# West Bengal data centre policy 2021: incentives, essential services and status

> West Bengal's Data Centre Policy 2021 gave stamp duty and electricity duty relief and essential services status; its five-year term ended around September 2026.

URL: https://invariant-ai.com/blog/west-bengal-data-centre-policy  
Published: 2026-11-21 · Publisher: Invariant · Region: West Bengal, India

West Bengal’s Data Centre Policy 2021, notified on 6 September 2021, is operative for five years or until a new policy or amendment replaces it, whichever is earlier, so its term ran to about September 2026. The policy gives 100% stamp duty and registration fee exemption, a five-year electricity duty waiver, industrial treatment of data centre electricity, dual grid power and classification of data centres as essential services. In May 2026 the state BJP president said the government was working on a new data centre policy; we found no successor as of 21 November 2026. Kolkata had 22 MW of operational data center capacity in mid-2026, according to Cushman & Wakefield.

## Key points

- West Bengal’s Data Centre Policy 2021, notified 6 September 2021, ran for five years or until replaced; we found no successor as of 21 November 2026.
- The 2021 policy gives 100% stamp duty and registration fee exemption and a five-year electricity duty waiver from commercial operation.
- Clause 5.3 of West Bengal’s 2021 policy classifies data centres as essential services.
- West Bengal data centres get FAR of 3.0 plus 1.0 purchasable and up to 60% ground coverage under the 2021 policy.
- Cushman & Wakefield counted 22 MW operational in six Kolkata data centres in mid-2026 and describes a cable landing station under construction at Tajpur.

## West Bengal Data Centre Policy 2021: key facts

| Item | Detail (checked 21 November 2026) |
| --- | --- |
| Policy | West Bengal Data Centre Policy 2021, Department of IT and Electronics |
| Notification | 490-Estt/ITE-18011/2/2021 dated 6 September 2021 |
| Validity | 5 years or until replaced (to about September 2026) |
| Headline incentives | 100% stamp duty and registration fee; electricity duty waiver for 5 years; essential services status |
| Power terms | Data centre electricity treated as industrial; dual power grid networks |
| Status | Term ended around September 2026; no successor found |

Sources: ([Department of IT and Electronics, West Bengal (text via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/)) ([Fox Mandal & Associates](https://www.foxmandal.in/rise-of-data-centres-in-west-bengal/))

## West Bengal Data Centre Policy 2021 incentives

West Bengal’s Data Centre Policy 2021 gives data centres the fiscal, power and building concessions below. ([Department of IT and Electronics, West Bengal (text via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/)) ([Fox Mandal & Associates](https://www.foxmandal.in/rise-of-data-centres-in-west-bengal/))

- 100% stamp duty and registration fee exemption.
- Electricity duty waiver for five years from commercial operation.
- Electricity used by data centres treated as industrial.
- Dual power grid networks.
- Classification under essential services (clause 5.3).
- FAR of 3.0 plus 1.0 purchasable, and up to 60% ground coverage.
- Self-certification under notified Acts, and preference in state cloud procurement.

Sources: ([Department of IT and Electronics, West Bengal (text via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/)) ([Fox Mandal & Associates](https://www.foxmandal.in/rise-of-data-centres-in-west-bengal/))

## West Bengal data centre policy after September 2026

We found no new West Bengal data centre policy as of 21 November 2026; the 2021 policy runs for five years from 6 September 2021 or until replaced. In May 2026 the state BJP president told Business Standard that the government was working on land and data centre policies. ([Department of IT and Electronics, West Bengal (text via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/)) ([Business Standard](https://www.business-standard.com/politics/bengal-govt-working-on-land-data-centre-policies-bengal-bjp-president-126052501625_1.html))

## Kolkata data centre capacity

Kolkata had 22 MW operational in six data centres in mid-2026, in New Town and Salt Lake, with 13 MW under construction and 71 MW planned, according to Cushman & Wakefield. The same report describes a cable landing station under construction at Tajpur. ([Cushman & Wakefield](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b))

**Read next:** [Data centres in Kolkata and East India](https://invariant-ai.com/blog/data-centres-in-kolkata) · [Odisha data centre policy](https://invariant-ai.com/blog/odisha-data-centre-policy)

For a site in West Bengal, Invariant checks how it gets power and the evidence behind that path (the distribution or transmission connection, the open access route, the nearest substations), screens seismic zone, flood history, groundwater status and airport height limits, and maps the central and state approvals the project needs, with the authority behind each one.

## More on data centres in India

**Start here:** [Data centres in India: capacity, cities, policy, power](https://invariant-ai.com/blog/data-centres-in-india) · [How to find a data centre site in India](https://invariant-ai.com/blog/find-data-centre-site-india) · [Data centre companies in India](https://invariant-ai.com/blog/data-centre-companies-india)

**Build and approvals:** [Approvals for a data centre in India](https://invariant-ai.com/blog/data-centre-approvals-india) · [How to set up a data centre in India](https://invariant-ai.com/blog/how-to-set-up-data-centre-india) · [Data centre cost per MW in India](https://invariant-ai.com/blog/data-centre-cost-per-mw-india) · [Site due diligence in India](https://invariant-ai.com/blog/data-centre-site-due-diligence-india) · [Data centre land and powered land in India](https://invariant-ai.com/blog/data-centre-land-india) · [Seismic zones, flood and cyclone risk](https://invariant-ai.com/blog/data-centre-seismic-flood-risk-india) · [Water and groundwater NOC for data centres](https://invariant-ai.com/blog/data-centre-water-india) · [DPDP Act and data localisation](https://invariant-ai.com/blog/dpdp-data-localisation-data-centres-india) · [Infrastructure status, tax holiday and DC SEZs](https://invariant-ai.com/blog/data-centre-incentives-india-central)

**Power:** [Power for data centres in India](https://invariant-ai.com/blog/power-for-data-centres-india) · [Grid connection: DISCOM, STU and CTU paths](https://invariant-ai.com/blog/data-centre-grid-connection-india) · [Green energy open access for data centres](https://invariant-ai.com/blog/green-energy-open-access-data-centres-india) · [Open access charges by state](https://invariant-ai.com/blog/open-access-charges-by-state-india) · [India data centre power demand to 2032](https://invariant-ai.com/blog/data-centre-power-demand-india) · [Power studies for Indian data centre sites](https://invariant-ai.com/blog/power-study-data-centre-india) · [Diesel generators and backup power rules](https://invariant-ai.com/blog/data-centre-backup-power-dg-sets-india)

**Policy by state:** [National data centre policy](https://invariant-ai.com/blog/national-data-centre-policy-india) · [State data centre policies compared](https://invariant-ai.com/blog/data-centre-policy-india-state-comparison) · [Maharashtra data centre policy](https://invariant-ai.com/blog/maharashtra-data-centre-policy) · [Uttar Pradesh data centre policy](https://invariant-ai.com/blog/uttar-pradesh-data-centre-policy) · [Tamil Nadu data centre policy](https://invariant-ai.com/blog/tamil-nadu-data-centre-policy) · [Telangana data centre policy](https://invariant-ai.com/blog/telangana-data-centre-policy) · [Gujarat data centre policy](https://invariant-ai.com/blog/gujarat-data-centre-policy) · [Karnataka data centre policy](https://invariant-ai.com/blog/karnataka-data-centre-policy) · [Andhra Pradesh data centre policy](https://invariant-ai.com/blog/andhra-pradesh-data-centre-policy) · [Haryana data centre policy](https://invariant-ai.com/blog/haryana-data-centre-policy) · [Rajasthan data centre policy](https://invariant-ai.com/blog/rajasthan-data-centre-policy) · [Odisha data centre policy](https://invariant-ai.com/blog/odisha-data-centre-policy) · [West Bengal data centre policy](https://invariant-ai.com/blog/west-bengal-data-centre-policy) · [Madhya Pradesh data centre policy](https://invariant-ai.com/blog/madhya-pradesh-data-centre-policy)

**Cities:** [Data centres in Mumbai and Navi Mumbai](https://invariant-ai.com/blog/data-centres-in-mumbai) · [Data centres in Chennai](https://invariant-ai.com/blog/data-centres-in-chennai) · [Data centres in Hyderabad](https://invariant-ai.com/blog/data-centres-in-hyderabad) · [Data centres in Noida and Delhi NCR](https://invariant-ai.com/blog/data-centres-in-noida) · [Data centres in Bengaluru](https://invariant-ai.com/blog/data-centres-in-bengaluru) · [Data centres in Pune](https://invariant-ai.com/blog/data-centres-in-pune) · [Data centres in Visakhapatnam](https://invariant-ai.com/blog/data-centres-in-visakhapatnam) · [Data centres in Gujarat: GIFT City, Ahmedabad, Jamnagar](https://invariant-ai.com/blog/data-centres-in-gujarat) · [Data centres in Kolkata and East India](https://invariant-ai.com/blog/data-centres-in-kolkata)

**Compare and invest:** [Mumbai vs Chennai vs Hyderabad](https://invariant-ai.com/blog/mumbai-vs-chennai-vs-hyderabad-data-centres) · [India vs Singapore vs Johor](https://invariant-ai.com/blog/india-vs-singapore-vs-johor-data-centres) · [AI data centres and IndiaAI GPUs](https://invariant-ai.com/blog/ai-data-centres-india) · [Data centre investment in India](https://invariant-ai.com/blog/data-centre-investment-india)

## Questions

### Does West Bengal have a data centre policy?

West Bengal’s Data Centre Policy 2021 ran for five years from 6 September 2021 or until replaced. We found no successor as of 21 November 2026. ([Department of IT and Electronics, West Bengal (text via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/))

### Are data centres essential services in West Bengal?

Yes. Clause 5.3 of the 2021 policy classifies data centre organisations under essential services. ([Department of IT and Electronics, West Bengal (text via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/)) ([Fox Mandal & Associates](https://www.foxmandal.in/rise-of-data-centres-in-west-bengal/))

### What incentives does West Bengal give a data center?

The 2021 policy gives 100% stamp duty and registration fee exemption, a five-year electricity duty waiver, industrial electricity treatment, dual grid power and building relaxations. ([Department of IT and Electronics, West Bengal (text via wbxpress)](https://wbxpress.com/west-bengal-data-centre-policy-2021/)) ([Fox Mandal & Associates](https://www.foxmandal.in/rise-of-data-centres-in-west-bengal/))

### Is West Bengal making a new data centre policy?

The state BJP president told Business Standard in May 2026 that the government was working on one. ([Business Standard](https://www.business-standard.com/politics/bengal-govt-working-on-land-data-centre-policies-bengal-bjp-president-126052501625_1.html))

### How much data centre capacity does Kolkata have?

Kolkata had about 22 MW operational in mid-2026, according to Cushman & Wakefield. ([Cushman & Wakefield](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b))

## Sources

- Department of IT and Electronics, West Bengal (text via wbxpress): [West Bengal Data Centre Policy 2021, notification 490-Estt/ITE-18011/2/2021 of 6 September 2021](https://wbxpress.com/west-bengal-data-centre-policy-2021/)
- Fox Mandal & Associates: [The dawning of data centres in West Bengal](https://www.foxmandal.in/rise-of-data-centres-in-west-bengal/)
- Business Standard: [Bengal government working on land and data centre policies](https://www.business-standard.com/politics/bengal-govt-working-on-land-data-centre-policies-bengal-bjp-president-126052501625_1.html)
- Cushman & Wakefield: [India data centre market overview, H1 2026](https://content.cushmanwakefield.com/api/public/content/6b60db63971344f3a3f5392374471667?v=90a58a0b)

## Related

- [Data centre policy in India: state data centre policies compared (2026)](https://invariant-ai.com/blog/data-centre-policy-india-state-comparison)
- [Data centres in Kolkata and East India: New Town, Salt Lake and Bhubaneswar (2026)](https://invariant-ai.com/blog/data-centres-in-kolkata)
- [Odisha data centre policy 2022: capital subsidy, power subsidy and SGST refund](https://invariant-ai.com/blog/odisha-data-centre-policy)
- [Power for data centres in India: grid supply, open access and tariffs by state](https://invariant-ai.com/blog/power-for-data-centres-india)

---

[Email your India data centre project requirements](mailto:pranav@invariant-ai.com) · [Book a call](https://cal.com/pranav-goswami/website-30min)