How to Verify Industrial Wastewater Capacity for a Factory Site

Check sewer line capacity, pump stations, treatment plant allocations and industrial pretreatment before choosing a factory site. See the dated Camp Hall records.

Diagram comparing the historic 170,000 gallons per day reported for Camp Hall sewer lines, 780,000 for a pump station, and 22.5 million for the Lower Berkeley treatment plant.

Camp Hall’s 2021 site sheet and Berkeley County’s fiscal 2023 report describe different parts of the sewer system. The figures have different scopes.

Ask the sewer utility to confirm three things for your factory’s proposed flow. Can the pipes and pump stations carry it? Can the receiving plant accept the volume and pollutant load after existing commitments? What local limits and pretreatment apply to the process? At Camp Hall Commerce Park, public records give distinct figures for the sewer lines, pumps, a planned extension and the receiving plant. Each helps narrow the questions to ask before you option a tract.

Before you start

  • Get the utility’s written decision for the exact connection, average and peak flow, wastewater characteristics and date you need service.
  • Reported flow, rated treatment capacity and capacity already obligated under permits are different measurements.
  • Camp Hall’s 2021 site sheet reported 170,000 gallons per day of excess capacity for in-park lines and 780,000 for a pump station. The larger plant-wide and planned project figures have different scopes.

What the Camp Hall records say about sewer capacity

Camp Hall identifies Berkeley County Water and Sanitation as the sewer provider. South Carolina’s older site sheet lists capacity for parts of the park. The county’s later records show why you need to track the planned service route and the date any upgrades can serve the tract.Camp HallSouth Carolina Department of CommerceBerkeley County

RecordReported figureWhat the figure covers
Park site sheet, 2021170,000 gallons per day for in-park sewer lines and 780,000 for a pump stationHistorical excess capacity reported for distinct parts of the collection system. The same sheet described 6.6 million gallons per day as expected system excess after improvements.South Carolina Department of Commerce
County public utilities minutes, November 14, 20221 million gallons per day design target discussedThe proposed project would send wastewater to Lower Berkeley. Staff described this as a change from an earlier plan to send it to Central Berkeley.Berkeley County
Berkeley County fiscal 2023 financial report22.5 million gallons per dayTreatment capacity reported for the entire Lower Berkeley plant. The report separately describes the Camp Hall project as adding 1 million gallons per day of sewer capacity for the park and other projects along I-26.Berkeley CountyBerkeley County
County procurement, June 17, 2025$42,835,995 listed as intent-to-award amountThe Camp Hall Master Sewer Extension contract listing names a contractor. It records a procurement stage. Ask the utility for commissioning and the earliest service date at your tract.Berkeley County Procurement

For a factory planning 200,000 gallons per day, the historic line figure is 30,000 gallons per day below the proposed flow even though the pump figure is higher. Use that comparison to ask which lines and pumps would actually carry your flow and what has changed since the site sheet. The records reviewed leave current capacity available to a new customer open.South Carolina Department of CommerceBerkeley County Procurement

Camp Hall industrial sewer and Lower Berkeley treatment capacity records

Download the Camp Hall sewer and treatment records CSV
Cite dataset

Invariant (2026). Camp Hall industrial sewer and Lower Berkeley treatment capacity records [Data set]. https://invariant-ai.com/blog/industrial-wastewater-capacity-site-selection#dataset

Archived release v1.0.1 · 2026-11-26

Download citation (CSL JSON)

Check water and sewer service by address

How much treatment capacity is actually available?

Check the plant’s permitted flow and the measurement period behind any flow report. Then ask the utility for the volume already committed to developments, including projects that have permits but are still under construction. South Carolina tracks that obligated flow alongside what the plant actually receives.South Carolina Department of Environmental Services

In South Carolina’s example, a 5 million gallon per day plant receives 3 million gallons per day on average and has 3.5 million gallons per day already obligated. The design less obligated flow leaves 1.5 million gallons per day of hydraulic margin on paper. Using current flow alone would show 2 million. The 500,000 gallon gap is a reason to ask about permits and allocations before judging sewer availability from discharge monitoring data.South Carolina Department of Environmental Services

Check the collection system and plant separately. An undersized line or pump can limit a connection even where the plant has room. A plant also needs to accept the wastewater’s strength and pollutants. Ask for any upgrades, who pays, and the dates when the affected facilities and your connection can operate.South Carolina Department of Environmental ServicesSouth Carolina Department of Environmental ServicesBerkeley County Water and Sanitation

When does a factory need industrial pretreatment?

Pretreatment reduces or changes pollutants before industrial wastewater enters a public sewer. Ask the local pretreatment program which national standards, local discharge limits and permit conditions apply to each process stream. An average of 25,000 gallons per day of process wastewater is one federal significant industrial user criterion. That calculation excludes sanitary, noncontact cooling and boiler blowdown flows. Industry category, the share of plant capacity and the control authority’s designation can also matter below that volume.Electronic Code of Federal RegulationsElectronic Code of Federal RegulationsSouth Carolina Department of Environmental Services

Send the utility your process description, a flow and strength profile, expected batch discharges and the start dates by phase. Ask what it needs for biochemical oxygen demand, suspended solids, pH, temperature and pollutants specific to the process. Where South Carolina requires a wastewater construction permit for on-site pretreatment, obtain it before building that treatment system.U.S. EPASouth Carolina Department of Environmental ServicesBerkeley County Water and Sanitation

What to submit to get a written sewer capacity decision

Send the utilityAsk for in writing
Exact parcel, phase plan, proposed wastewater streams and proposed tie-inConfirmation of the sewer provider, receiving plant, connection location and any off-site upgrades.
Average day, maximum day and peak discharge for each phaseFlow the utility can accept, current commitments relevant to the connection, and when the line, pumps and plant can serve each phase.
Process wastewater constituents, preliminary sampling and treatability dataApplicable discharge limits, pretreatment and monitoring requirements, and approval conditions.
Required startup date and fallback schedulePermit dependencies, connection and construction costs, what secures the allocation, when it expires, and the earliest confirmed service date.
Berkeley County Water and SanitationU.S. EPASouth Carolina Department of Environmental Services

Use Invariant Earth to identify the parcel and available service-area records at the start of the shortlist. Keep the original utility decision and supporting documents with that parcel so the team can compare the same dated evidence across properties.Invariant Earth

Questions that come up.

Can I use plant design capacity minus current flow to estimate available sewer capacity?

Get the utility’s committed flow as well. Current flow leaves out developments that have a sewer permit or allocation and have yet to start discharging. Confirm whether the exact service line and pumps can carry your proposed volume.South Carolina Department of Environmental Services

Can a factory under 25,000 gallons per day still need a pretreatment permit?

Yes. Process category, pollutant characteristics, the share of the receiving plant’s dry-weather capacity and local rules or designation can require review below that volume. Ask the control authority which standards and permits apply to the proposed streams.Electronic Code of Federal RegulationsElectronic Code of Federal RegulationsSouth Carolina Department of Environmental Services

Who confirms sewer capacity at Camp Hall Commerce Park?

Camp Hall names Berkeley County Water and Sanitation as the sewer provider. Ask the county to identify your connection and receiving plant, confirm the capacity and service date for your proposed flow, and refer you to the applicable pretreatment staff.Camp HallBerkeley County Water and Sanitation

Sources and references.

Primary sources checked for this guide on .

  1. Camp HallCamp Hall utilities and sewer provider ↗
  2. South Carolina Department of CommerceCamp Hall Palmetto Site sheet, PDF page 1, wastewater lines and pump station ↗
  3. Berkeley CountyNovember 14, 2022 public utilities minutes, item 3.b, planned service to Lower Berkeley ↗
  4. Berkeley CountyFiscal 2023 financial report, printed page 14, Lower Berkeley treatment capacity ↗
  5. Berkeley CountyFiscal 2023 financial report, printed page 15, Camp Hall Sewer Improvement ↗
  6. Berkeley County ProcurementCamp Hall Master Sewer Extension, solicitation BCWS-12-24/25 intent to award ↗
  7. South Carolina Department of Environmental ServicesWastewater construction permits and obligated plant flow ↗
  8. South Carolina Department of Environmental ServicesSewer pretreatment program and construction permits ↗
  9. Electronic Code of Federal Regulations40 CFR 403.3(v), significant industrial user definition ↗
  10. Electronic Code of Federal Regulations40 CFR 403.5, prohibited discharges and local limits ↗
  11. U.S. EPAIndustrial User Permitting Guidance Manual, application contents ↗
  12. Berkeley County Water and SanitationEngineering contacts and information for water and sewer availability requests ↗
  13. Invariant EarthCheck water and sewer service by address ↗