# SPP CHILLS for Data Centers: How Much Load Can Stay Online?

> Check how much data center load can run when Southwest Power Pool curtails non-firm CHILLS service. Compare study paths, firm power, and a 100 MW example.

URL: https://invariant-ai.com/blog/spp-chills-data-center-power  
Published: 2026-11-24 · Publisher: Invariant · Region: Southwest Power Pool, United States

Southwest Power Pool’s Conditional High Impact Large Load Service (CHILLS) can provide temporary, non-firm transmission service for a new data center or industrial load. It can run for up to seven years and can be curtailed. Before you count it toward a data center opening, identify the load that must stay on, how much firm service the utility can deliver, and what the site can supply when conditional imports fall to zero.

## Key points

- Ask the serving utility for the firm and conditional megawatts at the delivery point, by phase and service date.
- Check which equipment can shut down together and how much facility load remains during a curtailment.
- Price the temporary operating arrangement and name the studies, network work and agreements required for firm service.

## What does SPP CHILLS provide?

CHILLS uses transmission capability available after firm service needs are met. The accepted tariff sets a term of one to seven years. Conditional service can be reduced or interrupted under the tariff, and SPP describes it as a bridge while the customer secures the resources or upgrades needed for long-term service. ([Federal Energy Regulatory Commission](https://spp.org/documents/76880/20260605_order%20-%20revisions%20to%20add%20the%20conditional%20high%20impact%20large%20load%20service_er26-1323.pdf)) ([Southwest Power Pool](https://www.spp.org/engineering/large-load/))

The reserved amount is the contracted ceiling for the conditional service. Confirm the applicable transmission charges, the rules for exceeding that ceiling and the separate arrangement that supplies energy to the site. Where firm and conditional loads share a delivery point, SPP’s compliance filing describes separate metering. Ask the utility how the proposed meters and agreements cover your load in each phase. ([Southwest Power Pool](https://spp.org/Documents/77151/20260706_Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf)) ([Federal Energy Regulatory Commission](https://spp.org/Documents/78171/20261026_Order%20on%20Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf))

| Filing date | What changed |
| --- | --- |
| June 5, 2026 | FERC accepts SPP’s tariff revisions subject to a compliance filing. The order sets a July 1 effective date. ([Federal Energy Regulatory Commission](https://spp.org/documents/76880/20260605_order%20-%20revisions%20to%20add%20the%20conditional%20high%20impact%20large%20load%20service_er26-1323.pdf)) |
| July 6, 2026 | SPP files the revised terms. The filing explains separate metering for firm and conditional loads sharing a delivery point. ([Southwest Power Pool](https://spp.org/Documents/77151/20260706_Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf)) |
| October 26, 2026 | FERC accepts the compliance filing with the July 1 effective date. ([Federal Energy Regulatory Commission](https://spp.org/Documents/78171/20261026_Order%20on%20Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf)) |

SPP filed a separate set of market and curtailment changes in September. Its filing targeted implementation in the second quarter of 2027 and called for a later filing to set an effective date. Ask the utility to identify the tariff version and operating terms applicable at your intended start date. ([Southwest Power Pool](https://spp.org/documents/77674/20260902_revisions%20to%20clarify%20the%20conditional%20high%20impact%20large%20load%20policy_er26-3685-000.pdf))

## Which large-load study applies to the site?

SPP describes a High Impact Large Load as new or increased commercial or industrial load at a site that meets the applicable transmission threshold. The threshold is 10 MW at 69 kV or below, and 50 MW above 69 kV. Start with the serving utility and ask which entity will request transmission service. ([Southwest Power Pool](https://www.spp.org/engineering/large-load/))

| Study route | Why it applies | What to request |
| --- | --- | --- |
| Attachment AQ | Delivery point work where the transmission customer has enough designated resources for the load. | The study scope, remaining network upgrades, and any conditional service available before upgrades finish. ([Federal Energy Regulatory Commission](https://spp.org/documents/76880/20260605_order%20-%20revisions%20to%20add%20the%20conditional%20high%20impact%20large%20load%20service_er26-1323.pdf)) ([Southwest Power Pool](https://www.spp.org/engineering/large-load/)) |
| Attachment AX | A provisional load study when the transmission customer lacks sufficient designated resources and increased load requires facility changes. | The plan to secure resources, and any interim service, facility work or milestones needed to proceed. ([Federal Energy Regulatory Commission](https://spp.org/documents/76880/20260605_order%20-%20revisions%20to%20add%20the%20conditional%20high%20impact%20large%20load%20service_er26-1323.pdf)) ([Southwest Power Pool](https://www.spp.org/engineering/large-load/)) |
| Attachment BC | A delivery point assessment that can be used to study a conditional load. | The study result, the service agreements needed at that point, and the follow-on study route for long-term firm service. ([Federal Energy Regulatory Commission](https://spp.org/documents/76880/20260605_order%20-%20revisions%20to%20add%20the%20conditional%20high%20impact%20large%20load%20service_er26-1323.pdf)) ([Southwest Power Pool](https://spp.org/Documents/77151/20260706_Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf)) |

Ask for the assessed service level and affected-system dependencies in writing. A delivery point study under Attachment BC still needs an effective service agreement to establish the delivery point. Record the agreement, delivery point facilities, and commissioning steps alongside the proposed date. ([Southwest Power Pool](https://spp.org/Documents/77151/20260706_Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf)) ([Federal Energy Regulatory Commission](https://spp.org/Documents/78171/20261026_Order%20on%20Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf))

## How much of a 100 MW site can keep running?

Consider an illustrative 100 MW facility with 35 MW of firm grid service and 65 MW of conditional imports. Assume the utility and the proposed agreements allow these blocks at the site. During a curtailment, operators can shed 40 MW of facility load, leaving 60 MW to keep running. All load figures are facility MW, including the electrical and cooling loads that remain.

| Operating case | Available supply | Facility load after shedding | Shortfall |
| --- | --- | --- | --- |
| Normal service | 100 MW | 100 MW | 0 MW |
| Conditional import cut to 20 MW | 55 MW | 60 MW | 5 MW |
| All conditional import curtailed | 35 MW | 60 MW | 25 MW |
| Full curtailment with 20 MW of on-site output | 55 MW | 60 MW | 5 MW |
| Full curtailment with 25 MW of on-site output | 60 MW | 60 MW | 0 MW |

With conditional imports gone, 35 MW of firm supply leaves a 25 MW gap. An assumed 20 MW of permitted on-site output, measured net of plant auxiliaries and available in the same event, leaves 5 MW uncovered. Covering 5 MW for two hours would require 10 MWh delivered to the load before conversion losses, reserve and usable battery limits. Check the transition separately with the facility engineer.

[Download the tariff timeline and curtailment worksheet (JSON)](https://invariant-ai.com/blog/spp-chills-data-center-power-worksheet.json)

[Review the power study process](https://invariant-ai.com/blog/utility-grade-power-study)

[Check battery duration for an outage shortfall](https://invariant-ai.com/calculators/data-center-power-capacity) · [Compare on-site bridge power designs](https://invariant-ai.com/blog/behind-the-meter-power-for-data-centers)

## What to ask for before signing a lease or land option

- Firm service and conditional imports. Get the MW and date for each phase, the delivery point, and the exact agreements that support those figures.
- Curtailment terms. Get the applicable triggers, notice, reduction amount, duration and restoration protocol. Ask which terms are contractual and which event assumptions you must make.
- Replacement supply. Check net output in the relevant outage, startup and transfer time, fuel, operating permits, metering and utility approval for the operating configuration.
- Exit to firm service. Record the temporary end date, network upgrades, required resources, follow-on study and expected agreement dates. Compare those dates with the tenant’s delivery deadlines.

For a site comparison, give Invariant the candidate parcels, phased facility MW, minimum continuous load and earliest viable opening date. A site screen can identify the questions to take to the serving utilities and help compare the evidence they provide.

[Compare a utility letter, load study and service agreement](https://invariant-ai.com/blog/utility-will-serve-letter-load-study-esa) · [Work through a utility-grade power study](https://invariant-ai.com/blog/utility-grade-power-study)

## Questions

### Is CHILLS firm power for a data center?

CHILLS is non-firm transmission service. It is subject to curtailment and interruption. For a proposed site, obtain the firm import amount separately and check how the site carries its minimum load during a conditional interruption. ([Federal Energy Regulatory Commission](https://spp.org/documents/76880/20260605_order%20-%20revisions%20to%20add%20the%20conditional%20high%20impact%20large%20load%20service_er26-1323.pdf)) ([Southwest Power Pool](https://spp.org/Documents/77151/20260706_Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf))

### How long can a data center use SPP CHILLS?

The accepted terms allow a minimum of one year and a maximum of seven years. Confirm the effective service date, end date and conditions in the executed service agreement. ([Federal Energy Regulatory Commission](https://spp.org/documents/76880/20260605_order%20-%20revisions%20to%20add%20the%20conditional%20high%20impact%20large%20load%20service_er26-1323.pdf))

### Can one SPP delivery point have firm service and CHILLS?

SPP’s compliance filing describes a delivery point with both. It calls for separate metering of firm and conditional loads and explains that more than one service agreement may be needed. Ask the utility to confirm how that arrangement would apply at the site. ([Southwest Power Pool](https://spp.org/Documents/77151/20260706_Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf)) ([Federal Energy Regulatory Commission](https://spp.org/Documents/78171/20261026_Order%20on%20Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf))

## Sources

- Federal Energy Regulatory Commission: [FERC’s June 5 CHILLS order, ER26-1323-000 and ER26-1323-001](https://spp.org/documents/76880/20260605_order%20-%20revisions%20to%20add%20the%20conditional%20high%20impact%20large%20load%20service_er26-1323.pdf)
- Southwest Power Pool: [SPP’s July 6 filing with the revised tariff and service form, ER26-1323-002](https://spp.org/Documents/77151/20260706_Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf)
- Federal Energy Regulatory Commission: [FERC’s October 26 letter accepting the July filing, ER26-1323-002](https://spp.org/Documents/78171/20261026_Order%20on%20Compliance%20Filing%20-%20Revisions%20to%20Add%20the%20Conditional%20High%20Impact%20Large%20Load%20Service_ER26-1323-002.pdf)
- Southwest Power Pool: [SPP large-load study paths and tariff viewer](https://www.spp.org/engineering/large-load/)
- Southwest Power Pool: [SPP’s separate September 2 curtailment proposal, ER26-3685-000](https://spp.org/documents/77674/20260902_revisions%20to%20clarify%20the%20conditional%20high%20impact%20large%20load%20policy_er26-3685-000.pdf)

## Related

- [Behind-the-Meter Power for Data Centers | Bridge Power](https://invariant-ai.com/blog/behind-the-meter-power-for-data-centers)
- [Will-serve letter vs. load study vs. electric service agreement](https://invariant-ai.com/blog/utility-will-serve-letter-load-study-esa)
- [Power flow study for a data center: what it tests and how to read the results](https://invariant-ai.com/blog/data-center-power-flow-study)

---