  "title": "Nottingham solar interconnection study comparison",
  "source_publisher": "PJM Interconnection",
  "source_cycle": "Transition Cycle 2",
  "source_retrieved_date": "2026-11-22",
  "selection_method": "Select the two requests listed together at Nottingham 138 kV in PJM’s Phase II cycle summary. Record the study version and extract General and Cost Summary values from each request’s Phase I and Phase II reports. Use the published Total in the project allocation column.",
  "cluster_summary_url": "https://www.pjm.com/pjmfiles/pub/planning/project-queues/Cluster-Reports/TC2/TC2_PH2_Executive_Summary.htm",
  "point_of_interconnection": {
    "name": "Nottingham",
    "voltage_kv": 138,
    "county": "Harrison",
    "state": "Ohio"
  },
  "developer_as_reported": "Energy Pastures Solar Project, LLC",
  "requests": [
    {
      "queue_id": "AG2-082",
      "request_type": "original_request",
      "uprates_queue_id": null,
      "phase_two_minus_phase_one_allocated_cost_usd": 1838556,
      "studies": [
        {
          "phase": 1,
          "report_version": "1.00",
          "published_date": "2025-10-29",
          "base_case_year": 2028,
          "source_url": "https://www.pjm.com/pjmfiles/pub/planning/project-queues/TC2/PHASE_1/AG2-082/AG2-082_imp_PHASE_1.htm",
          "source_sha256": "60378524850df0fed702fee2db57ad92fcf3d35fe4bc925b45f7ad0239d5fff4",
          "maximum_facility_output_mw": 200.0,
          "requested_energy_mw": 200.0,
          "studied_capacity_mw": 133.4,
          "allocated_cost_usd_as_printed": 2326000,
          "selected_allocated_cost_components_usd": {
            "transmission_owner_interconnection_facilities": 0,
            "other_scope": 0,
            "stand_alone_network_upgrades": 0,
            "network_upgrades": 2326000
          }
        },
        {
          "phase": 2,
          "report_version": "1.00",
          "published_date": "2026-06-03",
          "base_case_year": 2028,
          "source_url": "https://www.pjm.com/pjmfiles/pub/planning/project-queues/TC2/PHASE_2/AG2-082/AG2-082_imp_PHASE_2.htm",
          "source_sha256": "cf9a7e56856635fdf4e9d6f01731e987f94bdbb6ffb9a224abd6151c5653ff9e",
          "maximum_facility_output_mw": 200.0,
          "requested_energy_mw": 200.0,
          "studied_capacity_mw": 133.4,
          "allocated_cost_usd_as_printed": 4164556,
          "selected_allocated_cost_components_usd": {
            "transmission_owner_interconnection_facilities": 609937,
            "other_scope": 375078,
            "stand_alone_network_upgrades": 172684,
            "network_upgrades": 3006856
          }
        }
      ]
    },
    {
      "queue_id": "AH1-580",
      "request_type": "uprate",
      "uprates_queue_id": "AG2-082",
      "phase_two_minus_phase_one_allocated_cost_usd": 3658540,
      "studies": [
        {
          "phase": 1,
          "report_version": "1.00",
          "published_date": "2025-10-29",
          "base_case_year": 2028,
          "source_url": "https://www.pjm.com/pjmfiles/pub/planning/project-queues/TC2/PHASE_1/AH1-580/AH1-580_imp_PHASE_1.htm",
          "source_sha256": "9ec6c620c21946562e4441b055b96c23b6a5a40b36a75194df8d849ae2e91924",
          "maximum_facility_output_mw": 400.0,
          "requested_energy_mw": 200.0,
          "studied_capacity_mw": 134.0,
          "allocated_cost_usd_as_printed": 2678000,
          "selected_allocated_cost_components_usd": {
            "transmission_owner_interconnection_facilities": 0,
            "other_scope": 352000,
            "stand_alone_network_upgrades": 0,
            "network_upgrades": 2326000
          }
        },
        {
          "phase": 2,
          "report_version": "1.00",
          "published_date": "2026-06-03",
          "base_case_year": 2028,
          "source_url": "https://www.pjm.com/pjmfiles/pub/planning/project-queues/TC2/PHASE_2/AH1-580/AH1-580_imp_PHASE_2.htm",
          "source_sha256": "63b8948705c5be2bf085716d3da4d41f3fe76a730a8f655b5358cf4e77f310d8",
          "maximum_facility_output_mw": 400.0,
          "requested_energy_mw": 200.0,
          "studied_capacity_mw": 134.0,
          "allocated_cost_usd_as_printed": 6336540,
          "selected_allocated_cost_components_usd": {
            "transmission_owner_interconnection_facilities": 609937,
            "other_scope": 978970,
            "stand_alone_network_upgrades": 172684,
            "network_upgrades": 4574949
          }
        }
      ]
    }
  ],
  "interpretation": [
    "AH1-580 is a 200 MW uprate of AG2-082. Its 400 MW maximum facility output includes the original request’s 200 MW.",
    "Cost totals are study estimates allocated to each request. They do not represent total project capital costs, final invoices, currently available capacity, or executed rights.",
    "The Phase II reports show a 2028 model base case. The study year is not an energization commitment.",
    "The selected component values are included for comparison. Minor rounding differences from the published total are retained."
  ]
}