# Point of interconnection

> The point of interconnection is where a data center’s facilities connect to the utility’s system: a bay at an existing substation, or a new switching station on a passing transmission line. The MW a site can get is studied separately at each one.

URL: https://invariant-ai.com/glossary/point-of-interconnection  
Updated: 2026-11-20 · Publisher: Invariant

Also called: POI, point of interconnection (POI), interconnection point, point of service

Choosing the point of interconnection is one of the first decisions in a large-load request. Two stations a mile apart can differ by hundreds of MW because of the lines and transformers behind them. Tapping a passing line requires a new switching station, which MISO's MTEP24 cost guide puts at about $15.8 million for a four-position 345 kV ring bus.

A utility load study is run for a named point, so filing at the wrong one costs months. A pre-study that tests every realistic point first is how developers avoid that.

## Sources

- [MISO transmission cost estimation guide for MTEP24](https://cdn.misoenergy.org/20240501%20PSC%20Item%2004%20MISO%20Transmission%20Cost%20Estimation%20Guide%20for%20MTEP24632680.pdf)

Guide: [Distance to substation and transmission](https://invariant-ai.com/blog/distance-to-transmission-line-data-center)

Related: [Utility-grade power study](https://invariant-ai.com/glossary/utility-grade-power-study), [Load study](https://invariant-ai.com/glossary/load-study), [Power flow study](https://invariant-ai.com/glossary/power-flow-study)