# General Network Access (GNA)

> General Network Access is the right, granted under CERC’s 2022 regulations, to inject into or draw from India’s inter-state transmission system. A bulk consumer with 50 MW or more of load can apply to connect to it directly.

URL: https://invariant-ai.com/glossary/general-network-access  
Updated: 2026-11-21 · Publisher: Invariant

Also called: GNA, general network access, ISTS connectivity, GNA regulations 2022

CERC’s Connectivity and General Network Access Regulations 2022, dated 7 June 2022, repealed the 2009 Connectivity Regulations; long-term access that had become effective under them is deemed to be GNA. Regulation 17.1(iii) lets a distribution licensee or a bulk consumer seeking to connect directly to the inter-state transmission system with a load of 50 MW and above apply for GNA.

A draft fourth amendment of 16 June 2026 proposes letting a drawee entity connected to a state transmission or distribution system also connect directly to the inter-state network, after technical studies. CERC’s explanatory memorandum names data centres among the entities that may need such dual connectivity for round-the-clock power. CTUIL supported dual connectivity for bulk consumers; Grid-India and CEA opposed it.

## Sources

- [CERC, Connectivity and General Network Access to the inter-State Transmission System Regulations 2022](https://cercind.gov.in/Regulations/175-Notification.pdf)
- [CERC, explanatory memorandum to the draft fourth amendment of the GNA Regulations (16 June 2026)](https://www.cercind.gov.in/2026/draft_reg/EM_GNA-fourth-Amnd.pdf)

Guide: [How a data centre gets a grid connection in India](https://invariant-ai.com/blog/data-centre-grid-connection-india)

Related: [CTU and STU (central and state transmission utilities)](https://invariant-ai.com/glossary/ctu-stu), [Open access (electricity, India)](https://invariant-ai.com/glossary/open-access-india), [Dual grid supply (two-source supply)](https://invariant-ai.com/glossary/dual-grid-supply)