# Data Center Utility Load Study Cost, Fees and Timeline

> Compare AEP Ohio load study fees, ERCOT study charges and financial security, and Dominion’s engineering process. See the cost assumptions for a 100 MW request.

URL: https://invariant-ai.com/blog/utility-load-study-cost-and-timeline  
Published: 2026-11-20 · Updated: 2026-11-23 · Publisher: Invariant · Region: United States

AEP Ohio lists study fees of $10,000 to $100,000 based on the MW requested. Texas sets a $100,000 study fee for covered large-load requests in ERCOT. A 100 MW new request under the standard Texas process also carries $5 million in baseline financial security at the intermediate agreement. Track each payment, the study date and the earliest utility service date separately before committing to land.

## Key points

- AEP Ohio lists $50,000 at exactly 50 MW and $100,000 at exactly 100 MW. Get written confirmation at the tariff’s 25 MW boundary.
- AEP Ohio describes reasonable-effort study periods of 45 or 60 days, depending on whether regional transmission upgrades are needed.
- For an ordinary covered Texas request, $50,000 per requested MW sets the baseline intermediate financial security. Construction contributions and later security have separate terms.
- Get the study scope, conditions, payment triggers and date of each service milestone for the specific point of connection.

## How much does a utility load study cost?

Start with the utility that will serve the site and the facility demand at the meter. The Ohio bands below come from AEP Ohio’s application instructions. The Texas figure comes from the adopted rule effective October 8, 2026. Dominion describes a project-specific engineering process. ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/)) ([Ohio Power Company](https://www.aepohio.com/lib/docs/ratesandtariffs/Ohio/November_2026_Ohio_Power_Tariff_Book.pdf)) ([Public Utility Commission of Texas](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html)) ([Dominion Energy Virginia](https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf))

| Utility or process | Request | Study fee | What to confirm |
| --- | --- | --- | --- |
| AEP Ohio Schedule DCT | Above 25 MW and below 50 MW | $10,000 | Confirm treatment in writing at exactly 25 MW. ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/)) ([Ohio Power Company](https://www.aepohio.com/lib/docs/ratesandtariffs/Ohio/November_2026_Ohio_Power_Tariff_Book.pdf)) |
| AEP Ohio Schedule DCT | 50 MW to below 100 MW | $50,000 | Use the MW requested on the application. ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/)) |
| AEP Ohio Schedule DCT | 100 MW or greater | $100,000 | Confirm the tranche and submission cutoff with Ohio Power. ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/)) |
| Texas ERCOT, 16 TAC §25.194 | Covered large-load interconnection | $100,000 | Due by execution of the intermediate agreement. Additional ERCOT study fees may apply under its protocols. ([Public Utility Commission of Texas](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html)) ([ERCOT](https://www.ercot.com/services/rq/large-load-integration)) |
| Dominion Energy Virginia | Site-specific scope after feasibility | Request an engineering quote | Ask for the engineering agreement, its scope and the expected date for a service plan. ([Dominion Energy Virginia](https://www.dominionenergy.com/virginia/large-business-services/data-center-requests)) ([Dominion Energy Virginia](https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf)) |

AEP Ohio’s intake page describes the formal process at 25 MW and above, while the November 2026 tariff defines a data center under Schedule DCT using demand greater than 25 MW. The published fee table also starts above 25 MW. Ask Ohio Power for the classification and fee when the planned request lands exactly on that boundary. ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/)) ([Ohio Power Company](https://www.aepohio.com/lib/docs/ratesandtariffs/Ohio/November_2026_Ohio_Power_Tariff_Book.pdf))

## What does a 100 MW request commit?

This example uses a new 100 MW facility request. Get the utility’s written amounts and due dates for your project. Keep the study invoice, financial security, construction contributions and ongoing minimum charges on separate lines.

| Process | Initial charges or security | What to budget next |
| --- | --- | --- |
| AEP Ohio | $100,000 study fee for 100 MW requested. | Check the LOA, collateral, and monthly demand provisions. At 100 MW post-ramp contract capacity, the tariff-based minimum is 82.5 MW before comparison with the prior-demand rule. ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/)) ([Ohio Power Company](https://www.aepohio.com/lib/docs/ratesandtariffs/Ohio/November_2026_Ohio_Power_Tariff_Book.pdf)) |
| Texas ERCOT | $100,000 study fee plus $5 million in baseline financial security at the intermediate agreement. | Ask what qualifies as security and whether equipment, construction contributions, additional fees or allocated upgrades raise later obligations. ([Public Utility Commission of Texas](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html)) |

Texas §25.194(d)(2) sets the $5 million baseline as 100 MW × $50,000 per requested MW. Certain early equipment and service commitments can require additional security or direct payment. At the standard large-load interconnection agreement stage, the rule sets security at the greater of $50,000 per contracted MW and the allocated system-upgrade cost, with possible other obligations under the applicable terms. ([Public Utility Commission of Texas](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html))

Under AEP Ohio Schedule DCT, 100 MW of post-ramp contract capacity gives a tariff minimum of 57.5 MW plus 25 MW, or 82.5 MW, subject to the stated cap on that part of the formula. The other test uses 85% of the highest previously established monthly billing demand in the past 11 months. The higher test sets the floor after ramp. During ramp, the tariff instead applies 85% of the load-ramp contract capacity. Keep these demand quantities separate from the utility’s dollar rates. ([Ohio Power Company](https://www.aepohio.com/lib/docs/ratesandtariffs/Ohio/November_2026_Ohio_Power_Tariff_Book.pdf)) ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/))

[Download the study fee and security evidence (CSV)](https://invariant-ai.com/blog/utility-load-study-cost-evidence.csv)

[Review the power study process](https://invariant-ai.com/blog/utility-grade-power-study)

## How long does a utility load study take?

Ohio Power says it will make reasonable efforts to complete a paid study within 60 days when regional transmission upgrades are needed and 45 days otherwise. The program can group projects by tranche or upgrade. Ask when your case enters study and what triggers the estimated completion date. ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/))

In ERCOT, ask the serving utility which study process applies to your request and what the queue and engineering milestones mean for each phase. In Dominion Virginia, the published process starts with feasibility, then identifies the scope of the engineering and construction agreements. Confirm when the utility can provide initial load, when it expects permanent service and which facilities control each date. ([Public Utility Commission of Texas](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html)) ([ERCOT](https://www.ercot.com/services/rq/large-load-integration)) ([Dominion Energy Virginia](https://www.dominionenergy.com/virginia/large-business-services/data-center-requests)) ([Dominion Energy Virginia](https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf))

[Compare the utility documents that support a delivery date](https://invariant-ai.com/blog/utility-will-serve-letter-load-study-esa)

## What to verify before paying for a study

Bring the parcel, proposed meter location, initial and final facility MW, phased dates, expected reliability, and any on-site generation. Ask which alternate connection points or ramp profiles it will accept. Record what the study will deliver and which utility approval comes next.

Ohio Power lists an executed option, lease or ownership as ways to establish site control for its load study request. Texas §25.194 lists qualifying property interests and documentation for the intermediate agreement. Review the specific evidence your utility will accept before starting a land option or utility filing. ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/)) ([Public Utility Commission of Texas](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html))

[Use the site selection and power-evidence worksheet](https://invariant-ai.com/blog/data-center-site-selection-checklist) · [See what an independent power study can check before filing](https://invariant-ai.com/blog/utility-grade-power-study)

## More due diligence guides

**Site due diligence guides:** [Site due diligence: the two-step process](https://invariant-ai.com/blog/data-center-site-due-diligence) · [Step 1: site feasibility screen](https://invariant-ai.com/blog/data-center-site-feasibility-study) · [Step 2: utility-grade power study](https://invariant-ai.com/blog/utility-grade-power-study) · [What a power flow study is](https://invariant-ai.com/blog/data-center-power-flow-study) · [N-1 contingency analysis](https://invariant-ai.com/blog/n-1-contingency-analysis-data-center) · [How to check substation capacity](https://invariant-ai.com/blog/data-center-substation-capacity-check) · [Distance to substation and transmission](https://invariant-ai.com/blog/distance-to-transmission-line-data-center) · [Flood zone screening](https://invariant-ai.com/blog/data-center-flood-zone-screening) · [Seismic risk screening](https://invariant-ai.com/blog/data-center-seismic-risk-screening) · [Wetlands, species and Phase I ESA](https://invariant-ai.com/blog/data-center-environmental-site-screening) · [FAA height limits near airports](https://invariant-ai.com/blog/faa-height-limits-data-center-site) · [Power due diligence for investors and lenders](https://invariant-ai.com/blog/data-center-power-due-diligence-investors) · [For landowners: a power study before you sell](https://invariant-ai.com/blog/power-study-before-selling-land-to-data-center)

**More on site selection:** [Five rungs of power evidence](https://invariant-ai.com/blog/power-evidence-data-center-site-verification) · [Will-serve letter vs load study vs ESA](https://invariant-ai.com/blog/utility-will-serve-letter-load-study-esa) · [Moratorium screening](https://invariant-ai.com/blog/data-center-moratorium-local-opposition-site-screening) · [Site selection checklist](https://invariant-ai.com/blog/data-center-site-selection-checklist) · [Texas: SB 6 and Batch Zero](https://invariant-ai.com/blog/texas-data-center-large-load-interconnection-2026) · [Find a data center site in the US](https://invariant-ai.com/blog/find-data-center-site-us) · [Site selection services](https://invariant-ai.com/blog/data-center-site-selection-services) · [Capacity for neoclouds and AI labs](https://invariant-ai.com/blog/ai-compute-capacity-for-neoclouds) · [Power check for AI tenants](https://invariant-ai.com/blog/provider-power-check-for-ai-tenants)

## Questions

### How much does a data center load study cost?

Ohio Power lists $10,000 above 25 MW and below 50 MW, $50,000 from 50 MW to below 100 MW, and $100,000 starting at 100 MW. The adopted Texas rule sets a $100,000 fee for covered requests, with financial security calculated separately. ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/)) ([Public Utility Commission of Texas](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html))

### How much financial security does a 100 MW Texas request require?

For an ordinary covered new ERCOT request, the baseline intermediate security is $50,000 per requested MW, or $5 million for 100 MW. Equipment and upgrade obligations can change the amount required at later steps. ([Public Utility Commission of Texas](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html))

### How long does a utility load study take?

Ohio Power describes reasonable-effort periods of 45 days without regional transmission upgrades and 60 days when they are required. Confirm the start milestone, applicable batch, and the separate utility service date for the site. ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/)) ([ERCOT](https://www.ercot.com/services/rq/large-load-integration))

### Do I need site control for a load study?

Ohio Power requires control of the site for its formal load study and lists ownership, a lease or an option. Covered Texas projects need acceptable site-control evidence for the intermediate agreement. Ask the serving utility which evidence applies to your filing. ([AEP Ohio](https://www.aepohio.com/company/about/rates/data-center-tariff/)) ([Public Utility Commission of Texas](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html))

## Sources

- AEP Ohio: [Schedule DCT study fees and process](https://www.aepohio.com/company/about/rates/data-center-tariff/)
- Ohio Power Company: [November 2026 Ohio Power Tariff Book, Schedule DCT sheets 223-1 to 223-8](https://www.aepohio.com/lib/docs/ratesandtariffs/Ohio/November_2026_Ohio_Power_Tariff_Book.pdf)
- Public Utility Commission of Texas: [Adopted 16 TAC §25.194, Large Load Interconnection Standards](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html)
- ERCOT: [Large Load Integration resources and study process](https://www.ercot.com/services/rq/large-load-integration)
- Dominion Energy Virginia: [Data center requests and construction schedule](https://www.dominionenergy.com/virginia/large-business-services/data-center-requests)
- Dominion Energy Virginia: [The contracting process for data centers, GS-5 report](https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf)

## Related

- [Data Center Site Selection Checklist and Criteria](https://invariant-ai.com/blog/data-center-site-selection-checklist)
- [Will-serve letter vs. load study vs. electric service agreement](https://invariant-ai.com/blog/utility-will-serve-letter-load-study-esa)
- [Texas data center power in 2026: SB 6, ERCOT Batch Zero and what they mean for site selection](https://invariant-ai.com/blog/texas-data-center-large-load-interconnection-2026)
- [Utility-grade power study for data centers: N-1 power flow before you file with the utility](https://invariant-ai.com/blog/utility-grade-power-study)

---

Site screens and power studies: pranav@invariant-ai.com, (628) 220-8972, https://cal.com/pranav-goswami/website-30min