Maryland approved a $38,618,242.60 award to Joseph B. Fay Company for marine demolition and related work on November 19, 2026. That award covers contract KB-4906-0000. The replacement main span and the two land approaches have their own procurements. Look up each separately in eMaryland Marketplace Advantage (eMMA) before deciding whether to bid or approach a prime contractor.
Before you start
- The engineer estimated the marine work at $91.94 million. The approved low bid was about 58% below that figure.
- The main span request for qualifications appeared on July 21, 2026. Use the solicitation and its amendments for current dates and eligibility.
- Keep federal relief, individual state contract awards, and payments in separate records. Each answers a different question.
What are the four Key Bridge Rebuild contract numbers?
MDTA’s industry materials give each package a contract number. Use it in eMMA for the solicitation and addenda, and in archived board packets for bid tabulations and approval. The table shows the dated milestones we verified by November 25, 2026. The bidding windows for the approaches come from MDTA’s published schedule.Maryland Transportation AuthorityMaryland Transportation AuthorityMaryland Transportation Authority
| Contract number | Work package | Published milestone |
|---|---|---|
| KB-4906-0000 | Demolition and miscellaneous marine work | Award approved November 19, 2026. The board packet anticipated a December notice to proceed.Maryland Transportation AuthorityMaryland Transportation AuthorityMaryland Transportation Authority |
| KB-4907-0000 | Main span and marine approaches | Request for qualifications issued July 21, 2026. MDTA listed summer 2027 for the anticipated notice to proceed.Maryland Transportation AuthorityMaryland Transportation AuthorityMaryland Transportation Authority |
| KB-4908-0000 | South land approach | MDTA listed fall 2026 to winter 2027 for the invitation for bids.Maryland Transportation AuthorityMaryland Transportation Authority |
| KB-4909-0000 | North land approach | MDTA listed winter 2027 for the invitation for bids.Maryland Transportation AuthorityMaryland Transportation Authority |
The main span uses a two-step design-build selection. MDTA uses the qualifications submissions to shortlist firms for the second step. Those firms are invited to submit technical and price proposals. A supplier planning to work on the main span can use the shortlist once MDTA publishes it. Check the notice and amendments for any participation restrictions.Maryland Transportation AuthorityState of MarylandMaryland Transportation Authority
Who won the marine demolition contract, and what did the other firms bid?
Maryland advertised KB-4906-0000 on August 25, 2026. The November board packet lists three base bids and an engineer’s estimate of $91,940,971.38. The lowest qualified bid came from Joseph B. Fay Company. MDTA confirmed the board approved the award on November 19.Maryland Transportation AuthorityMaryland Transportation Authority
| Bidder | Base bid | Disposition in the records reviewed |
|---|---|---|
| Joseph B. Fay Company | $38,618,242.60 | Award approvedMaryland Transportation AuthorityMaryland Transportation Authority |
| Seaward Marine Corporation | $63,569,000.00 | Bid recordedMaryland Transportation Authority |
| McLean-United FSK JV | $67,862,519.00 | Bid recordedMaryland Transportation Authority |
The approved bid was 58.00% below the engineer’s estimate, calculated by dividing the difference by the estimate. The board packet gives December 2026 as the anticipated notice-to-proceed month. Look for the issued notice to confirm when contract work may start.Maryland Transportation AuthorityMaryland Transportation Authority
Key Bridge Rebuild procurement history and marine work bid results
Download the four contract records, three bids and funding timeline JSONCite dataset
Invariant (2026). Key Bridge Rebuild procurement history and marine work bid results [Data set]. https://invariant-ai.com/blog/key-bridge-rebuild-contracts#dataset
How do the earlier Kiewit contract and federal relief fit in?
MDTA approved the $73 million Phase 1 award to Kiewit in August 2024. In April 2026, the agency announced it would seek other contractors for Phase 2 construction after negotiations over the construction price. Kiewit continued work already under contract. MDTA’s progress dashboard records both temporary work platforms as completed in October 2026. A photo or construction milestone can show work in progress while a different package is still in procurement.Maryland Transportation AuthorityMaryland Transportation AuthorityMaryland Transportation Authority
FHWA made $60 million in quick-release Emergency Relief funds available to the Maryland Department of Transportation in March 2024. Congress later set the federal share of eligible Emergency Relief work at 100% and directed that specified recoveries offset federal liability. The November 2026 marine work packet lists federal reimbursement as its funding source. For payments on the marine work award, look for expenditures and reimbursement records tied to that contract.U.S. Department of TransportationU.S. Government Publishing OfficeMaryland Transportation Authority
How to track state infrastructure contracts by package
Start with the buying agency and contract number. Save the bid deadline, amendment date, tabulation date, award authority and issued notice to proceed as separate fields. Federal spending records can help trace federal obligations or assistance. For procurements administered by a state agency, start the bid search in the state’s portal.Maryland Transportation AuthorityState of MarylandU.S. Government Publishing Office
When screening jobs by geography, link a contract to the work limits shown on the project map. For the Key Bridge, the main span and land approaches share the I-695 corridor, and their packages name different parts of it. Use those locations for proximity and transport checks in Invariant Earth and keep the bid record with its issuing agency.Maryland Transportation AuthorityMaryland Transportation Authority
Questions that come up.
Who won the Key Bridge marine demolition contract?
MDTA approved the award of KB-4906-0000 to Joseph B. Fay Company on November 19, 2026. The base bid was $38,618,242.60.Maryland Transportation AuthorityMaryland Transportation Authority
Where do I find bids for the Key Bridge rebuild?
Search eMaryland Marketplace Advantage by the MDTA contract number. Check the project’s industry page for links and planned dates, and the solicitation for current eligibility, amendments and deadlines.Maryland Transportation AuthorityState of MarylandMaryland Transportation Authority
What is the Key Bridge main span contract number?
The number is KB-4907-0000. Maryland issued a request for qualifications on July 21, 2026, as the first step in selecting a design-build team.Maryland Transportation AuthorityMaryland Transportation Authority
Sources and references.
Primary sources checked for this guide on .
- Maryland Transportation AuthorityNovember 19 board packet, contract KB-4906-0000 and bid tabulation ↗
- Maryland Transportation AuthorityNovember 19 board approval and marine work award to Joseph B. Fay Company ↗
- Maryland Transportation AuthorityJune industry forum, contract numbers and procurement methods ↗
- Maryland Transportation AuthorityCurrent package listings and links to Maryland’s procurement portal ↗
- Maryland Transportation AuthorityJuly 21 main span request for qualifications and two-step selection ↗
- State of MarylandeMaryland Marketplace Advantage solicitation record for the main span ↗
- Maryland Transportation AuthorityAugust 29, 2024 approval of the Phase 1 progressive design-build contract ↗
- Maryland Transportation AuthorityApril 28, 2026 decision on the Phase 2 construction negotiations ↗
- Maryland Transportation AuthorityKey Bridge Rebuild dashboard, procurement milestones and physical progress ↗
- U.S. Department of TransportationMarch 28, 2024 Emergency Relief quick-release funding ↗
- Maryland State Police Aviation Command via U.S. Army Corps of EngineersJune 7, 2024 aerial photograph of Key Bridge salvage operations ↗
Try Invariant Earth on a site you know.
Pick a US coordinate and inspect the source, dataset vintage, and status for each field.
Open the API quickstart