# Additional surcharge (open access)

> Additional surcharge is a charge on open access consumers, set by the state commission under Section 42(4) of the Electricity Act 2003, to cover the discom’s fixed costs of standing ready to supply them.

URL: https://invariant-ai.com/glossary/additional-surcharge  
Updated: 2026-11-21 · Publisher: Invariant

Also called: additional surcharge, AS open access, additional surcharge electricity

Section 42(4) of the Electricity Act 2003 makes a consumer that buys from someone other than its discom liable to pay an additional surcharge on wheeling charges, as specified by the state commission, to meet the fixed cost the discom carries from its obligation to supply.

Under the Green Energy Open Access Rules 2022 the additional surcharge does not apply to a green open access consumer that is paying fixed charges to the discom. Captive users that meet the ownership and consumption tests are also outside it.

## Sources

- [Electricity Act 2003 (with amendments), hosted by CERC](https://cercind.gov.in/Act-with-amendment.pdf)
- [Ministry of Power, Green Energy Open Access Rules 2022, G.S.R. 418(E), 6 June 2022](https://www.acma.in/uploads/ciculer-attachement/Electricity%20(Promoting%20Renewable%20Energy%20through%20Green%20Energy%20Open%20Access)%20Rules,2022.pdf)
- [Khaitan & Co, ERGO note on the Electricity (Amendment) Rules 2026 (20 March 2026)](https://www.khaitanco.com/sites/default/files/2026-03/ERGO_Electricity%20Amendment%20Rules%202026_20%20March%202026.pdf)

Guide: [Open access charges by state](https://invariant-ai.com/blog/open-access-charges-by-state-india)

Related: [Open access (electricity, India)](https://invariant-ai.com/glossary/open-access-india), [Cross subsidy surcharge (CSS)](https://invariant-ai.com/glossary/cross-subsidy-surcharge), [Green Energy Open Access Rules 2022 (GEOA)](https://invariant-ai.com/glossary/green-energy-open-access)