  "name": "San José Data Center 04 grading and settlement records",
  "description": "A 2020 fill settlement analysis and the applicant’s 2025 grading and foundation proposal for two data center buildings and a substation in San José. Includes original docket identifiers and PDF pages.",
  "date_published": "2026-11-26",
  "project": {
    "name": "San José Data Center 04 (SJ04)",
    "docket": "22-SPPE-02",
    "docket_url": "https://efiling.energy.ca.gov/Lists/DocketLog.aspx?docketnumber=22-SPPE-02",
    "project_url": "https://www.energy.ca.gov/powerplant/backup-generating-system/san-jose-data-center-04",
    "parcels_listed_by_cec": [
      "101-02-019",
      "101-02-020"
    ],
    "location": "Orchard Parkway and Component Drive, San José, California"
  },
  "records": [
    {
      "kind": "geotechnical_analysis",
      "author": "Terracon",
      "report_project": "Bay AZ1 Site (Northtown)",
      "report_id": "ND205079",
      "document_date": "2020-12-15",
      "docketed_date": "2022-09-09",
      "cec_transaction_number": "245955",
      "original_document": "https://efiling.energy.ca.gov/GetDocument.aspx?DocumentContentId=80141&tn=245955",
      "original_sha256": "e9eabbc318217eb0e4e301563fe9995f07d0e4f3be1549c40335c67e312997de",
      "printed_pages": [
        5,
        6,
        7
      ],
      "pdf_pages_one_based": [
        10,
        11,
        12
      ],
      "assumed_engineered_fill_unit_weight_lb_per_cubic_foot": 120,
      "settlement_cases": [
        {
          "area": "Building 1",
          "added_fill_ft": 10,
          "fill_load_lb_per_sq_ft": 1200,
          "estimated_total_settlement_from_fill_in": 6,
          "estimated_months_for_approximate_90_percent_clay_settlement": [
            6,
            6
          ]
        },
        {
          "area": "Building 2",
          "added_fill_ft": 10,
          "fill_load_lb_per_sq_ft": 1200,
          "estimated_total_settlement_from_fill_in": 5.5,
          "estimated_months_for_approximate_90_percent_clay_settlement": [
            4,
            5
          ]
        },
        {
          "area": "Substation",
          "added_fill_ft": 3,
          "fill_load_lb_per_sq_ft": 360,
          "estimated_total_settlement_from_fill_in": 2.5,
          "estimated_months_for_approximate_90_percent_clay_settlement": [
            4,
            4
          ]
        }
      ],
      "settlement_table_exclusions": [
        "liquefaction",
        "structural loads"
      ],
      "recommended_fill_monitoring": "survey at least monthly until settlement from fill is confirmed complete"
    },
    {
      "kind": "applicant_project_description",
      "author": "Microsoft Corporation",
      "revision": 4,
      "document_month": "2025-07",
      "docketed_date": "2025-07-14",
      "cec_transaction_number": "264764",
      "original_document": "https://efiling.energy.ca.gov/GetDocument.aspx?DocumentContentId=101543&tn=264764",
      "original_sha256": "563f388083b5531f22c3bfcfdd182212e3452fae97a1888d3d8ce5467bbbc182",
      "printed_pages": [
        16,
        19
      ],
      "pdf_pages_one_based": [
        17,
        20
      ],
      "grading_fill_import_expected": false,
      "soil_export_cubic_yards_conservative_upper_assumption": 106067,
      "soil_export_scope": "Includes potential remediation and recycled-water-pipeline excess soil as stated in the project description.",
      "anticipated_building_pile_depth_below_existing_grade_ft": 80,
      "flood_conveyance": "The proposal keeps finished grades near existing levels in roughly the western third to pass shallow floodwater."
    }
  ],
  "scope": "Published design history and modeled values. Field measurements, actual construction dates, and current contractor quantities require separate project records."
}