  "title": "Transformer delivery route checks and source records",
  "checked_on": "2026-11-24",
  "oregon_case": {
    "project": "Deschutes Solar and Battery Energy Storage System Facility",
    "status": "Preliminary application for site certificate under review in the November 2026 update",
    "source_url": "https://www.oregon.gov/energy/facilities/Facility%20Exhibits/DSB/2026-01-09-DSBAPP-pASC-13-Public-Services.pdf",
    "status_source_url": "https://www.oregon.gov/energy/facilities/Pages/EFSC-Project-Updates.aspx",
    "decision_scope": "Field survey and comparison of proposed routes using representative vehicle geometry. Verify the selected carrier and final approvals before committing to a movement.",
    "findings": [
      {
        "check": "Highway turns",
        "finding": "The preferred route would likely need a bypass at the I-84 and OR 197 interchange. The modeled transformer transporter could not make the turn safely as drawn.",
        "verification": "Have the carrier check the full turn with the actual transport configuration and get any bypass or road work into the schedule.",
        "references": "Route study printed pages 4–5 and 23"
      },
      {
        "check": "Weight-restricted bridge",
        "finding": "The survey flagged an OR 216 bridge for early investigation and called for bridge and culvert analysis after carrier selection.",
        "verification": "Have the road authority review the specific axle loads, axle spacing and crossings before relying on the route.",
        "references": "Route study printed page 24"
      },
      {
        "check": "Last leg to the transformer pad",
        "finding": "Modifying the existing driveway would require about 2,700 feet of new roadway. The engineer proposed a new driveway and about 800 feet of new road instead.",
        "verification": "Put the gate, pad, access rights, road works and construction dates on the same plan.",
        "references": "Route study printed page 24"
      }
    ]
  },
  "texas_permit_reference": {
    "source_url": "https://www.txdmv.gov/motor-carriers/oversize-overweight-permits/superheavy-single-trip",
    "application_lead_time_weeks": {
      "minimum": 3,
      "maximum": 4
    },
    "scope": "TxDMV instructions for a superheavy single-trip application unless an approved route is already on file. Actual authorization is specific to the movement, dates, origin and destination."
  },
  "candidate_evidence_template": {
    "site_or_parcel_id": null,
    "equipment_and_carrier": null,
    "origin_and_pad": null,
    "loaded_vehicle_dimensions": null,
    "gross_weight_and_axle_configuration": null,
    "critical_turns_and_clearances": null,
    "bridge_and_culvert_reviews": null,
    "access_and_temporary_works": null,
    "permit_ids_and_movement_window": null,
    "date_needed_and_next_owner": null
  }
}