# Manufacturing site selection for 100 buildable acres

> Find industrial sites with rail, water, wastewater and power. Use a South Carolina case to check parcel size, utility service, and what’s ready to build.

URL: https://invariant-ai.com/blog/manufacturing-site-selection-100-buildable-acres  
Published: 2026-11-22 · Publisher: Invariant · Region: United States

To find an industrial site with at least 100 buildable acres, start with state and utility site inventories and get the boundary of each tract actually on offer. Screen contiguous land, the path to rail, water and wastewater service, and phased utility power. Ask for a dated document behind each pass. A site can have enough total acres and still fail to fit the plant, yard, and rail siding in one usable layout.

## Key points

- Ask for 100 contiguous buildable acres with the footprint, yard, access and easements accounted for. Check availability on the same boundary you use for the layout.
- Ask the railroad and utilities to confirm the connection point, the required improvements and the date service can start.
- At Camp Hall Campus 9, a 2023 exhibit, a 2025 brochure and the listing reviewed in November 2026 show different acreage descriptions. The 120 listed available acres leave 20 acres above a 100-acre requirement before checking the layout.

## What to use for a first manufacturing shortlist

Use state and local economic development inventories to find candidate properties and the people who maintain their data. South Carolina’s LocateSC is one example. Start with the geography and your must-have traits, then get the current offering boundary, seller or option holder, and date behind each listing. Read the certification materials for any site advertised as certified. They tell you which studies were available for the program and what you can request. ([South Carolina Department of Commerce](https://www.sccommerce.com/news/sc-department-commerce-relaunches-locatesc-website)) ([South Carolina Department of Commerce](https://locatesc.sccommerce.com/palmetto-sites/documents/PalmettoSitesProgram-2026.pdf))

| Requirement | Where to start | What to request before committing |
| --- | --- | --- |
| 100 buildable acres | County parcel GIS, state site inventories, USGS terrain, mapped flood hazards and wetlands. | Current sale or lease boundary, survey, field delineation where needed, and a concept layout with required buffers and grading. ([South Carolina Department of Commerce](https://www.sccommerce.com/news/sc-department-commerce-relaunches-locatesc-website)) ([U.S. Geological Survey](https://www.usgs.gov/3d-elevation-program/about-3dep-products-services)) ([U.S. Fish and Wildlife Service](https://www.fws.gov/page/wetlands-data-limitations-exclusions-and-precautions)) ([FEMA](https://hazards.fema.gov/arcgis/rest/services/public/NFHL/MapServer/28)) |
| Freight rail | Bureau of Transportation Statistics rail network data, the carrier’s service map, and the industrial park’s track plan. | Serving carrier, usable siding or turnout, switching plan, railcar volume the carrier can handle, and a schedule for service or needed construction. ([Bureau of Transportation Statistics](https://rosap.ntl.bts.gov/view/dot/53568)) ([Palmetto Railways](https://palmettorailways.com/industrial-development/)) |
| Process water | Utility service-area maps, site utility plans, and the water provider’s records. | Tie-in location, available average and peak flow, pressure and fire flow, water quality, cost, and service date. ([Camp Hall](https://www.camphall.com/wp-content/uploads/2025/01/Campus_9_Camp_Hall_01.2025__1_.pdf)) ([Berkeley County Water and Sanitation](https://bcws.berkeleycountysc.gov/wp-content/uploads/Procedure-for-Requesting-Availability-Letters-for-Building-Permits.pdf)) |
| Industrial wastewater | The receiving sewer utility and its industrial pretreatment program, or the applicable discharge permitting authority. | Accepted flow and characteristics of the proposed waste stream, pretreatment needs, pump or line upgrades, and the applicable approval. ([U.S. EPA](https://www.epa.gov/npdes/pretreatment-standards-and-requirements-local-limits)) ([Berkeley County Water and Sanitation](https://bcws.berkeleycountysc.gov/wp-content/uploads/Procedure-for-Requesting-Availability-Letters-for-Building-Permits.pdf)) |
| Electric service | Serving utility and transmission owner, mapped facilities, and public project or study records. | MW by phase, point of service, supply and reliability terms, required upgrades, cost responsibility, and service dates. ([Camp Hall](https://www.camphall.com/sites/campus-9/)) ([Camp Hall](https://www.camphall.com/wp-content/uploads/2018/03/Campus_9-Exhibit-2-21-2023.pdf)) |

## How to test the 100-acre requirement

Start with the surveyed or proposed tract boundary. Map where the layout can’t go, including relevant wetlands and setbacks, recorded easements, terrain outside the grading plan, and road or utility corridors. Examine overlapping exclusions together so you subtract each area once. Then keep the geometry and area of each connected piece. The areas you can use for circulation, utilities, and drainage depend on the design and any applicable approval. ([U.S. Geological Survey](https://www.usgs.gov/3d-elevation-program/about-3dep-products-services)) ([U.S. Fish and Wildlife Service](https://www.fws.gov/page/wetlands-data-limitations-exclusions-and-precautions)) ([FEMA](https://hazards.fema.gov/arcgis/rest/services/public/NFHL/MapServer/28)) ([South Carolina Department of Commerce](https://locatesc.sccommerce.com/palmetto-sites/documents/PalmettoSitesProgram-2026.pdf))

For example, a site could have 110 acres left after exclusions in two blocks of 65 and 45 acres. Its largest block is 65 acres. A project that needs 100 contiguous acres needs a different layout or a different tract. Put the proposed building, laydown and truck yards, loading tracks, and access routes on the plan before clearing the acreage requirement.

## Camp Hall Campus 9 has three acreage descriptions

Camp Hall’s Campus 9 page links both an older site exhibit and a marketing brochure. We checked the listing and both files for the area each actually describes. The PDFs give overall acreage for the land they depict. The listing distinguishes the original developable acreage from the acres sold and those it still offers. ([Camp Hall](https://www.camphall.com/sites/campus-9/)) ([Camp Hall](https://www.camphall.com/wp-content/uploads/2018/03/Campus_9-Exhibit-2-21-2023.pdf)) ([Camp Hall](https://www.camphall.com/wp-content/uploads/2025/01/Campus_9_Camp_Hall_01.2025__1_.pdf))

| Record | Figure | What the figure describes |
| --- | --- | --- |
| Site exhibit · February 2023 | 90.94 acres | The overall total printed on the exhibit. It also shows a separately labeled parcel and a utility service territory boundary. ([Camp Hall](https://www.camphall.com/wp-content/uploads/2018/03/Campus_9-Exhibit-2-21-2023.pdf)) |
| Campus 9 brochure · January 2025 | 124.3 acres | The overall acreage described for parcels 6 and 7. The brochure also describes water, sewer, and roads as work in progress for the site. ([Camp Hall](https://www.camphall.com/wp-content/uploads/2025/01/Campus_9_Camp_Hall_01.2025__1_.pdf)) |
| Site listing · checked November 22, 2026 | 120 acres | The acreage the owner lists as available. It reports 147 original developable acres and 27 sold. ([Camp Hall](https://www.camphall.com/sites/campus-9/)) |

The 120 available acres give a 20-acre margin over a 100-acre requirement on paper. Ask the owner for the current boundary of the 120 acres and the survey or acreage calculation behind it. Run the project layout on that boundary. The older exhibit and brochure help explain why a site name alone is an unreliable key for acreage.

The utility evidence has its own dates. The brochure describes a 12-inch water line design along Camp Hall Boulevard. The listing says water and sewer are in place and its site details describe adjacency to a future substation. The older exhibit shows two electric service territories. These records provide leads for provider calls. Confirm the connection applicable to the offered tract and ask for the capacity and service date in writing. ([Camp Hall](https://www.camphall.com/wp-content/uploads/2025/01/Campus_9_Camp_Hall_01.2025__1_.pdf)) ([Camp Hall](https://www.camphall.com/wp-content/uploads/2018/03/Campus_9-Exhibit-2-21-2023.pdf)) ([Camp Hall](https://www.camphall.com/sites/campus-9/)) ([Berkeley County Water and Sanitation](https://bcws.berkeleycountysc.gov/wp-content/uploads/Procedure-for-Requesting-Availability-Letters-for-Building-Permits.pdf))

Palmetto Railways describes a 25-mile corridor connecting the commerce park to the CSX main line, with construction through fall 2026 on the page we reviewed. For a rail-served plant, ask if the corridor is in service and whether the railroad can accept and switch the proposed cars to the tract. Get the location and status of the siding or proposed turnout and the scope of any connection work. ([Palmetto Railways](https://palmettorailways.com/industrial-development/))

[Download the Camp Hall evidence and source links (JSON)](https://invariant-ai.com/blog/manufacturing-site-selection-100-buildable-acres.json)

[Screen a site with the API](https://docs.invariant-ai.com/screen-a-site)

## What to verify before paying for an option

Send the same requirements to each site contact. Include the minimum contiguous area, what needs to fit, railcar types and volumes, water and wastewater needs, and the MW and dates for each phase. Put the evidence next to each site in the shortlist. Use a current drawing for the property, a carrier response for rail, and utility responses for service and timeline. Record who can answer each open question and when the buyer needs the answer.

**Related site diligence guides:** [Compare manufacturing jobs and industry concentration by county](https://invariant-ai.com/blog/county-manufacturing-employment-data) · [Use the site selection due diligence checklist](https://invariant-ai.com/blog/site-selection-due-diligence) · [Compare GIS APIs for U.S. site selection](https://invariant-ai.com/blog/best-gis-apis-for-site-selection) · [Find industrial permits and enforcement records](https://invariant-ai.com/blog/industrial-environmental-permit-history-by-parcel) · [Check documents behind a site’s stated power capacity](https://invariant-ai.com/blog/power-evidence-data-center-site-verification) · [Verify what a certified industrial site is ready for](https://invariant-ai.com/blog/shovel-ready-industrial-site-checklist) · [Verify rail service, truck access and trailer parking at a warehouse](https://invariant-ai.com/blog/warehouse-site-selection-rail-truck-access)

## Questions

### How do I find industrial sites with 100 buildable acres?

Use state and local industrial property inventories to find tracts above your minimum. Get the exact offered boundary and subtract exclusions using a project-specific layout. Measure the largest contiguous usable block and verify that it’s available. ([South Carolina Department of Commerce](https://www.sccommerce.com/news/sc-department-commerce-relaunches-locatesc-website)) ([South Carolina Department of Commerce](https://locatesc.sccommerce.com/palmetto-sites/documents/PalmettoSitesProgram-2026.pdf)) ([Camp Hall](https://www.camphall.com/sites/campus-9/))

### What does rail access mean on an industrial site listing?

A listing may refer to a nearby line, a planned corridor, or an active siding. Confirm the route and carrier for the exact tract, whether the siding can be used, switching terms, and the date the carrier can start service. ([Bureau of Transportation Statistics](https://rosap.ntl.bts.gov/view/dot/53568)) ([Palmetto Railways](https://palmettorailways.com/industrial-development/))

### How do I check water and sewer capacity for a factory site?

Ask the water provider for the allocated flow, pressure, and connection date. Send the sewer authority the proposed flow and wastewater characteristics so it can identify treatment and pretreatment requirements. Keep the written utility response with the site layout and schedule. ([Berkeley County Water and Sanitation](https://bcws.berkeleycountysc.gov/wp-content/uploads/Procedure-for-Requesting-Availability-Letters-for-Building-Permits.pdf)) ([U.S. EPA](https://www.epa.gov/npdes/pretreatment-standards-and-requirements-local-limits))

## Sources

- South Carolina Department of Commerce: [LocateSC property search and site data](https://www.sccommerce.com/news/sc-department-commerce-relaunches-locatesc-website)
- South Carolina Department of Commerce: [Palmetto Sites Program, 2026](https://locatesc.sccommerce.com/palmetto-sites/documents/PalmettoSitesProgram-2026.pdf)
- U.S. Geological Survey: [3D Elevation Program products and services](https://www.usgs.gov/3d-elevation-program/about-3dep-products-services)
- U.S. Fish and Wildlife Service: [Wetlands mapping limitations and exclusions](https://www.fws.gov/page/wetlands-data-limitations-exclusions-and-precautions)
- FEMA: [National Flood Hazard Layer map service](https://hazards.fema.gov/arcgis/rest/services/public/NFHL/MapServer/28)
- Bureau of Transportation Statistics: [North American Rail Network data](https://rosap.ntl.bts.gov/view/dot/53568)
- Palmetto Railways: [Camp Hall Industrial Corridor status and planned main-line connection](https://palmettorailways.com/industrial-development/)
- Berkeley County Water and Sanitation: [Procedure for requesting water and sewer availability letters](https://bcws.berkeleycountysc.gov/wp-content/uploads/Procedure-for-Requesting-Availability-Letters-for-Building-Permits.pdf)
- U.S. EPA: [Local limits for industrial wastewater pretreatment](https://www.epa.gov/npdes/pretreatment-standards-and-requirements-local-limits)
- Camp Hall: [Campus 9 site exhibit, February 2023](https://www.camphall.com/wp-content/uploads/2018/03/Campus_9-Exhibit-2-21-2023.pdf)
- Camp Hall: [Campus 9 brochure, January 2025](https://www.camphall.com/wp-content/uploads/2025/01/Campus_9_Camp_Hall_01.2025__1_.pdf)
- Camp Hall: [Campus 9 site listing and property resources](https://www.camphall.com/sites/campus-9/)

## Related

- [Best GIS APIs for U.S. site selection](https://invariant-ai.com/blog/best-gis-apis-for-site-selection)
- [Environmental permits and enforcement by parcel](https://invariant-ai.com/blog/industrial-environmental-permit-history-by-parcel)
- [Data center power verification: the five rungs of evidence that a site can be powered](https://invariant-ai.com/blog/power-evidence-data-center-site-verification)