Data center · Definition
General Network Access (GNA)
Also known as: GNA, general network access, ISTS connectivity, GNA regulations 2022
General Network Access is the right, granted under CERC’s 2022 regulations, to inject into or draw from India’s inter-state transmission system. A bulk consumer with 50 MW or more of load can apply to connect to it directly.
CERC’s Connectivity and General Network Access Regulations 2022, dated 7 June 2022, repealed the 2009 Connectivity Regulations; long-term access that had become effective under them is deemed to be GNA. Regulation 17.1(iii) lets a distribution licensee or a bulk consumer seeking to connect directly to the inter-state transmission system with a load of 50 MW and above apply for GNA.
A draft fourth amendment of 16 June 2026 proposes letting a drawee entity connected to a state transmission or distribution system also connect directly to the inter-state network, after technical studies. CERC’s explanatory memorandum names data centres among the entities that may need such dual connectivity for round-the-clock power. CTUIL supported dual connectivity for bulk consumers; Grid-India and CEA opposed it.
How a data centre gets a grid connection in India ↗
Related terms
Sources