# GPU colocation for AI labs and neoclouds: what to ask a provider before you sign

> GPU colocation checklist for AI labs and neoclouds: power per cabinet, liquid cooling, energized vs contracted MW, delivery dates, minimum terms, fiber and SLAs.

URL: https://invariant-ai.com/blog/gpu-colocation-for-ai-labs  
Published: 2026-11-20 · Publisher: Invariant · Region: United States

GPU colocation works when a provider can deliver the power per cabinet your racks need, cool it, and do both by your date. Ask for four things in writing: kW per cabinet and the cooling method for your density, total MW energized today versus contracted for later, the delivery date and what it depends on, and the remedy if that date slips. Most halls built before 2023 were designed for 5 to 15 kW a cabinet; a GB200 NVL72 rack runs near 120 kW.

## Key points

- Energized MW and contracted MW are different. Ask which one your racks sit on.
- Get the cooling method for your exact density, not a general "liquid ready" claim.
- A delivery date with no remedy is a hope. Leases with longstop dates exist for this reason.
- Check fiber routes and cross-connect pricing early; they shape both latency and cost.

## The questions that matter

| Question | Why it matters | Good answer |
| --- | --- | --- |
| How many kW per cabinet, and how is it cooled? | Density sets cooling; cooling sets whether your racks fit | A number for your configuration, with rear-door, direct-to-chip or immersion named |
| How much of the hall’s MW is energized today? | Contracted power can slip; energized power is there | MW energized, MW contracted, with the utility document for each |
| When can my racks be live, and what does that date depend on? | Fit-out, cooling plant and transformers drive most delays | A date with its dependencies listed |
| What happens if the date slips? | You may be paying for GPUs you cannot run | Rent abatement, credits or a termination right |
| What is the minimum term and commit? | Power-heavy deals carry long commitments | Term and ramp that match your contracts |
| Which carriers and routes are in the building? | Latency, redundancy and cross-connect cost | Named carriers, diverse paths |

Sources: ([U.S. Securities and Exchange Commission](https://www.sec.gov/Archives/edgar/data/0002097508/000118518526004213/bldcex10-51i.htm)) ([eeNews Europe](https://www.eenewseurope.com/en/nvidia-offers-120kw-liquid-cooled-blackwell-rack-as-industry-standard))

## Why the power date is the real risk

Capacity deals fail on dates. Poolside’s planned 2 GW campus deal with CoreWeave broke down over whether the first cluster could be ready in time. Large compute contracts, such as Microsoft’s $9.7 billion deal with IREN, pay against delivery milestones. ([Baxtel](https://baxtel.com/news/poolside-pursues-new-partners-for-texas-data-center-following-coreweave-deal-breakdown)) ([TechInformed](https://techinformed.com/microsoft-signs-9-7-billion-iren-deal-for-nvidia-gb300-capacity/))

Tenants now write power into leases. One data center lease filed with the SEC lets the tenant terminate if firm capacity is not delivered by a longstop date, and gives the tenant approval rights over the power plan. ([U.S. Securities and Exchange Commission](https://www.sec.gov/Archives/edgar/data/0002097508/000118518526004213/bldcex10-51i.htm))

If you are taking colocation or a lease, you inherit the provider’s power risk. A power check on the provider’s site tells you whether the date is backed by an energized service, a signed agreement, or only a request in a queue.

## Where we fit

We find colocation and built capacity that can take your density by your date, and we run a power check on any provider you are already talking to. You get the document behind their MW and what the date depends on, before you sign.

## More for neoclouds and AI labs

**For neoclouds and AI labs:** [Capacity for neoclouds and AI labs](https://invariant-ai.com/blog/ai-compute-capacity-for-neoclouds) · [How much power a GPU cluster needs](https://invariant-ai.com/blog/gpu-cluster-power-requirements) · [Liquid cooling for 40 to 130 kW racks](https://invariant-ai.com/blog/liquid-cooling-gpu-data-center) · [Where to put 1 to 10 MW of GPUs](https://invariant-ai.com/blog/small-gpu-cluster-1-to-10-mw) · [Build, lease or colocate](https://invariant-ai.com/blog/neocloud-build-lease-or-colocate) · [Power longstop dates in GPU leases](https://invariant-ai.com/blog/gpu-lease-power-longstop-diligence) · [Power check on a provider or site](https://invariant-ai.com/blog/provider-power-check-for-ai-tenants)

**Sites and power:** [AI data center sites](https://invariant-ai.com/blog/ai-data-center-site) · [Energized sites available now](https://invariant-ai.com/blog/energized-data-center-sites-available-now) · [Built data centers for sale and lease](https://invariant-ai.com/blog/data-center-for-sale) · [10 MW data center site](https://invariant-ai.com/blog/10-mw-data-center-site) · [100 MW data center site](https://invariant-ai.com/blog/100-mw-data-center-site) · [Converting a mining site to AI](https://invariant-ai.com/blog/convert-bitcoin-mining-site-to-ai-hpc-data-center) · [Behind-the-meter power](https://invariant-ai.com/blog/behind-the-meter-power-for-data-centers) · [Utility-grade power study](https://invariant-ai.com/blog/utility-grade-power-study) · [Site due diligence](https://invariant-ai.com/blog/data-center-site-due-diligence)

## Questions

### What is GPU colocation?

Renting space, power and cooling in a data center for your own GPU servers, rather than renting GPU instances from a cloud. You own or lease the hardware; the provider runs the building.

### How many kW per rack do I need for GPUs?

About 20 to 41 kW for two to four DGX H100 systems, about 57 kW for four DGX B200 systems, and about 120 kW for a GB200 NVL72 rack. ([eeNews Europe](https://www.eenewseurope.com/en/nvidia-offers-120kw-liquid-cooled-blackwell-rack-as-industry-standard))

### What should be in a GPU colocation contract?

kW per cabinet, cooling method, energized versus contracted MW, a delivery date with dependencies, a remedy if it slips, term and commit, and named carriers.

### Can Invariant check a colocation provider’s power?

Yes. We check the document behind the provider’s MW and what the date depends on, and report back before you sign.

## Sources

- eeNews Europe: [Nvidia offers 120 kW liquid-cooled Blackwell rack as industry standard](https://www.eenewseurope.com/en/nvidia-offers-120kw-liquid-cooled-blackwell-rack-as-industry-standard)
- U.S. Securities and Exchange Commission: [Data center lease exhibit with a firm capacity longstop date (S-4/A exhibit 10.51)](https://www.sec.gov/Archives/edgar/data/0002097508/000118518526004213/bldcex10-51i.htm)
- Baxtel: [Poolside pursues new partners for Texas data center following CoreWeave deal breakdown](https://baxtel.com/news/poolside-pursues-new-partners-for-texas-data-center-following-coreweave-deal-breakdown)
- TechInformed: [Microsoft signs $9.7 billion IREN deal for Nvidia GB300 capacity](https://techinformed.com/microsoft-signs-9-7-billion-iren-deal-for-nvidia-gb300-capacity/)

## Related

- [Power longstop dates in GPU and data center leases: check the provider’s power before you sign](https://invariant-ai.com/blog/gpu-lease-power-longstop-diligence)
- [Liquid cooling for GPU racks: what a data center needs for 40 to 130 kW racks](https://invariant-ai.com/blog/liquid-cooling-gpu-data-center)
- [Power check on a data center provider or site for AI tenants and neoclouds](https://invariant-ai.com/blog/provider-power-check-for-ai-tenants)

---

Site screens and power studies: pranav@invariant-ai.com, (628) 220-8972, https://cal.com/pranav-goswami/website-30min