Data center · Definition

Consent to Establish and Consent to Operate (CTE and CTO)

Also known as: CTE and CTO, consent to establish, consent to operate, pollution board consent, CTE CTO data centre

Consent to Establish (CTE) and Consent to Operate (CTO) are the permissions a state pollution control board grants under the Water Act 1974 and the Air Act 1981: CTE before a project is set up, CTO before it starts operating.

Section 25 of the Water Act 1974 requires the state board’s previous consent to establish an industry, operation or process likely to discharge sewage or trade effluent, and section 21 of the Air Act 1981 requires it to establish or operate an industrial plant in an air pollution control area. CPCB’s January 2025 classification lets boards grant CTO for up to 5 years to Red, 10 years to Orange and 15 years to Green category units.

For a data centre, CPCB says projects such as data centres whose pollution potential comes from gensets only may be classified by genset capacity and fuel, with 1 MVA or more on liquid fuel in Orange and on gaseous fuel in Green. Building construction of 20,000 sq m or more of built-up area is separately Orange, and its consents are to be taken as per its environmental clearance conditions. State boards must adopt the CPCB classification and may categorise new or left-out sectors themselves, so confirm the category with the board for the site.

Approvals needed for a data centre in India ↗

Related terms