Data center power capacity calculator

Convert IT load to facility MW, check how much on-site power remains after a generator outage, and estimate battery runtime for the shortfall.

Design case

Enter both power figures at the facility intake, under the conditions for each case.

Servers, storage, and networking.
Use the ratio for the design condition.

Capacity check

62.5 MW

Total facility demand

Normal conditions
7.5 MW spare
Outage case
7.5 MW short
Check battery runtime during an outage

Enter the battery’s discharge power and usable energy at the facility intake. Use the energy available at the expected state of charge after losses and reserves.

Discharge power needed
7.5 MW
Usable energy needed
1.875 MWh
Runtime at this shortfall
16 min

The battery covers the entered duration at this shortfall.

How to read the result

Multiply IT load by the facility-to-IT power ratio. Subtract that demand from the net power available in each case. A shortfall is the extra net power needed at the facility intake for that case.

In the example above, 50 MW of IT load at a ratio of 1.25 needs 62.5 MW at the intake. A plant that delivers 70 MW normally has 7.5 MW to spare. With 55 MW available after the largest unit is lost, the facility is 7.5 MW short.

For sizing, use the engineer’s demand schedule or a ratio calculated for the design condition. Annual power usage effectiveness (PUE) measures energy over a year. Obtain net plant output after site derating, plant auxiliary loads, and losses to the intake. Include grid imports only where the utility can supply them in the scenario under review.

How much battery energy covers a generator shortfall?

Multiply the constant shortfall in MW by the duration in hours to get the usable MWh needed. A 500 MW IT campus at a design ratio of 1.20 needs 600 MW at the facility intake. With 550 MW available after generators settle into the outage condition, the 50 MW shortfall requires 25 usable MWh for 30 minutes. The inverter also needs to deliver at least 50 MW to the intake during that period.

This calculation holds the shortfall constant. Model the first seconds after a trip, generator ramp, black start, battery recharge, and repeat outages separately. Plan for a sustained source or load reduction before the battery is depleted.

Before using the result for procurement, have the engineer check reserves, fuel delivery, switching, common equipment, and load pickup.