# Interconnection Queue Data for Solar and Battery Storage

> Find U.S. interconnection queue data, verify solar and battery project status, and trace 58 Kern County requests across Berkeley Lab and California ISO reports.

URL: https://invariant-ai.com/blog/interconnection-queue-data  
Published: 2026-11-23 · Publisher: Invariant · Region: United States

Use Berkeley Lab’s Queued Up workbook for historical U.S. transmission interconnection requests, then check project status in the operator’s latest report for the relevant study cycle. In Kern County, California, one historical file showed 58 solar and storage requests as active at the end of 2025. California ISO’s November report matched 46. The other 12 appeared in its separate Cluster 15 workbook.

## Key points

- Match requests by operator and queue ID. Keep the report date and worksheet with the status.
- For a project near your site, confirm the proposed point of interconnection, net export requested and latest study or agreement.
- Read solar MW, battery MW and net MW at the point of interconnection as separate fields. A hybrid can list 250 MW for each resource and request just 250 MW of net export.

## Where to get U.S. interconnection queue data

An interconnection queue lists requests to connect to a power system. Use the annual Berkeley Lab release to compare territories and recover an earlier view of the pipeline. It covers generation and storage requests seeking transmission connection. Use the serving utility’s own process for distribution connections, and look up large customer loads through the relevant load-service process. ([Queued Up workbook and codebook](https://eta.lbl.gov/publications/queued-2026-edition-characteristics))

| Source | What to use it for | Where to check the status |
| --- | --- | --- |
| Berkeley Lab and GridTracker, Queued Up | Historical comparisons of requests across U.S. transmission operators. Includes a project workbook and codebook. | Use the original queue ID and archived year-end status, then open the operator report. ([Queued Up workbook and codebook](https://eta.lbl.gov/publications/queued-2026-edition-characteristics)) |
| California ISO | Individual queue IDs, study groups, reported dispositions and requested MW. | Check Cluster 14 and earlier, Cluster 15, or Cluster 16 according to the project. ([Operator report directory](https://www.caiso.com/generation-transmission/generation/generator-interconnection)) |
| PJM | Individual requests and study or agreement documents where posted. | Use the serial or cycle request list according to the project’s track. ([PJM service requests](https://www.pjm.com/planning/service-requests)) |
| ERCOT | Texas generation requests in the monthly Generator Interconnection Status report. | Record the monthly vintage and follow up with the transmission provider for project-specific documents. ([ERCOT generator queue](https://www.ercot.com/gridinfo/resource/index)) |

## What happened to 58 requests in Kern County?

We selected 58 California ISO rows from Berkeley Lab’s year-end 2025 data: 40 solar-plus-battery requests, 12 battery requests and six solar requests. Each had Kern as its reported county and active as its queue status. We matched the operator’s queue ID to each row and checked the county on both sides. California ISO publishes Cluster 15 separately from Cluster 14 and earlier. ([Queued Up workbook and codebook](https://eta.lbl.gov/publications/queued-2026-edition-characteristics)) ([Operator report directory](https://www.caiso.com/generation-transmission/generation/generator-interconnection))

| California ISO source | Matched requests | What the report showed |
| --- | --- | --- |
| Cluster 14 and earlier, run November 23, 2026 | 46 | 37 active, five completed and four withdrawn. ([Cluster 14 and earlier workbook](https://www.caiso.com/documents/publicqueuereport.xlsx)) |
| Cluster 15, posted July 16, 2026 | 12 | 11 listed on the Cluster 15 worksheet and one on its withdrawn worksheet. ([Cluster 15 workbook](https://www.caiso.com/documents/cluster-15-interconnection-requests.xlsx)) |

Two examples show why a dated match matters. Queue 1335 appears on the November completed sheet with an actual online date of July 22, 2026. Queue 2329 appears on the separate Cluster 15 withdrawn sheet with a withdrawal date of July 1. Without the Cluster 15 check, that second request would simply be missing from the legacy report. Keep July’s Cluster 15 listing date alongside those 11 matches when using the results. ([Cluster 14 and earlier workbook](https://www.caiso.com/documents/publicqueuereport.xlsx)) ([Cluster 15 workbook](https://www.caiso.com/documents/cluster-15-interconnection-requests.xlsx))

[Download the 58-request reconciliation with workbook row numbers (JSON)](https://invariant-ai.com/blog/kern-county-solar-storage-queue-status.json)

[Compare solar sites](https://invariant-ai.com/blog/solar-farm-site-selection-gis)

The download includes the match decisions, source sheet names, workbook row numbers and file hashes. It preserves missing dates as empty values. This is a follow-up on a fixed year-end cohort. A count of every current request in Kern County would also need newer applications and separate treatment for overlapping reports. ([Queued Up workbook and codebook](https://eta.lbl.gov/publications/queued-2026-edition-characteristics)) ([Operator report directory](https://www.caiso.com/generation-transmission/generation/generator-interconnection))

## Which MW figure belongs in a solar or storage screen?

The California ISO Cluster 16 workbook lists Airchair 1 under public project number 55357. It shows 250 MW of solar, 250 MW of battery storage and 250 MW net at the proposed connection. The project requests energy-only service and a May 2032 commercial operation date. For a site screen, record the 250 MW at the connection as requested export and keep the two resource figures for equipment and revenue analysis. ([Cluster 16 workbook](https://www.caiso.com/documents/cluster-16-queue-report.xlsx))

Before pricing a battery site, ask for the allowed grid import, discharge limit, charging hours and any curtailment or upgrade conditions in the study and agreement. When comparing sites around the same station, verify the actual bus or line segment. Then check what a withdrawal or later study changed before assuming the site can use the same amount of export.

**Verify the connection before committing land:** [Check battery charging and discharge conditions](https://invariant-ai.com/blog/battery-storage-site-interconnection) · [Check solar land and compare two dated PJM study estimates](https://invariant-ai.com/blog/solar-farm-site-selection-gis) · [Read load headroom and solar export ratings separately](https://invariant-ai.com/blog/grid-capacity-apis-load-headroom)

## How to evaluate an interconnection queue data API

Give each provider a fixed set of queue IDs, including a completed request, a withdrawal and a request in a separately published cluster. Compare the output with the operator’s original files. Check whether the response includes the study cycle and date, original status, point of interconnection, capacity units and the difference between a requested and an actual online date. A blank should stay blank when an older report or a different project key cannot establish the value.

Use Invariant Earth to assemble the parcel and mapped infrastructure evidence for prospective sites. Attach each operator record to its queue ID and retain each dated observation when the proposed connection or project status changes. Ask for the current study and agreement when the connection drives the price or schedule. ([Live Invariant Earth fields](https://api.invariant-ai.com/v1/meta/fields)) ([API source and date fields](https://docs.invariant-ai.com/responses))

## Questions

### Where can I download U.S. interconnection queue data?

Berkeley Lab and GridTracker’s Queued Up release provides the historical transmission generation and storage workbook. Check the original ISO, RTO or utility report for the latest information about a particular request. ([Queued Up workbook and codebook](https://eta.lbl.gov/publications/queued-2026-edition-characteristics)) ([Operator report directory](https://www.caiso.com/generation-transmission/generation/generator-interconnection)) ([PJM service requests](https://www.pjm.com/planning/service-requests)) ([ERCOT generator queue](https://www.ercot.com/gridinfo/resource/index))

### How do I look up a solar project by queue number?

Find its operator, then search its published queue report for the project’s study cycle. In California ISO, Cluster 15 and Cluster 16 have separate public reports. Save the operator, queue number, report date and original status. ([Operator report directory](https://www.caiso.com/generation-transmission/generation/generator-interconnection))

### Can I add solar and battery megawatts to calculate export at the grid connection?

Use the separately reported net MW at the connection when screening export. California ISO’s Airchair 1 request lists 250 MW of solar and 250 MW of storage with 250 MW net at the point of interconnection. Verify the studied or contracted limit for a commitment. ([Cluster 16 workbook](https://www.caiso.com/documents/cluster-16-queue-report.xlsx))

### What does a missing queue ID mean?

Check the coverage and vintage of the report before recording an outcome. In the Kern County comparison, 12 older snapshot IDs absent from one California ISO workbook all matched another workbook from the same operator. ([Queued Up workbook and codebook](https://eta.lbl.gov/publications/queued-2026-edition-characteristics)) ([Cluster 14 and earlier workbook](https://www.caiso.com/documents/publicqueuereport.xlsx)) ([Cluster 15 workbook](https://www.caiso.com/documents/cluster-15-interconnection-requests.xlsx))

## Sources

- Lawrence Berkeley National Laboratory and GridTracker: [Queued Up 2026 Edition, project-level data and codebook through December 31, 2025](https://eta.lbl.gov/publications/queued-2026-edition-characteristics)
- California ISO: [Generator interconnection reports and study-cluster scope](https://www.caiso.com/generation-transmission/generation/generator-interconnection)
- California ISO: [Public Queue Report, run November 23, 2026](https://www.caiso.com/documents/publicqueuereport.xlsx)
- California ISO: [Cluster 15 Queue Report, posted July 16, 2026](https://www.caiso.com/documents/cluster-15-interconnection-requests.xlsx)
- California ISO: [Cluster 16 Queue Report, posted October 16, 2026](https://www.caiso.com/documents/cluster-16-queue-report.xlsx)
- PJM: [Serial and Cycle Service Request Status coverage](https://www.pjm.com/planning/service-requests)
- ERCOT: [Monthly Generator Interconnection Status Report](https://www.ercot.com/gridinfo/resource/index)
- Invariant Earth: [Invariant Earth parcel and mapped infrastructure fields](https://api.invariant-ai.com/v1/meta/fields)
- Invariant Earth: [API response provenance and timestamps](https://docs.invariant-ai.com/responses)

## Related

- [Solar farm site selection with GIS and interconnection data](https://invariant-ai.com/blog/solar-farm-site-selection-gis)
- [Battery storage site selection for charging and discharge](https://invariant-ai.com/blog/battery-storage-site-interconnection)
- [Best Grid Capacity APIs for Load Headroom and Site Screening](https://invariant-ai.com/blog/grid-capacity-apis-load-headroom)
- [Best GIS APIs for U.S. site selection](https://invariant-ai.com/blog/best-gis-apis-for-site-selection)