Data center site selection tools for power capacity

Compare six power screening tools for a 200 MW data center. See how a South Carolina docket separates load plans, upgrades, and actual energization.

Diagram of the Aiken No. 3 to Mt. Zion transmission buildout. A 16.2-mile section leads to the Mt. Zion switching station. Two feeders totaling 1.5 miles lead to customer substations. The first energized on December 15, 2025.

Simplified transmission scope for the Aiken project. The South Carolina Public Service Commission granted certificates in July 2024. Santee Cooper later reported the first customer substation energized in December 2025.

For a 200 MW data center, use a power screening tool to compare where you could connect, how much load each point can support under a stated study case, and what has to happen before each phase. Start with a site search or sourced grid report, then get a study that tests your actual load profile. Before committing to a site or promising a date, ask the serving utility for the documents behind the MW, the upgrades, and the schedule.

Before you start

  • Compare tools on the same site, load ramp and target dates. Ask which connection points, planning cases, prior requests and outages drive each answer.
  • Keep modeled load capacity, signed service terms, construction and energization as separate steps.
  • For a planned 200 MW project in South Carolina, the accepted connection required work across two transmission owners and customer substations. The utility later reported that one substation had energized while the other had a revised target window.

Which power screening tool fits the decision?

Use the comparison to choose a starting point for procurement. It describes what each provider publishes about its tools as of November 22, 2026. Invariant publishes this guide. The South Carolina example comes from the public docket. It is independent of the provider descriptions.

ToolWhat the provider documentsWhat to ask for on the same 200 MW site
PacesPortfolio and parcel screening with regional withdrawal-capacity views, plus project reports and support for interconnection applications.Ask how the regional capacity layer was calculated. Request a worked report with the selected connection, modeled phase MW, dependencies, and an explanation of how it arrived at its dates.Paces
GeoforgeSite reports combine offtake capacity by year and scenario, modeled on ISO/RTO grid cases as described by the provider, with queue context and planned upgrades. Its example shows a connection shortlist and an estimated time-to-power range.Ask which loads and upgrades were included in each scenario. Have the provider show how the timeline changes if a named upgrade slips or a competing request advances.GeoforgeGeoforge
PVcase ProspectMap-based screening using modeled withdrawal capacity. Its capacity documentation explains the use of planning scenarios and a focus on later-stage queue projects.Confirm the exact substation bus, constraint scenario and year. Ask which projects were included and how the report handles a load larger than the displayed withdrawal capacity.PVcasePVcase
GridCAREGrid simulation and utility collaboration to identify underused capacity. Its National Grid announcement describes an effort to identify capacity for large loads in New York.Confirm the utility and service area for your site. Ask what flexibility or curtailment the case assumes, how many MW would be available in each phase, and who can approve the service terms.GridCARE
MireyeCited location and infrastructure data, including substations, transmission voltage classes and site screening bundles.Use it to identify nearby candidates and inspect sources. Ask separately for evidence behind any MW figure or service date you intend to carry into underwriting.Mireye
InvariantEarth provides parcel and grid context. The published study workflow describes AC power flow and loss-of-one-element contingency tests by connection and study year, with indicative upgrade costs and timing.Ask which cases are reconstructed or supplied by a utility, how the model was checked, and what evidence supports each phase and its cost range.InvariantInvariant

Treat the date from a screening report as an estimate with a source and assumptions. A queue entry records a request or study status, depending on the system. Ask whether the product shows large loads, generation, or both, and which requests were actually included in the planning case. Operators publish different amounts of load information. For example, ERCOT has a separate large-load integration process.GeoforgePVcaseERCOT

Aiken County shows what a 200 MW connection takes

Central Electric Power Cooperative’s application in South Carolina PSC docket 2024-61-E identified a planned data center with up to 200 MW of peak demand. It described a large-power service agreement entered in September 2023. Santee Cooper initially considered a 115 kV connection. According to testimony cited in the commission’s order, that option required significant upgrades, and 230 kV service was expected to be faster and more cost-effective for the customer.South Carolina PSC docketSouth Carolina Public Service Commission

EvidenceWhat the public record saysWhat to carry into a site comparison
Approved transmission scope · July 23, 2024The order describes two 230 kV lines on the 16.2-mile Aiken No. 3 to Mt. Zion route. Central’s two lines from Mt. Zion to customer substations total about 1.5 miles.Track the upstream buildout, switching station, feeders and customer work separately. A map of the lead line alone would miss the upstream work.South Carolina Public Service Commission
Construction complete · reported December 9, 2025Santee Cooper later cited its December filing reporting completion of the transmission lines, switching station and Central feeder lines.File the utility’s report against the scope it names. Keep commissioning stages and site works as separate milestones.Santee Cooper
First customer substation energized · December 15, 2025Santee Cooper confirmed the date in an April 2, 2026 filing.Mark the first substation’s energization. The selected filing gives the date and leaves the MW energized at that stage unspecified.Santee Cooper
Second date revised · April 2, 2026 filingSantee Cooper reported that the customer requested a May or June 2026 window for the second substation.Save the revised window as a request. Use a subsequent utility record to establish actual energization.Santee Cooper

There were 510 days between the certificate and the first reported energization. The project record explains the work between those dates. At Aiken, the presence of a 115 kV line would have identified a corridor. The chosen buildout added 230 kV facilities on that corridor, a switching station, and customer feeders. For a new site, ask what could change the ranking of connection options, including outage resilience and any shared routes or equipment.South Carolina Public Service CommissionSouth Carolina Public Service CommissionSantee Cooper

Aiken data center transmission and energization evidence

Download the Aiken milestones and links to the source filings JSON
Cite dataset

Invariant (2026). Aiken data center transmission and energization evidence [Data set]. https://invariant-ai.com/blog/data-center-power-screening-tools#dataset

Review the power study process

How to test tools with the same load and site

Give each provider the same parcel and a load ramp stated in total utility MW. An illustrative request might be 50 MW in 2027, 120 MW in 2028, and 200 MW in 2029. If your requirement starts with IT load, explicitly include the facility loads and operating assumptions that determine what the utility must deliver. Supply the critical-load requirement, operating flexibility, and whether on-site generation can support any phase.

  • Ask for every plausible point of interconnection, including connection voltage, transmission owner, feasible route, and which utility should receive the request. Keep distance and load capacity in their own fields.
  • For each phase, ask for the base case, year, relevant seasonal cases, load scenarios, and contingency assumptions. Request the limiting equipment and modeled headroom in MW. Record the grid data vintage and any missing inputs.
  • Ask which existing and proposed loads, generators, and transmission upgrades are included. Track queue status and identify the upgrades required for each phase, who pays, and which schedule events can change the result.
  • Keep signed service terms, clearing and construction approvals, procurement steps, and energization evidence in a dated file. Assign follow-up to the party that can confirm the next milestone.
ERCOTSouth Carolina Public Service CommissionSantee CooperInvariant

Compare the output at the decision you need to make. For an initial shortlist, a documented reason to investigate or rule out a site may be enough. For an option payment or a tenant delivery commitment, get the utility’s written assessment, the service terms, and a milestone schedule tied to your load. Keep any unresolved assumptions visible to the team making the commitment.

Questions that come up.

What is the best data center site selection tool for power capacity?

Evaluate Paces or Geoforge for a screened shortlist, PVcase for comparing modeled withdrawal at mapped connections, and project-specific study providers for your exact load ramp. Check the inputs, point of interconnection, study year, and output you can verify. The serving utility establishes the applicable service terms.PacesGeoforgePVcaseERCOT

Can a substation’s voltage tell me whether it can serve 200 MW?

Voltage helps identify potential connections. To assess a 200 MW load, ask for a study of the site, the proposed operating case, the limiting facilities, required upgrades, and the utility’s service terms. At Aiken, the original 115 kV option and the selected 230 kV plan had different upgrade requirements.South Carolina Public Service CommissionInvariant

Does an energized customer substation establish the campus’s available MW?

An energization record establishes the milestone for the equipment it names. Match that equipment and date to the MW, service terms, and phases documented by the utility before making a campus-wide delivery claim.Santee Cooper

Sources and references.

Primary sources checked for this guide on .

  1. PacesSite screening and grid workflows for data center developers ↗
  2. GeoforgePower report data and method ↗
  3. GeoforgeExample power report with a connection shortlist and timeline ↗
  4. PVcaseScreen data center sites using withdrawal capacity ↗
  5. PVcaseMethodology and queue assumptions in capacity data ↗
  6. GridCARELarge-load collaboration with National Grid ↗
  7. MireyeInfrastructure fields and site screening bundles ↗
  8. InvariantEarth public field catalog ↗
  9. InvariantPublished power study workflow and limits ↗
  10. ERCOTERCOT Large Load Integration ↗
  11. South Carolina PSC docketCentral application, docket 2024-61-E, proposed demand ↗
  12. South Carolina Public Service CommissionOrder 2024-498, approved transmission scope ↗
  13. South Carolina Public Service CommissionOrder 2024-498, evidence on connection alternatives ↗
  14. Santee CooperApril 2, 2026 Aiken transmission project status report ↗