# Build, lease or colocate: how neoclouds and AI labs get to power fastest

> Build vs lease vs colocate for neoclouds and AI labs: time to power, capital, control and risk at 5, 50 and 500 MW, and when to move from one to the next.

URL: https://invariant-ai.com/blog/neocloud-build-lease-or-colocate  
Published: 2026-11-20 · Publisher: Invariant · Region: United States

For a neocloud or AI lab, colocation gets you running fastest with the least capital, leasing a whole building or site gives you control at medium scale, and building on powered land gives the lowest long-run cost per MW but the longest wait and the most risk. The deciding variable is the date power is available, which is why the right choice changes with size: colocation below about 5 MW, a lease from about 5 to 50 MW, and building above that.

## Key points

- Time to power usually beats price per kW. Idle GPUs cost far more than rent.
- Building means owning the utility relationship, the large-load tariff and its minimum bill.
- Leasing moves the power risk to the landlord, but only if the lease says so.
- Many neoclouds do all three at once: colo for today, a lease for next year, land for 2028.

## The trade-offs

|  | Colocate | Lease a building or site | Build on powered land |
| --- | --- | --- | --- |
| Typical size | Up to about 10 MW | About 5 to 100 MW | 50 MW to 1 GW+ |
| Time to power | Weeks to months | Months | Usually 18 months or more |
| Capital | Lowest | Fit-out and equipment | Highest |
| Control over design | Low | Medium | Full |
| Who holds the power risk | Provider | Landlord, if the lease says so | You |
| Utility commitments | None directly | Often passed through | Minimum bill, term, security |

Sources: ([Lawrence Berkeley National Laboratory and The Brattle Group](https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf))

## When building makes sense

Owning the power pays off once the cluster is big and long-lived enough to absorb a long utility term. New large-load tariffs set minimum bills near 80 to 85% of contract demand for 12 years or more, so you need the demand to fill it. ([Lawrence Berkeley National Laboratory and The Brattle Group](https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf)) ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff))

Building also means a utility study cycle. In Texas, large loads now go through ERCOT’s batch process; elsewhere, a load study can take months before construction starts. ([Willkie Farr & Gallagher](https://www.willkie.com/publications/2026/06/ercot-approves-implementing-new-batch-zero-process-for-large-load-interconnections))

## On-site generation as a shortcut

Some neoclouds bridge to grid power with on-site gas. It can work, but it has its own clock: turbines, air permits and gas supply. Cleanview counted only about 2 GW running out of some 90 GW of identified behind-the-meter projects. ([Cleanview](https://cleanview.co/reports/behind-the-meter-data-centers/full-report)) ([US EPA](https://www.epa.gov/title-v-operating-permits/who-has-obtain-title-v-permit))

## More for neoclouds and AI labs

**For neoclouds and AI labs:** [Capacity for neoclouds and AI labs](https://invariant-ai.com/blog/ai-compute-capacity-for-neoclouds) · [How much power a GPU cluster needs](https://invariant-ai.com/blog/gpu-cluster-power-requirements) · [GPU colocation: what to ask a provider](https://invariant-ai.com/blog/gpu-colocation-for-ai-labs) · [Liquid cooling for 40 to 130 kW racks](https://invariant-ai.com/blog/liquid-cooling-gpu-data-center) · [Where to put 1 to 10 MW of GPUs](https://invariant-ai.com/blog/small-gpu-cluster-1-to-10-mw) · [Power longstop dates in GPU leases](https://invariant-ai.com/blog/gpu-lease-power-longstop-diligence) · [Power check on a provider or site](https://invariant-ai.com/blog/provider-power-check-for-ai-tenants)

**Sites and power:** [AI data center sites](https://invariant-ai.com/blog/ai-data-center-site) · [Energized sites available now](https://invariant-ai.com/blog/energized-data-center-sites-available-now) · [Built data centers for sale and lease](https://invariant-ai.com/blog/data-center-for-sale) · [10 MW data center site](https://invariant-ai.com/blog/10-mw-data-center-site) · [100 MW data center site](https://invariant-ai.com/blog/100-mw-data-center-site) · [Converting a mining site to AI](https://invariant-ai.com/blog/convert-bitcoin-mining-site-to-ai-hpc-data-center) · [Behind-the-meter power](https://invariant-ai.com/blog/behind-the-meter-power-for-data-centers) · [Utility-grade power study](https://invariant-ai.com/blog/utility-grade-power-study) · [Site due diligence](https://invariant-ai.com/blog/data-center-site-due-diligence)

## Questions

### Should a neocloud build its own data center?

Usually only once it needs tens of MW or more for many years. Below that, colocation or leasing gets to power faster with less capital and less utility risk.

### Is it faster to lease or build data center capacity?

Leasing an energized building or site is usually months; building on powered land is usually 18 months or more, set by the utility date and long-lead equipment.

### What does it cost to commit to utility power for a data center?

Beyond construction, large-load tariffs set minimum bills near 80 to 85% of contract demand for 12 years or more. ([Lawrence Berkeley National Laboratory and The Brattle Group](https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf)) ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff))

### Can Invariant help us decide?

Yes. Send the cluster plan and dates and we lay out the options we can source in each route.

## Sources

- Cleanview: [Behind-the-meter data centers: full report](https://cleanview.co/reports/behind-the-meter-data-centers/full-report)
- Lawrence Berkeley National Laboratory and The Brattle Group: [Electricity rate designs for large loads (August 2026)](https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf)
- Willkie Farr & Gallagher: [ERCOT approves new Batch Zero process for large load interconnections](https://www.willkie.com/publications/2026/06/ercot-approves-implementing-new-batch-zero-process-for-large-load-interconnections)
- AEP Ohio: [Data center tariff](https://www.aepohio.com/company/about/rates/data-center-tariff)
- US EPA: [Who has to obtain a Title V permit](https://www.epa.gov/title-v-operating-permits/who-has-obtain-title-v-permit)

## Related

- [Data center capacity for neoclouds and AI labs: power, space and cooling for your GPUs (2026)](https://invariant-ai.com/blog/ai-compute-capacity-for-neoclouds)
- [Power longstop dates in GPU and data center leases: check the provider’s power before you sign](https://invariant-ai.com/blog/gpu-lease-power-longstop-diligence)