← Glossary

Data center · Definition

Environmental clearance (EIA Notification 2006)

Also known as: environmental clearance, EC for data centre, EIA 2006 item 8(a), SEIAA clearance

Environmental clearance is the prior approval required under the EIA Notification 2006 for listed project types. A data centre needs it as a building and construction project of 20,000 sq m or more of built-up area, or as a township or area development project.

Item 8(a) of the EIA Notification 2006 covers building and construction projects of 20,000 sq m to under 1,50,000 sq m of built-up area; item 8(b) covers townships and area development projects of 50 ha or more or 1,50,000 sq m or more. Category B projects are appraised by the State Environment Impact Assessment Authority (SEIAA), with applications and documents on the PARIVESH portal.

In a written Rajya Sabha reply of 6 August 2026, reported by Business Standard, the environment ministry said AI data centres do not, per se, require environmental clearance under the EIA Notification; clearance is needed when one is proposed as a building and construction project above 20,000 sq m of built-up area or as a township or area development project. In Maharashtra, SEIAA issued a clearance under item 8(a) in November 2025 for a data centre expansion covering two data centre buildings, two generator buildings and a substation, with 76,930 sq m of total built-up area.

Approvals needed for a data centre in India ↗

Related terms

Sources

Last updated 21 November 2026