CTU and STU (central and state transmission utilities)

Also known as: CTU, STU, CTUIL, state transmission utility, central transmission utility

The Central Transmission Utility (CTUIL) plans and coordinates the inter-state transmission system and is the nodal agency for connectivity to it; each state transmission utility (STU) plans and coordinates the state’s intra-state transmission system.

Under sections 38 and 39 of the Electricity Act 2003, the Central Transmission Utility undertakes transmission through the inter-state system and plans and coordinates it, and each State Transmission Utility does the same for the intra-state system. Under CERC’s 2022 regulations the CTU is the nodal agency for connectivity and General Network Access to the inter-state system.

Data centres now appear in CTU planning. In CERC’s June 2026 explanatory memorandum, CTUIL cited uncertainty in bulk loads such as green hydrogen and data centres as one reason it could not finalise transmission for the remaining 33 GW of about 53 GW of in-principle connectivity granted in Rajasthan, Gujarat and Maharashtra.

How a data centre gets a grid connection in India ↗