Data center power delivery schedule calculator
Work back from your opening date to the latest date you need power. Compare the proposed service date and facility megawatts for each phase.
Check your opening dates
Start with the example or enter your own dates. Enter total facility MW at the meter for each phase and the calendar days needed after power arrives.
How the dates are calculated
Subtract commissioning and buffer days from the target opening to get the latest date you need power. Add the same days to the reported service date to estimate opening. Compare service MW and demand separately.
In the example, a June 30, 2028 opening with 45 days of commissioning and buffer needs power by May 16. A June 15 service date moves the estimated opening to July 30, 30 days late, even though reported power exceeds demand by 10 MW. The 80 MW buildout still needs a service date and a power figure.
Use the service date and MW from the same documented milestone. Check what the serving utility can provide and when. Check customer construction, permits, and commissioning against their own schedules as well.