AEP Ohio data center demand charge calculator

Calculate monthly billing demand and base distribution charges for an AEP Ohio Schedule DCT new-load contract during or after its load ramp.

Billing inputs

Use one energized contract and one billing month.

MW
Use the final MW in the signed service agreement.
MW
Use the demand reading Ohio Power uses for this bill.
MW
Use the greatest billed MW from the preceding 11 months.

Monthly billing demand

85 MW

Base distribution and customer subtotal
$686,986.30
Contract-tier floor
82.5 MW
Prior-bill floor
85 MW
Distribution at $8.08 per kW
$686,800.00
Monthly customer charge
$186.30
Demand charges above the metered peak
$161,600.00

Budget energy, transmission and other riders, applicable reactive demand charges, and taxes separately.

How AEP Ohio calculates Schedule DCT demand

During the ramp, use the greater of the metered peak and 85% of the monthly ramp capacity in the agreement. After the ramp, compare the metered peak with the contract-tier minimum and 85% of the highest monthly billing demand from the preceding 11 months. Multiply the largest demand in kW by the filed distribution rate, then add the monthly customer charge.

How is the contract-tier minimum set?

From 25,001 through 75,000 kW of contracted capacity, start at 15,000 kW and add 85% of capacity above 25,000 kW. Above 75,000 kW, start at 57,500 kW and add all capacity above 75,000 kW, then cap the contract-tier minimum at 85% of total contracted capacity.

What is the charge for a 100 MW primary-voltage contract?

With a 65 MW peak after the ramp and a prior billed peak of 100 MW, the lookback gives 85 MW and the contract-tier floor gives 82.5 MW. The bill uses 85 MW. At $8.08 per kW, base distribution costs $686,800. Add the $186.30 customer charge for a base subtotal of $686,986.30.

During the ramp, a 50 MW agreed monthly capacity and a 35 MW peak produce 42.5 MW of billed demand. The primary-voltage base subtotal is $343,586.30.

Which contract and rate should you enter?

Use the Ohio Power schedule assigned to the account. This example models one energized New Load contract at primary or secondary service voltage. The rates come from the November 2026 tariff book. Ask Ohio Power how it treats affiliated loads, alternate service voltages, and agreements with service that has yet to energize.