEP-Ohio_DCT_Load_Study_Letter_25.11.7.pdf#page=3)) |

AEP Ohio later reported that 5,642 MW had signed binding contracts under the new tariff as of February 12, 2026. That update gives the scale of the committed cohort. It leaves the distribution by bus, year and cluster open. Ask your provider how it treats unconfirmed demand, then test a scenario with a different set of competing projects. ([AEP Ohio](https://www.aepohio.com/lib/docs/ratesandtariffs/ohio/AEP-Ohio_DCT_Load_Study_Letter_25.11.7.pdf#page=3)) ([AEP Ohio](https://www.aepohio.com/company/news/view?releaseID=10753))

## What the 49 PJM upgrade rows show

We extracted the required and projected dates for each b4068 sub-ID in the March assessment. Two rows projected June 2028, 21 projected October 2030, and 26 projected October 2031. These are counts of published sub-IDs. A project forecast should identify the subset the connection actually depends on. ([PJM](https://www.pjm.com/-/media/DotCom/planning/rtep-dev/baseline-reports/2025-rtep-baseline-assessment.pdf#page=19))

Two rows in that assessment show an invalid calendar value in the required-date column. The February board recommendations show June 1, 2030 for both sub-IDs. The download retains the February dates and the March source values separately, with the latter normalized to null. Ask a provider which source its model used and how it handles this sort of discrepancy. ([PJM](https://www.pjm.com/-/media/DotCom/planning/rtep-dev/baseline-reports/2025-rtep-baseline-assessment.pdf#page=45)) ([PJM](https://www.pjm.com/-/media/DotCom/committees-groups/committees/teac/2026/20260203/20260203-pjm-board-whitepaper-february-2026.pdf#page=30))

[Download the 49 PJM upgrade rows and AEP Ohio study evidence (JSON)](https://invariant-ai.com/blog/pjm-b4068-transmission-upgrade-dates.json)

[Review the power study process](https://invariant-ai.com/blog/utility-grade-power-study)

## How to test the first phase before paying for a site option

Give the vendor the parcel, the minimum load needed on day one, the full facility load, the two service dates and how much load you can curtail. For example, ask for 50 MW by July 2030 and 200 MW by January 2032 at the meter. Those are illustrative targets, with the utility service for your project to be confirmed.

- Ask for the modeled MW on each date at the same connection point. Record the model year, the limiting equipment and the outage assumption.
- Request a second run with the relevant upgrade out of service through your target date. Ask which phase remains feasible and what changes the answer.
- Get the utility’s written service terms, required work and estimated start of service. Keep energization and facility handover as separate milestones.

**Continue the power diligence:** [Compare more power screening tools and the Aiken energization case](https://invariant-ai.com/blog/data-center-power-screening-tools) · [See what a site-specific load study can test](https://invariant-ai.com/blog/utility-grade-power-study) · [Find and verify a site for a 200 MW data center](https://invariant-ai.com/blog/200-mw-data-center-site)

**Evaluate other data APIs:** [Run the same vendor evaluation across workflows](https://invariant-ai.com/blog/physical-world-data-api-evaluation)

## Questions

### What are the best Geoforge alternatives for finding power for a data center?

Consider Paces for portfolio screening, PVcase Prospect for modeled point-of-interconnection constraints, GridCARE for opportunities that depend on utility-supported load flexibility, and Invariant for a phased site study. Test your actual service dates with each provider. ([Paces](https://www.paces.com/post/the-power-development-funnel-from-siting-to-interconnection)) ([PVcase](https://help.pvcase.com/hc/en-us/articles/47268175189907-Constraint-scenarios)) ([National Grid](https://www.nationalgrid.com/document/601726/download)) ([Invariant](https://invariant-ai.com/blog/utility-grade-power-study))

### What is the difference between required and projected in-service dates?

The required date expresses when the planning case needs an upgrade. The projected date is the schedule estimate in that record. PJM’s March 2026 assessment lists June 1, 2030 and October 31, 2031 respectively for b4068.2. Use the relevant utility agreement and construction schedule to evaluate customer service. ([PJM](https://www.pjm.com/-/media/DotCom/planning/rtep-dev/baseline-reports/2025-rtep-baseline-assessment.pdf#page=23)) ([AEP Ohio](https://www.aepohio.com/lib/docs/ratesandtariffs/ohio/AEP-Ohio_DCT_Load_Study_Letter_25.11.7.pdf#page=3))

### Can a power screening report tell me when I can energize a data center?

A power screen can estimate when the grid could support a proposed load under a specific case. The serving utility’s agreement and work plan establish the commercial service terms and estimated date. Confirm energization through a commissioning or utility record. ([Invariant](https://invariant-ai.com/blog/utility-grade-power-study)) ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/))

## Sources

- Geoforge: [Power reports and grid data methodology](https://geoforge.ai/)
- Geoforge: [Public example of a power site report](https://geoforge.ai/report/power)
- Paces: [Site screening, point-of-interconnection analysis and studies](https://www.paces.com/post/the-power-development-funnel-from-siting-to-interconnection)
- PVcase: [Prospect capacity and constraint scenarios](https://help.pvcase.com/hc/en-us/articles/47268175189907-Constraint-scenarios)
- National Grid: [2026/27 half-year results, GridCARE work on flexible loads](https://www.nationalgrid.com/document/601726/download)
- Invariant: [Site-specific power study scope and example](https://invariant-ai.com/blog/utility-grade-power-study)
- AEP Ohio: [November 7, 2025 load study letter, pages 3 to 5](https://www.aepohio.com/lib/docs/ratesandtariffs/ohio/AEP-Ohio_DCT_Load_Study_Letter_25.11.7.pdf#page=3)
- AEP Ohio: [February 2026 update on signed data center contracts](https://www.aepohio.com/company/news/view?releaseID=10753)
- AEP Ohio: [Data center tariff and process for service agreements](https://www.aepohio.com/company/about/rates/data-center-tariff/)
- PJM: [March 18, 2026 reliability assessment, b4068 rows on printed pages 15 to 21 and 41](https://www.pjm.com/-/media/DotCom/planning/rtep-dev/baseline-reports/2025-rtep-baseline-assessment.pdf#page=19)
- PJM: [Required and projected dates for Greentown to Teddy, row b4068.2](https://www.pjm.com/-/media/DotCom/planning/rtep-dev/baseline-reports/2025-rtep-baseline-assessment.pdf#page=23)
- PJM: [Two b4068 rows with non-calendar values in the required date column](https://www.pjm.com/-/media/DotCom/planning/rtep-dev/baseline-reports/2025-rtep-baseline-assessment.pdf#page=45)
- PJM: [February 2026 board recommendations, b4068.48 and b4068.49, printed page 27](https://www.pjm.com/-/media/DotCom/committees-groups/committees/teac/2026/20260203/20260203-pjm-board-whitepaper-february-2026.pdf#page=30)
- PJM: [Transition Cycle 2 impact study, cross-reference from proposal 570 to b4068](https://www.pjm.com/pjmfiles/pub/planning/project-queues/TC2/PHASE_2/AG2-329/AG2-329_imp_PHASE_2.htm)

## Related

- [Data center site selection tools for power capacity](https://invariant-ai.com/blog/data-center-power-screening-tools)
- [Utility-grade power study for data centers: N-1 power flow before you file with the utility](https://invariant-ai.com/blog/utility-grade-power-study)
- [200 MW data center sites for sale and how to verify power](https://invariant-ai.com/blog/200-mw-data-center-site)