Before you option land for a utility-scale solar farm, check whether the tract fits the proposed array and whether the grid can take the project’s output on your schedule. Use GIS to calculate contiguous buildable acreage and map routes to candidate connections. Then verify the exact point of interconnection, requested export in MW AC, upgrade costs, and schedule against the operator’s studies and project agreement.
Before you start
- Keep the buildable polygons, the exclusions that produced them, and the largest contiguous area. The acreage on an assessor record cannot tell you what fits.
- Use line and substation maps to find connection candidates. Verify the terminal or line tap, the route from the project, and the export case with the transmission provider.
- Carry forward the latest study version and scope. At one Ohio substation, the estimate for a 200 MW solar uprate went from $2.68 million to $6.34 million between PJM study phases.
Calculate buildable acres inside the land you can control
Start with the surveyed or cadastral boundary and the parcels you can actually assemble. Mark gaps, easements, and access you would need across other land. Set a preliminary slope and grading tolerance with the layout engineer. Keep terrain, mapped wetlands, flood hazards, setbacks, and permit constraints as separate layers so the team can see and revise each assumption.
| Screen | Where to start | What to keep |
|---|---|---|
| Land and site control | County parcel GIS, assessor records, recorded plats and easements, and the current local siting rules. | Parcel IDs and boundaries, control dates, known easements, and the jurisdiction responsible for each approval.U.S. Department of Energy |
| Slope and grading | USGS 3DEP elevation. Choose the best available resolution for the site and check it against a survey before design. | Slope raster, elevation resolution and vintage, the assumed slope limits, and areas that need a grading check.U.S. Geological Survey |
| Water and hazards | U.S. Fish and Wildlife Service wetland mapping and FEMA’s National Flood Hazard Layer. | Mapped wetland and flood polygons, map dates, any screening buffers, and areas to verify in the field.U.S. Fish and Wildlife ServiceFEMA |
| Solar resource and layout | National Solar Radiation Database weather and irradiance, a preliminary array layout, and site access plans. | Resource dataset and weather years, MW DC, inverter MW AC, usable blocks, and space for roads, drainage, and equipment.National Laboratory of the Rockies |
| Connection route | Transmission-owner maps and records, local parcel geometry, and the applicable generator interconnection queue. | Candidate connection, likely transmission owner, plausible lead-line route, and the parcels or rights of way the route crosses.Lawrence Berkeley National LaboratoryPJM Interconnection |
Intersect each exclusion with the tract, merge the overlapping exclusions, and subtract their combined area using a local projected coordinate system suited to measuring acreage. Say a 960-acre tract has 150 acres above your slope limit and 120 acres in a preliminary wetland exclusion, with 45 acres that satisfy both. The combined exclusion is 225 acres, leaving 735 acres for further screening. A layout with a largest contiguous block of 410 acres has a different design problem from a single 735-acre block. These numbers are illustrative. Keep each disconnected block, then test roads, drainage, equipment, and grading on the layout.PVcase
What establishes solar export capacity at a substation?
A transmission map can show that a line crosses the property. A queue can show who has applied and what the operator has published about those applications. To underwrite export, identify the exact connection and ask the operator which service, study assumptions, upgrades, and operating limits apply to your request. Ask for the date of the evidence and any conditions on construction and operation.Lawrence Berkeley National LaboratoryPJM Interconnection
- Record the proposed export at the connection in MW AC. Track panel nameplate in MW DC and inverter rating separately. For co-located batteries, also specify import, discharge, plant controls, and which resources can operate at the same time.
- Name the substation bus or line tap, voltage, transmission owner, and proposed generator lead. Trace a viable route and identify crossings or easements that could delay it.
- Check the operator’s queue and study versions by request ID. Capture earlier requests the study depends on, other affected transmission systems, required upgrades, cost allocation, and who is responsible for building what.
- Get the latest applicable study, agreement, and upgrade schedule before treating an export assumption as committed. Confirm the applicable operating limits, milestones, and deliverability terms with the operator.
The public queue is useful when an option period is short. It can help focus questions and reveal competing or dependent requests. Each entry has a status and a reporting date. A withdrawn project’s requested MW cannot be treated as capacity available to your tract. For distribution-connected projects, start with the serving utility and its applicable process.Lawrence Berkeley National Laboratory
At Nottingham 138 kV, the same uprate got a higher estimate
PJM studied two linked requests from Energy Pastures Solar Project in Harrison County, Ohio. AG2-082 was the original 200 MW request. AH1-580 requested a 200 MW increase at the same point of interconnection. The 400 MW maximum facility output on the AH1-580 report includes the original 200 MW. Adding that 400 MW to the original 200 MW would count the original request twice.PJM InterconnectionPJM InterconnectionPJM Interconnection
| PJM request | Phase I estimate · Oct 29, 2025 | Phase II estimate · Jun 3, 2026 | Increase |
|---|---|---|---|
| AG2-082 · original 200 MW | $2,326,000 | $4,164,556 | $1,838,556PJM InterconnectionPJM Interconnection |
| AH1-580 · 200 MW uprate | $2,678,000 | $6,336,540 | $3,658,540PJM InterconnectionPJM Interconnection |
The uprate still requested 200 MW of energy service in Phase II. Its allocated physical network upgrade line increased from $2.326 million to $4.575 million, and the new estimate included $609,937 for transmission-owner interconnection facilities. Phase I had recorded zero on that facilities line and said that the physical facilities study would begin in Phase II. Carry the scope and stage beside the number. A zero from an earlier study may describe what has been priced so far.PJM InterconnectionPJM Interconnection
We used the project allocation total as printed in each report. Those totals are estimates for those requests. The Phase II reports used a 2028 model base case. A separate agreement and project schedule would establish rights and milestones. The study figures cannot establish remaining capacity for a new applicant at Nottingham.PJM InterconnectionPJM Interconnection
Nottingham solar interconnection study comparison
Download the four dated PJM study records JSONCite dataset
Invariant (2026). Nottingham solar interconnection study comparison [Data set]. https://invariant-ai.com/blog/solar-farm-site-selection-gis#dataset
Which GIS tools and APIs fit a solar developer’s workflow?
Use public GIS layers when you need to run your own polygon calculations. PVcase Prospect documents a greenfield workflow for filtering by buildable acres and working with site constraints. Geoforge’s example report shows how a separate power screen can organize modeled headroom, queue records, and upgrades. Ask each provider which cases it covers and which results you can export with dates and sources.PVcaseGeoforge
Invariant Earth publishes fields for elevation, slope, wetland and flood indicators, and distance to transmission lines and substations. Use point fields to enrich a search, then use the tract and layout polygons to calculate buildable acreage. When evaluating an API, ask for the original source and geometry, the units, and the behavior when data is missing. Invariant publishes this guide. We checked the listed capabilities against public documentation.InvariantInvariant
A useful shortlist lets the next reviewer recreate the decision. Save the parcel and buildable geometry, the assumed project layout, and one record per candidate connection. Give each record a source, date, proposed MW, study stage, estimated upgrades, and open items. Before a land option goes hard, assign a person and due date to the evidence that could change your decision.
Questions that come up.
Can I estimate buildable solar acres from parcel data?
Use the parcel boundary as the starting geometry. Subtract the union of exclusions and project setbacks, then keep both the total remaining area and the contiguous blocks. Check the preliminary result against site control, a layout, local requirements, and field surveys.U.S. Department of EnergyPVcaseU.S. Fish and Wildlife Service
Does a nearby power line mean a solar farm can connect?
A nearby power line gives you a candidate to investigate. Confirm the actual connection configuration, who owns the line, how the project can reach it, and whether the operator’s study supports the requested export under its modeled conditions.PJM InterconnectionPJM Interconnection
Why are the PJM MW Energy and MW Capacity fields different?
PJM reports the MW in the energy request separately from the MW it recognizes as Capacity in the study. AH1-580 lists a 200 MW energy request and a 134 MW Capacity increase. Its 400 MW maximum facility output refers to the combined facility after the proposed uprate.PJM Interconnection
Sources and references.
Primary sources checked for this guide on .
- U.S. Department of EnergyLarge-scale solar siting resources ↗
- U.S. Geological Survey3D Elevation Program products and services ↗
- U.S. Fish and Wildlife ServiceWetlands mapping limitations and exclusions ↗
- FEMANational Flood Hazard Layer map service ↗
- National Laboratory of the RockiesNational Solar Radiation Database downloads ↗
- PVcasePVcase Prospect greenfield siting guide ↗
- Lawrence Berkeley National LaboratoryTransmission interconnection queue data and coverage ↗
- PJM InterconnectionNew service requests cycle process, Manual 14H ↗
- PJM InterconnectionTransition Cycle 2, Phase II summary and common connections ↗
- PJM InterconnectionAG2-082 study, Phase I, October 29, 2025 ↗
- PJM InterconnectionAG2-082 study, Phase II, June 3, 2026 ↗
- PJM InterconnectionAH1-580 study, Phase I, October 29, 2025 ↗
- PJM InterconnectionAH1-580 study, Phase II, June 3, 2026 ↗
- GeoforgeExample power screening report ↗
- InvariantPublic Earth API field catalog ↗
- InvariantEarth API responses and provenance ↗
Try Invariant Earth on a site you know.
Pick a US coordinate and inspect the source, dataset vintage, and status for each field.
Open the API quickstart