Battery storage recharge calculator
Check whether a grid-scale battery can recharge before its next dispatch. Enter the MW available in each charging window, usable MWh, round-trip efficiency and the site’s export limit.
Plan one daily cycle
Use power and energy at the grid connection. Start with an empty usable energy window.
Charging windows
Enter nonoverlapping hours before dispatch and the import MW available to the battery in each.
Dispatch check
360 MWh
Usable export energy after charging
- Energy needed for dispatch
- 400 MWh
- Grid energy available to charge
- 400 MWh
- Grid energy needed for target
- 444.444 MWh
- Runtime at target output
- 3.6 hours
The plan is short by 40 MWh.
How to check a battery recharge window
Multiply the MW available for charging in each window by its length in hours. Add the resulting MWh and multiply by AC round-trip efficiency. Cap the result at the battery’s usable export energy. The dispatch needs its target MW times its duration, and the connection must support the target MW throughout the dispatch.
Can a 50 MW import limit refill a 100 MW battery in eight hours?
At 90% efficiency, eight hours at 50 MW imports 400 MWh and yields 360 MWh for export. That runs a 100 MW dispatch for 3.6 hours, leaving a 40 MWh shortfall against a four-hour target. With 400 MWh of usable export energy, the battery needs 444.44 MWh of grid input, about 8 hours and 53 minutes at 50 MW. A second one-hour window at 50 MW supplies enough energy in this example.
Which limits belong in the calculator?
Use the lower of the usable charging equipment rating and the import allowance left after any other site loads in each window. Use the lower of the discharge equipment limit and the permitted grid export. PJM’s Deka Road study evaluated 3.6 MW of charging load and 3 MW of injection in separate cases. Get the applicable limits and hours for your own connection from the utility study or agreement.
This screen assumes constant limits within each window, fixed losses at the grid connection and one charge before one dispatch. Use usable energy at the applicable age and temperature. For operating schedules, model ramping, auxiliary loads, changing efficiency and state of charge across cycles.