# Powered Shell vs. Turnkey Data Center: Power, Fit-Out and Rent

> Compare powered shell and turnkey data centers by utility MW, critical IT load, fit-out scope, commissioning, and rent commencement. See what to ask before you sign.

URL: https://invariant-ai.com/blog/powered-shell-vs-turnkey-data-center  
Published: 2026-11-24 · Publisher: Invariant · Region: United States

A powered shell typically includes a building and a path to electrical service. The tenant takes responsibility for some or all of the interior fit-out. In a turnkey data center, the provider delivers the electrical, cooling and safety systems required to operate the contracted data hall. Before comparing quotes, get both offers in terms of the same deliverable: critical IT capacity accepted for use by a specific date.

## Key points

- Ask where each MW figure is measured. Service at the meter, capacity backed by an uninterruptible power supply, and critical IT load available in a hall describe different parts of the facility.
- Request the lease exhibit that assigns each piece of equipment, the acceptance test, and the date that starts rent.
- Price phased deliveries separately. A campus can be under lease, drawing power, and accepting IT load in different buildings at the same time.

## [What is included in each delivery?](<https://invariant-ai.com/blog/powered-shell-vs-turnkey-data-center#compare-delivery-scope>)

Prince William County’s assessment report describes a powered shell as a building with access to power and connectivity where the tenant completes the interior build-out. Its turnkey category covers fully built and equipped facilities. Those categories give you a starting point. Use the deal documents to assign the actual work, including who owns or removes installed fixtures when the lease expires. ([Prince William County Department of Finance](<https://www.pwcva.gov/assets/2025-06/Prince%20William%20County%202024%20Data%20Center%20Revenue%20Report.pdf>))

| What to check | Powered shell | Turnkey data center |
| --- | --- | --- |
| Power handoff | Confirm utility service size, delivery date and the exact point where landlord-provided equipment ends. | Confirm accepted critical IT load at the contractual handoff, by hall and delivery phase. |
| Electrical and cooling fit-out | Assign switchgear, UPS, backup generation, cooling, controls and rack power distribution to named parties. | Check included redundancy, allowed rack density, cooling method and any tenant-specific equipment or design changes. |
| Acceptance | Check shell sign-off and the date the tenant can begin work. Track commissioning and occupancy for the finished hall separately. | Request the agreed commissioning results, occupancy evidence for the hall and signed acceptance for the capacity being delivered. |
| Commercial terms | Identify which party funds and owns the fit-out, when rent begins, and whether the tenant reimburses the landlord for work. | Confirm the billable kW, delivery-by-phase terms, power charges, and which services are included in base rent. |

## [A marketed 22.8 MW shell still has a delivery question](<https://invariant-ai.com/blog/powered-shell-vs-turnkey-data-center#read-shell-power-evidence>)

A Five 9s Digital brochure markets a 50,000-square-foot shell in South Carolina with 22.8 MW of near-term power. It estimates about three months from application to bringing power from a substation to the building. That describes a broker’s service estimate. Ask for the utility’s written allocation for this building, the start date of the estimate, the equipment and work on each side of the meter, and the resulting IT capacity in the proposed design. ([Five 9s Digital](<https://assets.ctfassets.net/o03ihmgd94o7/6MkAEiSrKEU0bFZl8IVOAH/19123861cd950dd2fd37ae56f4fb3b7f/SC_Powered_Data_Center_Shell.pdf>))

Public records can help you find the property and establish which work was permitted. Prince William County’s data center process, for example, shows separate shell approvals, trade and fire inspections, and an option for temporary occupancy by phase. Its assessment report also estimates about 400 MW across the powered-shell inventory from floor area and a market density assumption. Use that portfolio estimate for context and ask the utility for service evidence for the actual building. ([Prince William County Building Development](<https://www.pwcva.gov/assets/2021-04/New%20Structure%20Data%20Center%20Building%20Flow%20Chart.pdf>)) ([Prince William County Department of Finance](<https://www.pwcva.gov/assets/2025-06/Prince%20William%20County%202024%20Data%20Center%20Revenue%20Report.pdf>))

## [What changed when Lake Mariner amended its fit-out terms?](<https://invariant-ai.com/blog/powered-shell-vs-turnkey-data-center#follow-fit-out-to-rent>)

TeraWulf’s August 2026 presentation says July 5 amendments for buildings CB-3, CB-4 and CB-5 at Lake Mariner changed delivery timing and how tenant-requested fit-out was paid. TeraWulf said it would fund about $150 million of fit-out costs incurred through June 30 and recover the covered work through rent. It also said the tenant would pay cash, plus an agreed margin, for fit-out costs incurred after July 5. The rent comparison changes once you know who advanced the money and which costs the rent covers. ([TeraWulf](<https://www.sec.gov/Archives/edgar/data/1083301/000108330126000162/terawulfq22026investorpr.htm>))

At September 30, TeraWulf reported 438 MW of contracted critical IT capacity at Lake Mariner, with 102 MW in operation and generating revenue. Its November release identified another 336 MW under construction across CB-4 and CB-5. Those records give three useful measures for a transaction review: the contracted total, the amount already operating, and the work remaining. For a specific offer, get the corresponding handoff and rent schedule by hall. ([TeraWulf](<https://www.sec.gov/Archives/edgar/data/1083301/000162828026071671/wulf-20260930.htm>)) ([TeraWulf](<https://www.sec.gov/Archives/edgar/data/1083301/000162828026071306/a_wulfearningsreleaseq32026.htm>))

[Download the shell and fit-out evidence CSV (CSV)](https://invariant-ai.com/blog/data-center-shell-and-fit-out-evidence.csv)

[Download citation (CSL JSON)](https://invariant-ai.com/citations/powered-shell-vs-turnkey-data-center.dataset.csl.json)

[Request a data center site search](https://invariant-ai.com/blog/data-center-site-selection-services)

## [How do you compare two quotes per usable IT kilowatt?](<https://invariant-ai.com/blog/powered-shell-vs-turnkey-data-center#compare-offers-per-it-kw>)

Start with one delivery requirement, such as 8 MW of accepted critical IT load in the first phase. In an illustrative comparison, a shell priced at $75 per month per kW of 10 MW of gross building service bills $750,000 a month before fit-out and other charges. A fitted offer priced at $125 per month per kW of 8 MW of IT capacity bills $1 million a month before additional charges. Confirm the shell design can support the required 8 MW, then compare tenant capital, early rent during construction, energy and operating charges, and the date each option can carry the workload. The prices here are examples for calculating the billing basis.

| Evidence to request | What it should tell you |
| --- | --- |
| Utility service agreement and electrical one-line | Service boundary, actual MW and date for the phase, with equipment and work needed to reach the IT handoff. |
| Landlord and tenant scope exhibit | Who designs, buys, installs, owns, maintains and replaces each major system, with tenant allowances or reimbursements. |
| Commissioning and occupancy package | Which hall and conditions were tested, which exceptions remain, and what the jurisdiction approved for occupancy. |
| Lease delivery and rent schedule | The acceptance date and billable capacity by hall, the rent trigger, and the parties’ remedies for late or partial delivery. |

**Compare live options:** [Find facilities and development sites by power and date](https://invariant-ai.com/blog/find-data-center-site-us) · [Compare fitted facilities and powered shells for sale](https://invariant-ai.com/blog/data-center-for-sale) · [Compare current lease leads and the power they advertise](https://invariant-ai.com/blog/data-center-space-for-lease) · [Check what the utility service documents establish](https://invariant-ai.com/blog/utility-will-serve-letter-load-study-esa)

## [Questions](<https://invariant-ai.com/blog/powered-shell-vs-turnkey-data-center#questions>)

### Does a powered shell already have power?

Some shells have energized service. Others are marketed with a utility delivery path or proposed upgrades. Ask for the MW allocated to the specific building, the service date and the utility document or meter evidence that supports it. ([Five 9s Digital](<https://assets.ctfassets.net/o03ihmgd94o7/6MkAEiSrKEU0bFZl8IVOAH/19123861cd950dd2fd37ae56f4fb3b7f/SC_Powered_Data_Center_Shell.pdf>))

### Does turnkey mean I can deploy my servers immediately?

Confirm acceptance of the specific hall, its critical IT load, available cooling at your rack density, and the occupancy approvals. A fitted facility can still be under construction, partly delivered or reserved for another tenant. ([Prince William County Building Development](<https://www.pwcva.gov/assets/2021-04/New%20Structure%20Data%20Center%20Building%20Flow%20Chart.pdf>)) ([TeraWulf](<https://www.sec.gov/Archives/edgar/data/1083301/000162828026071671/wulf-20260930.htm>)) ([TeraWulf](<https://www.sec.gov/Archives/edgar/data/1083301/000162828026071306/a_wulfearningsreleaseq32026.htm>))

### When does rent start on a data center lease?

The lease sets the trigger. Check whether rent starts at shell delivery, an agreed date, or acceptance of each hall. Read the amendments too, since fit-out scope and delivery dates can change after signing. ([TeraWulf](<https://www.sec.gov/Archives/edgar/data/1083301/000108330126000162/terawulfq22026investorpr.htm>)) ([TeraWulf](<https://www.sec.gov/Archives/edgar/data/1083301/000162828026071671/wulf-20260930.htm>))

## [Sources](<https://invariant-ai.com/blog/powered-shell-vs-turnkey-data-center#sources>)

- Prince William County Department of Finance: [2024 Data Center Revenue Report, assessment classifications and Table 2](<https://www.pwcva.gov/assets/2025-06/Prince%20William%20County%202024%20Data%20Center%20Revenue%20Report.pdf>)
- Prince William County Building Development: [New data center building review and phased occupancy process](<https://www.pwcva.gov/assets/2021-04/New%20Structure%20Data%20Center%20Building%20Flow%20Chart.pdf>)
- Five 9s Digital: [South Carolina Powered Shell, building and power sections](<https://assets.ctfassets.net/o03ihmgd94o7/6MkAEiSrKEU0bFZl8IVOAH/19123861cd950dd2fd37ae56f4fb3b7f/SC_Powered_Data_Center_Shell.pdf>)
- TeraWulf: [Q2 2026 earnings presentation, Lake Mariner lease amendments](<https://www.sec.gov/Archives/edgar/data/1083301/000108330126000162/terawulfq22026investorpr.htm>)
- TeraWulf: [Form 10-Q for September 30, 2026, Lake Mariner and HPC lease revenue](<https://www.sec.gov/Archives/edgar/data/1083301/000162828026071671/wulf-20260930.htm>)
- TeraWulf: [Q3 2026 earnings release, Lake Mariner delivery update](<https://www.sec.gov/Archives/edgar/data/1083301/000162828026071306/a_wulfearningsreleaseq32026.htm>)

## Related

- [U.S. Data Centers for Sale and Lease](https://invariant-ai.com/blog/data-center-for-sale)
- [Find a Data Center Site in the U.S. | Powered Land and Facilities](https://invariant-ai.com/blog/find-data-center-site-us)
- [GPU colocation for AI labs and neoclouds: what to ask a provider before you sign](https://invariant-ai.com/blog/gpu-colocation-for-ai-labs)
- [Will-serve letter vs. load study vs. electric service agreement](https://invariant-ai.com/blog/utility-will-serve-letter-load-study-esa)

---

Site screens and power studies: pranav@invariant-ai.com, (628) 220-8972, https://cal.com/pranav-goswami/website-30min