  "name": "Taylor Technology Campus power, reclaimed water and approval milestones",
  "version": "1.0.0",
  "guide_url": "https://invariant-ai.com/blog/taylor-technology-campus-power-water-approvals#taylor-water-capacity-and-delivery",
  "reviewed_date": "2026-11-26",
  "scope": "Normalize public developer targets, a local council vote, and dated and conditional terms in the city-posted agreement. Establish scope from the named source and page before using a value.",
  "spatial_coverage": "Taylor Technology Campus, formerly Project Mustang, Williamson County, Texas",
  "observations": [
    {
      "id": "prior-zoning-application",
      "record_type": "withdrawal",
      "source_id": "city-vote",
      "event_date": "2026-09-03",
      "city_case_id": "PZ 2026-2715",
      "corroborating_source_id": "withdrawn-plan"
    },
    {
      "id": "development-agreement",
      "record_type": "council_approval",
      "source_id": "city-vote",
      "event_date": "2026-10-08",
      "yes_votes": 5,
      "no_votes": 0
    },
    {
      "id": "campus-scale",
      "record_type": "developer_target",
      "source_id": "developer",
      "published_date": "2026-10-09",
      "capacity_mw_up_to": 1000,
      "capacity_label": "hyperscale data center capacity",
      "gross_or_it_basis": null
    },
    {
      "id": "initial-power",
      "record_type": "developer_target",
      "source_id": "developer",
      "published_date": "2026-10-09",
      "target_period": "2028-H1",
      "first_phase_net_deliverable_mw": null
    },
    {
      "id": "preliminary-plat",
      "record_type": "agreement_deadline",
      "source_id": "annexation",
      "section": "10.1",
      "pdf_page": 35,
      "required_by_date": "2027-04-08"
    },
    {
      "id": "annexation-petition",
      "record_type": "agreement_relative_deadline",
      "source_id": "annexation",
      "section": "10.2",
      "pdf_page": 35,
      "days_after_approval_or_conditional_approval": 7
    },
    {
      "id": "land-purchase",
      "record_type": "agreement_termination_condition",
      "source_id": "purchase",
      "section": "9.3(e)",
      "pdf_page": 33,
      "closing_date_to_avoid_termination_right": "2027-10-08"
    },
    {
      "id": "reclaimed-plant-design",
      "record_type": "system_design_basis",
      "source_id": "reclaimed-authorization",
      "section": "6.1(a)",
      "pdf_page": 18,
      "treatment_design_basis_gallons_per_day": 1000000
    },
    {
      "id": "reclaimed-treatment-completion",
      "record_type": "agreement_relative_deadline",
      "source_id": "reclaimed-deadline",
      "section": "6.1(d)",
      "pdf_page": 21,
      "months_after_city_receives_qualified_notice": 24,
      "later_milestone": "Developer completion of off-site reclaimed-water improvements",
      "extensions_and_conditions_apply": true
    },
    {
      "id": "reclaimed-campus-average",
      "record_type": "service_term_after_acceptance",
      "source_id": "reclaimed-service",
      "section": "6.3(d)(3)",
      "pdf_page": 29,
      "campus_average_gallons_per_day_up_to": 150000
    },
    {
      "id": "reclaimed-hvac-fill",
      "record_type": "one_time_collective_volume",
      "source_id": "reclaimed-service",
      "section": "6.3(d)(3)",
      "pdf_page": 29,
      "total_hvac_fill_gallons_up_to": 1575000
    },
    {
      "id": "state-wastewater-application",
      "record_type": "state_pending_list_entry",
      "source_id": "state-pending",
      "corroborating_source_id": "state-notice",
      "reviewed_date": "2026-11-26",
      "application_number": "WQ0016554001",
      "proposed_average_discharge_gallons_per_day_up_to": 150000
    },
    {
      "id": "state-wastewater-withdrawal-trigger",
      "record_type": "agreement_relative_deadline",
      "source_id": "withdrawal-trigger",
      "section": "6.4",
      "pdf_pages": [
        29,
        30
      ],
      "application_number": "WQ0016554001",
      "business_days_after_first_site_development_permit": 5,
      "disannexation_exception_applies": true
    }
  ],
  "source_urls": {
    "city-vote": "https://www.taylortx.gov/1416/Taylor-Technology-Campus",
    "withdrawn-plan": "https://taylortx.gov/m/NewsFlash/Archive/Item/2079?arcId=3442",
    "developer": "https://bigwattdigital.com/press-release/co-development-partners-big-watt-digital-and-powerhouse-data-centers-announce-planning-approval-for-taylor-technology-campus/",
    "purchase": "https://www.taylortx.gov/DocumentCenter/View/16793#page=33",
    "annexation": "https://www.taylortx.gov/DocumentCenter/View/16793#page=35",
    "reclaimed-authorization": "https://www.taylortx.gov/DocumentCenter/View/16793#page=18",
    "reclaimed-deadline": "https://www.taylortx.gov/DocumentCenter/View/16793#page=21",
    "reclaimed-service": "https://www.taylortx.gov/DocumentCenter/View/16793#page=29",
    "withdrawal-trigger": "https://www.taylortx.gov/DocumentCenter/View/16793#page=29",
    "state-pending": "https://www.tceq.texas.gov/permitting/wastewater/pending-permits/tpdes-applications",
    "state-notice": "https://www.tceq.texas.gov/downloads/agency/decisions/hearings/notices/2026/2026-12-01-nmcv-taylor-property-investors-llc-wq0016554001-pm.pdf"
  },
  "source_snapshots": [
    {
      "url": "https://www.taylortx.gov/DocumentCenter/View/16793",
      "sha256": "fbf247083451ed07bf6525589b56ab1bba60618d25307134f8fdb8f7cb5a91e1"
    },
    {
      "url": "https://www.taylortx.gov/1416/Taylor-Technology-Campus",
      "sha256": "c0c02b56947ce02d24933e35d5b3da094b1e09d193a263cc7b3b318df2c28fe4"
    },
    {
      "url": "https://bigwattdigital.com/press-release/co-development-partners-big-watt-digital-and-powerhouse-data-centers-announce-planning-approval-for-taylor-technology-campus/",
      "sha256": "2ad23c1708b868454638fd17756b900d19565abd9b19bfb07233b362cfca904a"
    },
    {
      "url": "https://taylortx.gov/m/NewsFlash/Archive/Item/2079?arcId=3442",
      "sha256": "062bed0f7538d55d3885144c6927405559bd96c51bc6735613b13c5d54c62d7f"
    },
    {
      "url": "https://www.tceq.texas.gov/permitting/wastewater/pending-permits/tpdes-applications",
      "sha256": "c4cad2b1dc7e77a9a298c08fe1c53cb8089c20b246bd49b91fae2a4e3753d118"
    },
    {
      "url": "https://www.tceq.texas.gov/downloads/agency/decisions/hearings/notices/2026/2026-12-01-nmcv-taylor-property-investors-llc-wq0016554001-pm.pdf",
      "sha256": "9fa2777d006b7570ddd2715fc8d39270a49f34bbd61469539b8ffcbb421f6e4a"
    }
  ],
  "unresolved_in_reviewed_records": [
    "Net MW at the facility meter in the first phase and the tenant’s contracted critical IT capacity.",
    "Evidence of completion of annexation, the date on the qualified water construction notice, and acceptance of the on-site and off-site improvements.",
    "The applicable final air authorization and whether the first phase has all permits, fuel supply, commissioned generation and operating rights needed to serve load.",
    "The first site development permit and whether TCEQ received or processed the required withdrawal."
  ]
}