  "name": "Power milestones at four U.S. gigawatt data center developments",
  "description": "Seven dated developer and utility records covering energized buildings, planned grid capacity, onsite generation design, critical IT load, and regulatory approval at projects in Texas and Louisiana.",
  "reviewedOn": "2026-11-22",
  "guide": "https://invariant-ai.com/blog/1-gw-data-center-site",
  "readingNotes": [
    "Each record represents the scope of a particular dated announcement. A later announcement can revise an earlier milestone.",
    "Capacity figures use the basis stated in each record. Do not sum rows across phases, projects or measurement boundaries.",
    "A null capacity means the cited record gives no applicable MW figure. These are project references and do not describe inventory available to a buyer."
  ],
  "sources": [
    {
      "id": "abilene-live",
      "publisher": "Crusoe",
      "date": "2025-09-30",
      "title": "Crusoe announces flagship Abilene data center is live",
      "url": "https://www.crusoe.ai/resources/newsroom/crusoe-announces-flagship-abilene-data-center-is-live"
    },
    {
      "id": "abilene-expansion",
      "publisher": "Crusoe",
      "date": "2026-03-27",
      "title": "Crusoe announces a new 900 MW campus next to the original Abilene campus",
      "url": "https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure"
    },
    {
      "id": "childress",
      "publisher": "Crusoe",
      "date": "2026-07-15",
      "title": "Crusoe and Lancium announce a 1 GW campus in Childress",
      "url": "https://www.crusoe.ai/resources/newsroom/crusoe-and-lancium-announce-1-gigawatt-ai-data-center-campus-in-childress-texas"
    },
    {
      "id": "hyperion",
      "publisher": "Meta",
      "date": "2026-07-13",
      "title": "Meta announces an expansion of its Richland Parish data center",
      "url": "https://about.fb.com/news/2026/07/teachers-local-businesses-win-as-meta-expands-louisiana-data-center/"
    },
    {
      "id": "hyperion-utility",
      "publisher": "Entergy Louisiana",
      "date": "2025-08-20",
      "title": "Entergy reports regulatory approval for infrastructure serving Meta’s Louisiana campus",
      "url": "https://www.entergy.com/news/entergy-louisiana-receives-lpsc-approval-for-major-infrastructure-investments-to-support-metas-data-center-and-improve-reliability"
    }
  ],
  "records": [
    {
      "id": "abilene-original-first-phase",
      "site": "Abilene original campus",
      "region": "Texas",
      "milestone": "Energized first two buildings",
      "evidenceState": "developer_reported_energized",
      "capacityMw": 200,
      "capacityBasis": "Two buildings rated at 100 MW each",
      "sourceIds": [
        "abilene-live",
        "abilene-expansion"
      ],
      "scope": "Crusoe reported the first two buildings energized. 200 MW is their combined rating. The sources give no meter reading or spare tenant capacity."
    },
    {
      "id": "abilene-original-full-buildout",
      "site": "Abilene original campus",
      "region": "Texas",
      "milestone": "Full eight-building campus",
      "evidenceState": "developer_announced_buildout",
      "capacityMw": 1200,
      "capacityBasis": "Total power capacity for the original campus",
      "sourceIds": [
        "abilene-expansion"
      ],
      "scope": "The March 2026 announcement targeted completion of the second phase by year-end 2026. This is the campus total inclusive of the first two buildings."
    },
    {
      "id": "abilene-adjacent-generation",
      "site": "Abilene adjacent Microsoft campus",
      "region": "Texas",
      "milestone": "Onsite power plant design",
      "evidenceState": "developer_announced_design",
      "capacityMw": 900,
      "capacityBasis": "Onsite generation design",
      "sourceIds": [
        "abilene-expansion"
      ],
      "scope": "The figure describes the planned plant for a separate campus next to the original Abilene development. The release gives no net output at the customer meter under design-day conditions."
    },
    {
      "id": "abilene-adjacent-it",
      "site": "Abilene adjacent Microsoft campus",
      "region": "Texas",
      "milestone": "Critical IT capacity design",
      "evidenceState": "developer_announced_design",
      "capacityMw": 672,
      "capacityBasis": "Two buildings designed for 336 MW of critical IT load each",
      "sourceIds": [
        "abilene-expansion"
      ],
      "scope": "Calculated as 2 × 336 MW. The same campus appears in the generation record. These are different measurements of one development and cannot be added."
    },
    {
      "id": "childress-full-buildout",
      "site": "Childress campus",
      "region": "Texas",
      "milestone": "Full-scale grid connection as announced",
      "evidenceState": "developer_announced_buildout",
      "capacityMw": 1000,
      "capacityBasis": "Grid-connected capacity at full scale",
      "sourceIds": [
        "childress"
      ],
      "scope": "The project announcement describes a 270-acre campus. It does not report the first block of energized load."
    },
    {
      "id": "richland-compute-expansion",
      "site": "Hyperion",
      "region": "Louisiana",
      "milestone": "Compute expansion announced",
      "evidenceState": "developer_announced_expansion",
      "capacityMw": 5000,
      "capacityBasis": "Compute capacity, using Meta’s terminology",
      "sourceIds": [
        "hyperion"
      ],
      "scope": "The figure is Meta’s announced target in July 2026. The announcement does not give metered utility capacity or a phased service schedule."
    },
    {
      "id": "richland-utility-infrastructure",
      "site": "Hyperion",
      "region": "Louisiana",
      "milestone": "Utility reports regulatory approval for new generation and transmission",
      "evidenceState": "utility_reported_regulatory_approval",
      "capacityMw": null,
      "capacityBasis": null,
      "sourceIds": [
        "hyperion-utility"
      ],
      "scope": "Entergy’s August 2025 release anticipated two Richland Parish plants in late 2028 and a Waterford plant by the end of 2029. These were utility project targets when announced. The release gives no MW allocation at the campus meter."
    }
  ]
}