# Gujarat data centre policy 2026-29: 150 MW threshold and ₹1 per unit subsidy

> Viksit Gujarat Data Centre Policy 2026-29: 150 MW minimum IT load, 51% renewable power, ₹1 per unit for 20 years and a 7.5 GW target, launched 9 July 2026.

URL: https://invariant-ai.com/blog/gujarat-data-centre-policy  
Published: 2026-11-21 · Publisher: Invariant · Region: Gujarat, India

The Viksit Gujarat Data Centre Policy 2026-29 gives incentives only to projects with an approved IT load of at least 150 MW, and targets 7.5 GW and about ₹6 lakh crore of investment. Gujarat launched the policy on 9 July 2026 and issued its Government Resolution on 7 August 2026. At least 51% of power for core operations must be renewable. According to Cyril Amarchand Mangaldas, incentives include a ₹1 per unit tariff subsidy for 20 years, 100% electricity duty reimbursement for 20 years and an interest subsidy of up to 4% for 10 years, capped at 75% of eligible fixed capital investment. These terms are as reported by a law firm and the press; we have not seen the notified Government Resolution.

## Key points

- Gujarat’s 2026-29 policy requires an approved IT load of at least 150 MW, which makes it a policy for large campuses, not for small colocation sites.
- Under the Gujarat policy, eligible fixed capital investment excludes land, land development and chips and is capped at the lower of 80% of fixed capital investment or ₹60,000 crore per GW, according to Cyril Amarchand Mangaldas.
- Battery storage counts for at most 10% of the Gujarat capital subsidy, according to the same summary.
- The Gujarat policy document highlights Dholera and GIFT City, and the state announced two planned cable landing stations in Gujarat, according to DD India.
- Gujarat data centre incentives cannot be combined with other Gujarat policies, but central schemes are allowed.

## Gujarat Data Centre Policy 2026-29: key facts

| Item | Detail (checked 21 November 2026) |
| --- | --- |
| Policy | Viksit Gujarat Data Centre Policy 2026-29 |
| Launched | 9 July 2026, Gandhinagar; Government Resolution issued 7 August 2026 |
| Validity | 3 years from notification, extendable; incentives stop at 7.5 GW |
| Targets | 7.5 GW and about ₹6 lakh crore of investment |
| Eligibility | Approved IT load of at least 150 MW; at least 51% renewable power for core operations |
| Headline incentives (as reported; resolution not seen) | ₹1 per unit for 20 years; electricity duty 100% for 20 years; interest subsidy up to 4% for 10 years; stamp duty and registration 100%; SGST reimbursement |
| Cap | Total support up to 75% of eligible fixed capital investment, disbursed over 20 years |
| Status | Notified; check the Government Resolution text before filing |

Sources: ([DD India](https://ddindia.co.in/2026/07/gujarat-launches-data-centre-policy-2026-29-to-attract-investment-build-digital-infrastructure-hub/)) ([IANS](https://ianslive.in/gujarat-notifies-data-centre-policy-to-build-75-gw-green-ai-capacity-by-2029--20260807190500)) ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/)) ([Free Press Journal](https://www.freepressjournal.in/india/gujarat-unveils-data-centre-policy-2026-29-eyes-6-lakh-crore-investment-in-digital-infrastructure))

## Who qualifies and how the investment is counted

- Gujarat’s policy requires an approved IT load of at least 150 MW.
- Eligible fixed capital investment excludes land, land development and chips, and is capped at the lower of 80% of fixed capital investment or ₹60,000 crore per GW.
- Battery storage is limited to 10% of the capital subsidy.
- No stacking with other Gujarat policies; central schemes are allowed.

Sources: ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/))

## Gujarat fiscal incentives for data centres

Gujarat’s fiscal incentives for data centres are listed below as reported by Cyril Amarchand Mangaldas and tele.net; we have not seen the notified Government Resolution. ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/)) ([tele.net](https://tele.net.in/gujarat-government-launches-data-centre-policy-2026-29/))

- Capital subsidy of 2.5% of eligible fixed capital investment, for projects in the Dholera Special Investment Region.
- Interest subsidy up to 4% a year for 10 years on bank or financial institution term loans, with an annual cap of ₹25 crore.
- Power tariff subsidy of ₹1 per unit for 20 years from commercial operation.
- Electricity duty reimbursement of 100% for 20 years from commercial operation.
- Stamp duty and registration fee exemption of 100% on lease or purchase of land, and SGST reimbursement.
- Desalination support of 20% of eligible capital cost or ₹2 crore per MLD, whichever is lower.
- Total support capped at 75% of eligible fixed capital investment, disbursed over 20 years.

Sources: ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/)) ([tele.net](https://tele.net.in/gujarat-government-launches-data-centre-policy-2026-29/))

## Power terms and essential service status

Gujarat’s policy requires at least 51% of power for core operations to be renewable. Open access is permitted and dual power supply through two independent feeders is provided. Cyril Amarchand Mangaldas reports that the policy treats data centre operations as an essential service under the Gujarat Essential Services Maintenance Act, 1972. ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/))

**Power in detail:** [Green energy open access for data centres](https://invariant-ai.com/blog/green-energy-open-access-data-centres-india) · [Grid connection: DISCOM, STU and CTU paths](https://invariant-ai.com/blog/data-centre-grid-connection-india)

## The earlier IT/ITeS Policy 2022-27

Before 2026, data centres in Gujarat were supported under the IT/ITeS Policy 2022-27: one-time capital support of up to 25% of eligible expenditure, capped at ₹150 crore, for greenfield Tier 3 or higher facilities of at least 4,000 sq ft and 150 racks, plus ₹1 per unit for five years, according to Cyril Amarchand Mangaldas. ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/))

## GIFT City and Dholera

Gujarat’s policy document highlights Dholera and GIFT City, and the state’s Science and Technology Secretary announced plans for two cable landing stations in Gujarat, according to DD India. ([DD India](https://ddindia.co.in/2026/07/gujarat-launches-data-centre-policy-2026-29-to-attract-investment-build-digital-infrastructure-hub/))

**Read next:** [Data centres in Gujarat: GIFT City, Ahmedabad, Jamnagar](https://invariant-ai.com/blog/data-centres-in-gujarat) · [AI data centres and IndiaAI GPUs](https://invariant-ai.com/blog/ai-data-centres-india)

For a site in Gujarat, Invariant checks how it gets power and the evidence behind that path (the distribution or transmission connection, the open access route, the nearest substations), screens seismic zone, flood history, groundwater status and airport height limits, and maps the central and state approvals the project needs, with the authority behind each one.

## More on data centres in India

**Start here:** [Data centres in India: capacity, cities, policy, power](https://invariant-ai.com/blog/data-centres-in-india) · [How to find a data centre site in India](https://invariant-ai.com/blog/find-data-centre-site-india) · [Data centre companies in India](https://invariant-ai.com/blog/data-centre-companies-india)

**Build and approvals:** [Approvals for a data centre in India](https://invariant-ai.com/blog/data-centre-approvals-india) · [How to set up a data centre in India](https://invariant-ai.com/blog/how-to-set-up-data-centre-india) · [Data centre cost per MW in India](https://invariant-ai.com/blog/data-centre-cost-per-mw-india) · [Site due diligence in India](https://invariant-ai.com/blog/data-centre-site-due-diligence-india) · [Data centre land and powered land in India](https://invariant-ai.com/blog/data-centre-land-india) · [Seismic zones, flood and cyclone risk](https://invariant-ai.com/blog/data-centre-seismic-flood-risk-india) · [Water and groundwater NOC for data centres](https://invariant-ai.com/blog/data-centre-water-india) · [DPDP Act and data localisation](https://invariant-ai.com/blog/dpdp-data-localisation-data-centres-india) · [Infrastructure status, tax holiday and DC SEZs](https://invariant-ai.com/blog/data-centre-incentives-india-central)

**Power:** [Power for data centres in India](https://invariant-ai.com/blog/power-for-data-centres-india) · [Grid connection: DISCOM, STU and CTU paths](https://invariant-ai.com/blog/data-centre-grid-connection-india) · [Green energy open access for data centres](https://invariant-ai.com/blog/green-energy-open-access-data-centres-india) · [Open access charges by state](https://invariant-ai.com/blog/open-access-charges-by-state-india) · [India data centre power demand to 2032](https://invariant-ai.com/blog/data-centre-power-demand-india) · [Power studies for Indian data centre sites](https://invariant-ai.com/blog/power-study-data-centre-india) · [Diesel generators and backup power rules](https://invariant-ai.com/blog/data-centre-backup-power-dg-sets-india)

**Policy by state:** [National data centre policy](https://invariant-ai.com/blog/national-data-centre-policy-india) · [State data centre policies compared](https://invariant-ai.com/blog/data-centre-policy-india-state-comparison) · [Maharashtra data centre policy](https://invariant-ai.com/blog/maharashtra-data-centre-policy) · [Uttar Pradesh data centre policy](https://invariant-ai.com/blog/uttar-pradesh-data-centre-policy) · [Tamil Nadu data centre policy](https://invariant-ai.com/blog/tamil-nadu-data-centre-policy) · [Telangana data centre policy](https://invariant-ai.com/blog/telangana-data-centre-policy) · [Gujarat data centre policy](https://invariant-ai.com/blog/gujarat-data-centre-policy) · [Karnataka data centre policy](https://invariant-ai.com/blog/karnataka-data-centre-policy) · [Andhra Pradesh data centre policy](https://invariant-ai.com/blog/andhra-pradesh-data-centre-policy) · [Haryana data centre policy](https://invariant-ai.com/blog/haryana-data-centre-policy) · [Rajasthan data centre policy](https://invariant-ai.com/blog/rajasthan-data-centre-policy) · [Odisha data centre policy](https://invariant-ai.com/blog/odisha-data-centre-policy) · [West Bengal data centre policy](https://invariant-ai.com/blog/west-bengal-data-centre-policy) · [Madhya Pradesh data centre policy](https://invariant-ai.com/blog/madhya-pradesh-data-centre-policy)

**Cities:** [Data centres in Mumbai and Navi Mumbai](https://invariant-ai.com/blog/data-centres-in-mumbai) · [Data centres in Chennai](https://invariant-ai.com/blog/data-centres-in-chennai) · [Data centres in Hyderabad](https://invariant-ai.com/blog/data-centres-in-hyderabad) · [Data centres in Noida and Delhi NCR](https://invariant-ai.com/blog/data-centres-in-noida) · [Data centres in Bengaluru](https://invariant-ai.com/blog/data-centres-in-bengaluru) · [Data centres in Pune](https://invariant-ai.com/blog/data-centres-in-pune) · [Data centres in Visakhapatnam](https://invariant-ai.com/blog/data-centres-in-visakhapatnam) · [Data centres in Gujarat: GIFT City, Ahmedabad, Jamnagar](https://invariant-ai.com/blog/data-centres-in-gujarat) · [Data centres in Kolkata and East India](https://invariant-ai.com/blog/data-centres-in-kolkata)

**Compare and invest:** [Mumbai vs Chennai vs Hyderabad](https://invariant-ai.com/blog/mumbai-vs-chennai-vs-hyderabad-data-centres) · [India vs Singapore vs Johor](https://invariant-ai.com/blog/india-vs-singapore-vs-johor-data-centres) · [AI data centres and IndiaAI GPUs](https://invariant-ai.com/blog/ai-data-centres-india) · [Data centre investment in India](https://invariant-ai.com/blog/data-centre-investment-india)

## Questions

### What is the Gujarat data centre policy 2026-29?

The Viksit Gujarat Data Centre Policy 2026-29 gives incentives to data centre projects of 150 MW or more, and targets 7.5 GW and about ₹6 lakh crore of investment. It was launched on 9 July 2026 and notified on 7 August 2026. ([DD India](https://ddindia.co.in/2026/07/gujarat-launches-data-centre-policy-2026-29-to-attract-investment-build-digital-infrastructure-hub/)) ([IANS](https://ianslive.in/gujarat-notifies-data-centre-policy-to-build-75-gw-green-ai-capacity-by-2029--20260807190500)) ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/)) ([Free Press Journal](https://www.freepressjournal.in/india/gujarat-unveils-data-centre-policy-2026-29-eyes-6-lakh-crore-investment-in-digital-infrastructure))

### What is the minimum size for a data centre under Gujarat’s policy?

An approved IT load of at least 150 MW, with at least 51% renewable power for core operations. ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/))

### What power tariff subsidy does Gujarat give data centres?

Gujarat gives ₹1 per unit for 20 years, plus 100% electricity duty reimbursement for 20 years, as reported by Cyril Amarchand Mangaldas and tele.net. ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/)) ([tele.net](https://tele.net.in/gujarat-government-launches-data-centre-policy-2026-29/))

### Is a data center an essential service in Gujarat?

According to Cyril Amarchand Mangaldas’s summary of the 2026 policy, yes: data centre operations are treated as an essential service under the Gujarat Essential Services Maintenance Act, 1972. We have not seen the notified resolution. ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/))

### Can Gujarat incentives be combined with central schemes?

Yes. The Gujarat policy bars stacking with other Gujarat policies but allows central schemes. ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/))

### What did Gujarat offer data centres before the 2026 policy?

Gujarat supported data centres under its IT/ITeS Policy 2022-27, according to Cyril Amarchand Mangaldas. That policy offered one-time capital support of up to 25% of eligible expenditure, capped at ₹150 crore, for greenfield Tier 3 or higher facilities of at least 4,000 sq ft and 150 racks, plus ₹1 per unit for five years. ([Cyril Amarchand Mangaldas](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/))

## Sources

- DD India: [Gujarat launches Data Centre Policy 2026-29](https://ddindia.co.in/2026/07/gujarat-launches-data-centre-policy-2026-29-to-attract-investment-build-digital-infrastructure-hub/)
- IANS: [Gujarat notifies data centre policy to build 7.5 GW green AI capacity by 2029](https://ianslive.in/gujarat-notifies-data-centre-policy-to-build-75-gw-green-ai-capacity-by-2029--20260807190500)
- Cyril Amarchand Mangaldas: [Gujarat Data Center Policy 2026-2029: a push for large-scale data center infrastructure](https://corporate.cyrilamarchandblogs.com/2026/07/gujarat-data-center-policy-2026-2029-a-push-for-large-scale-data-center-infrastructure/)
- Free Press Journal: [Gujarat unveils Data Centre Policy 2026-29, eyes ₹6 lakh crore investment in digital infrastructure](https://www.freepressjournal.in/india/gujarat-unveils-data-centre-policy-2026-29-eyes-6-lakh-crore-investment-in-digital-infrastructure)
- tele.net: [Gujarat government launches Data Centre Policy 2026-29](https://tele.net.in/gujarat-government-launches-data-centre-policy-2026-29/)

## Related

- [Data centre policy in India: state data centre policies compared (2026)](https://invariant-ai.com/blog/data-centre-policy-india-state-comparison)
- [Data centres in Gujarat: Jamnagar, GIFT City, Ahmedabad and Dholera (2026)](https://invariant-ai.com/blog/data-centres-in-gujarat)
- [AI data centres in India: gigawatt campuses, IndiaAI GPUs and power (2026)](https://invariant-ai.com/blog/ai-data-centres-india)
- [Green energy open access for data centres in India: rules, banking and ISTS (2026)](https://invariant-ai.com/blog/green-energy-open-access-data-centres-india)
- [National data centre policy in India: the 2020 draft and what applies now (2026)](https://invariant-ai.com/blog/national-data-centre-policy-india)

---

[Email your India data centre project requirements](mailto:pranav@invariant-ai.com) · [Book a call](https://cal.com/pranav-goswami/website-30min)