  "milestones": [
    {
      "site": "EV Realty Torrance",
      "date": "2026-03-18",
      "date_basis": "Date on the Caltrans project programming request in the signed baseline",
      "stage": "design_scope_amendment",
      "previous_dc_ports": 60,
      "revised_dc_ports": 50,
      "previous_simultaneous_charging_kw": 7600,
      "revised_simultaneous_charging_kw": 9000,
      "source_url": "https://catc.ca.gov/-/media/ctc-media/documents/programs/baseline-agreements/2026-05/ev-realty-south-bay-truck-charging-hub-project-signed.pdf#page=12"
    },
    {
      "site": "EV Realty San Bernardino",
      "date": "2026-03-25",
      "date_basis": "Equipment supplier report date",
      "stage": "test_charge_reported",
      "truck_make_tested": "Windrose",
      "mcs_dispensers_in_test_setup": 2,
      "shared_power_unit_rating_kw": 1200,
      "measured_session_peak_kw": null,
      "source_url": "https://kempower.com/america/news/first-kempower-mega-satellite-mcs-in-north-america-charged-successfully-under-real-world-conditions-at-ev-realtys-san-bernardino-hub-in-california/"
    },
    {
      "site": "EV Realty San Bernardino",
      "date": "2026-04-09",
      "date_basis": "Operator announcement date",
      "stage": "hub_opening_reported",
      "total_ports_reported": 76,
      "grid_capacity_reported_kw": 9000,
      "pull_through_stalls_with_ccs_or_mcs": 4,
      "current_free_compatible_bays": null,
      "source_url": "https://evrealtyus.com/2026/04/ev-realty-opens-major-truck-charging-hub-in-californias-inland-empire-with-76-ports-and-9-mw-of-capacity/",
      "layout_source_url": "https://evrealtyus.com/projects/san-bernardino-ca/"
    },
    {
      "site": "Forum Mobility FM Harbor",
      "date": "2026-05-27",
      "date_basis": "Notice of Exemption posting date",
      "stage": "installation_notice_posted",
      "planned_mcs_dispensers": 2,
      "permit_reference": "Harbor Development Permit 26-020",
      "source_url": "https://ceqanet.lci.ca.gov/2026051023"
    },
    {
      "site": "Forum Mobility FM Harbor",
      "date": "2026-11-05",
      "date_basis": "Ribbon-cutting date reported by the operator",
      "stage": "launch_session_reported",
      "mcs_chargers_announced": 2,
      "current_free_compatible_bays": null,
      "source_url": "https://forummobility.com/news/forum-mobility-announces-first-ultra-fast-mcs-chargers-in-socal-port-gateway-at-fm-harbor/"
    },
    {
      "site": "EV Realty Torrance",
      "date": "2026-11-17",
      "date_basis": "Operator construction announcement date",
      "stage": "construction_start_reported",
      "commercial_fleet_opening_target": "mid-2027",
      "commercial_fleet_opening_confirmed_on": null,
      "source_url": "https://evrealtyus.com/2026/11/ev-realty-breaks-ground-on-9-mw-truck-charging-hub-in-torrance/"
    },
    {
      "site": "Greenlane Colton",
      "date": "2026-11-18",
      "date_basis": "Commission resolution adoption date",
      "stage": "grant_approved",
      "resolution": "26-1118-07a",
      "agreement": "ZVI-26-003",
      "approved_grant_usd": 2107088,
      "planned_public_single_port_mcs_chargers": 2,
      "mcs_commissioned_on": null,
      "source_url": "https://efiling.energy.ca.gov/GetDocument.aspx?DocumentContentId=121542&tn=273723#page=11"
    },
    {
      "site": "Greenlane Colton",
      "date": "2026-11-19",
      "date_basis": "Notice of Exemption posting date",
      "stage": "installation_notice_posted",
      "planned_mcs_dispensers": 2,
      "planned_mcs_power_cabinets": 1,
      "mcs_booking_starts_on": null,
      "source_url": "https://ceqanet.lci.ca.gov/2026110675"
    }
  ],
  "torrance_design_comparison": {
    "port_groups": [
      { "equipment": "DC fast charging", "ports": 30, "up_to_kw_per_port": 350 },
      { "equipment": "MCS", "ports": 20, "up_to_kw_per_port": 1200 }
    ],
    "total_ports": 50,
    "sum_of_individual_port_maxima_kw": 34500,
    "simultaneous_ev_charging_design_kw": 9000,
    "calculation": "30 × 350 kW + 20 × 1,200 kW = 34,500 kW. The baseline specifies 9,000 kW of simultaneous charging. Actual power depends on the site allocation, equipment and truck acceptance.",
    "port_ratings_source_url": "https://catc.ca.gov/-/media/ctc-media/documents/programs/baseline-agreements/2026-05/ev-realty-south-bay-truck-charging-hub-project-signed.pdf#page=5",
    "simultaneous_capacity_source_url": "https://catc.ca.gov/-/media/ctc-media/documents/programs/baseline-agreements/2026-05/ev-realty-south-bay-truck-charging-hub-project-signed.pdf#page=21"
  }
}