A utility-scale battery energy storage system (BESS) needs a connection that can take power from the grid when the project plans to charge and deliver power back when it plans to discharge. Screen those two directions separately. Record the point of interconnection, the allowed hours and operating conditions for each direction, and the upgrades and dates that apply. Then check whether the permitted charging window can refill enough energy for the discharge you plan to sell.
Before you start
- Ask the operator for maximum net import and export in MW at the same connection point, with dates, operating limits, and the documents behind both values.
- A 100 MW battery that needs to deliver 400 MWh takes nearly nine hours to refill from empty at a 50 MW import cap and 90% meter-to-meter efficiency.
- Keep MW, MWh, and service rights separate in the site record. The report for a 55 MW Virginia battery indicates grid charging in its project summary and leaves the numeric import limit unresolved at that level.
What should a utility-scale battery site screen include?
Start with the operating plan. State the planned discharge in MW, how many hours it must last, the energy available at the meter in MWh, and which hours the project needs to recharge. Identify the grid connection so both studies refer to the same physical point. If solar shares the connection, specify whether the battery can charge from the solar array, the grid, or both. Include the maximum simultaneous net export from the entire site.U.S. Energy Information AdministrationFederal Energy Regulatory CommissionCalifornia ISO
| Screen | What to record | Evidence to request |
|---|---|---|
| Charge from the grid | Net import MW, import hours by season, limits during peak load or outages, and any restrictions on grid charging. | Charging cases and operating assumptions, with the applicable service or agreement terms from the operator.Federal Energy Regulatory CommissionCalifornia ISO |
| Discharge to the grid | Net export MW, usable MWh at the meter, export duration, applicable curtailment, and commercial service requested. | Export cases and agreement, including the limits at the proposed point of interconnection and any deliverability terms.Federal Energy Regulatory CommissionU.S. Energy Information Administration |
| Check the queue and upgrades | Shared connection point, earlier requests the study depends on, upgrade owner, cost allocation, and the date each upgrade is needed. | The operator’s queue and dated study revisions, facilities scope, and schedule for construction and energization.PJM InterconnectionPJM Interconnection |
| Check land and access | Controlled acreage, equipment and access layout, flood and drainage constraints, fire access and spacing, and the route of the lead line. | A layout tied to the actual parcels, local planning and fire requirements, and the easements needed for the route.NYSERDA |
FERC’s Order No. 2023 directs U.S. transmission providers using the applicable procedures to study storage with assumptions that reflect proposed charging behavior, subject to reliability and good utility practice. Ask the provider which tariff and process apply to the particular connection and whether you need separate charging service. Capture the actual hours, limits, and conditions in the documents that will govern operation.Federal Energy Regulatory CommissionFederal Energy Regulatory Commission
Three public studies show three kinds of charging evidence
| Study | Discharge or output evidence | Charge evidence | What to carry forward |
|---|---|---|---|
| Tupelo Storage · Virginia · PJM 2026 | 55 MW maximum facility output and 220 MWh battery specification. | The project summary says grid charging is planned. The summary gives no numeric import MW. | Ask for the charging case and import terms. PJM’s Phase II cost summary allocates an estimated $7.64 million to this request.PJM Interconnection |
| Deka Road · Pennsylvania · PJM 2011 | 3 MW studied injection. PJM recognized zero MW as Capacity in the study and described the export as curtailable for reliability. | 3.6 MW studied load at the same existing 69 kV connection. | The two directional values differ. Preserve the connection arrangement and the study’s stated treatment of export.PJM Interconnection |
| Oneida Energy Storage · Ontario · IESO 2022 | 250 MW injection evaluated in the study scope. The stated project rating was 250 MW and 1,000 MWh. | 250 MW withdrawal evaluated in the same assessment. | Conditional approval carried connection requirements. Certain outage conditions limited the equipment’s ability to provide maximum active power alongside required reactive power.Independent Electricity System Operator |
At Oneida, the grid operator required reactive power capability equal to 33% of rated active power at the transformer terminals. It found 28.4% under the typical voltage condition it assessed at maximum injection. Reactive power helps control voltage and affects how much equipment capacity remains for active power. The assessment required the applicant to address that shortfall. Northland Power announced on May 7, 2025 that Oneida had entered commercial operation. The study figures above describe the proposed project and study conditions in 2022.Independent Electricity System OperatorNorthland Power
The practical test for a new site is to ask which limits already apply, which depend on planned equipment, and which conditions would reduce either direction. For queue records, save the project ID, resource type, stage, related requests, study date, and document URL. For an upgrade, keep the cost estimate vintages and responsibility for construction beside the expected service date.PJM InterconnectionIndependent Electricity System OperatorPJM Interconnection
Battery import and export evidence from three connection studies
Download the site study records and recharge calculation JSONCite dataset
Invariant (2026). Battery import and export evidence from three connection studies [Data set]. https://invariant-ai.com/blog/battery-storage-site-interconnection#dataset
Can a 50 MW import limit refill a 100 MW battery overnight?
Consider two illustrative battery sites that each need to export 100 MW for four hours and can import up to 50 MW when charging is permitted. Assume 400 MWh of usable export energy, an empty usable energy window at the start, and a constant 90% round-trip efficiency measured at the connection point. To calculate the export energy the charging window can support, multiply 50 MW by the allowed hours and 0.90, up to the battery’s 400 MWh usable limit.
| Allowed charging window | Maximum energy the grid can deliver in the window | Usable export energy from that charge | At 100 MW |
|---|---|---|---|
| 8 hours | 400 MWh | 360 MWh | 3.6 hours. Short by 40 MWh. |
| 9 hours | 450 MWh | 400 MWh, capped by usable energy | 4 hours. Meets the energy requirement in this screen. |
The battery needs about 444 MWh of grid energy and 8 hours, 53 minutes, and 20 seconds at full import to refill from empty. Nine hours leaves little margin. Check the allowed hours against seasonal restrictions, the state of charge at the start of each dispatch cycle, and end-of-life usable capacity. A commercial model should also account for charge ramp, losses across operating conditions, and which hours have power available at an acceptable price.
How to compare candidate battery sites before signing an option
Use parcel boundaries, terrain, flood layers, and transmission maps to check the land and map viable connection routes. Use the operator’s queue and studies at each proposed point to identify other projects and upgrades. A substation distance field is useful for finding candidates. A dated charge and discharge case is what helps the team compare two sites with similar distances.PJM InterconnectionNYSERDA
Send the same operating request for each candidate. State the MW and MWh at the meter, the charging schedule, the expected start date, and how operation changes under outages. Ask the operator to return the cases and documents behind each answer, the earliest date each direction can operate, and the cost and schedule of shared or assigned upgrades. Keep unknown values visible in the shortlist so a reviewer can tell where the investment case relies on unverified service.Federal Energy Regulatory CommissionPJM InterconnectionIndependent Electricity System Operator
Questions that come up.
Does a 100 MW battery always need 100 MW of charging capacity?
Charge MW depends on how much energy the battery needs to restore and how long it can charge. A 400 MWh export target with 90% round-trip efficiency needs about 444 MWh of imported energy from empty. At 50 MW, that requires nearly nine hours at full import.
Can a generator interconnection queue tell me how much a battery can charge?
A queue may list the battery’s size, resource type, and application status. Look for separate numeric import MW and operating conditions in the project’s study and applicable service documents. Some study summaries identify grid charging without stating the allowed import MW.PJM InterconnectionPJM Interconnection
How do I compare a standalone battery with solar plus storage?
Compare net import and simultaneous net export at the same point of interconnection. For a hybrid, specify whether the battery can charge from the grid and how the controls share the connection with solar. Document the operating limits the provider actually studied and the conditions attached to any agreement.Federal Energy Regulatory CommissionCalifornia ISO
Sources and references.
Primary sources checked for this guide on .
- Federal Energy Regulatory CommissionExplainer on the Interconnection Final Rule ↗
- Federal Energy Regulatory CommissionStorage charging assumptions, FERC docket ER24-330-001 ↗
- U.S. Energy Information AdministrationDuration of utility-scale batteries depends on how they are used ↗
- PJM InterconnectionNew Service Requests Cycle Process, Manual 14H ↗
- California ISODynamic model review guideline for inverter-based interconnection requests ↗
- NYSERDABattery Energy Storage System Guidebook ↗
- PJM InterconnectionTupelo Storage, AG2-272 Phase II System Impact Study ↗
- PJM InterconnectionDeka Road, W3-093 Feasibility and Impact Study ↗
- Independent Electricity System OperatorOneida Energy Storage, System Impact Assessment ↗
- Northland PowerMay 7, 2025 announcement of Oneida commercial operation ↗