# Environmental clearance (EIA Notification 2006)

> Environmental clearance is the prior approval required under the EIA Notification 2006 for listed project types. A data centre needs it as a building and construction project of 20,000 sq m or more of built-up area, or as a township or area development project.

URL: https://invariant-ai.com/glossary/environmental-clearance-eia  
Updated: 2026-11-21 · Publisher: Invariant

Also called: environmental clearance, EC for data centre, EIA 2006 item 8(a), SEIAA clearance

Item 8(a) of the EIA Notification 2006 covers building and construction projects of 20,000 sq m to under 1,50,000 sq m of built-up area; item 8(b) covers townships and area development projects of 50 ha or more or 1,50,000 sq m or more. Category B projects are appraised by the State Environment Impact Assessment Authority (SEIAA), with applications and documents on the PARIVESH portal.

In a written Rajya Sabha reply of 6 August 2026, reported by Business Standard, the environment ministry said AI data centres do not, per se, require environmental clearance under the EIA Notification; clearance is needed when one is proposed as a building and construction project above 20,000 sq m of built-up area or as a township or area development project. In Maharashtra, SEIAA issued a clearance under item 8(a) in November 2025 for a data centre expansion covering two data centre buildings, two generator buildings and a substation, with 76,930 sq m of total built-up area.

## Sources

- [MoEF, EIA Notification 2006](https://environmentclearance.nic.in/writereaddata/EIA_notifications/2006_09_14_EIA.pdf)
- [Business Standard, AI data centres do not need standalone environmental clearance, says govt (6 August 2026)](https://www.business-standard.com/technology/artificial-intelligence/ai-data-centres-do-not-need-standalone-environmental-clearance-126080601373_1.html)
- [SEIAA Maharashtra, environmental clearance for a Navi Mumbai data centre (21 November 2025)](https://assets.airtel.in/nxtra/pdf/EC_Environmental_Clearance_Certificate_Nxtra%20Mahape_DC-02_25.11.25.pdf)

Guide: [Approvals needed for a data centre in India](https://invariant-ai.com/blog/data-centre-approvals-india)

Related: [Consent to Establish and Consent to Operate (CTE and CTO)](https://invariant-ai.com/glossary/cte-cto), [CPCB pollution category (Red, Orange, Green, White, Blue)](https://invariant-ai.com/glossary/cpcb-industry-category)