Start with Invariant when you need to compare parcels and model power delivery on the same set of sites. A development platform can help a team build a pipeline. A site selection advisor can also negotiate the deal. Compare each on the actual land, electrical service points and dates your project needs. In Fairfax County, Virginia, the proposed Plaza 500 data center’s 176 MW request, state order, county substation review and utility construction schedule each came from a different record.
Before you start
- Give every provider the same boundary, facility demand by phase and earliest acceptable service dates. Ask what it can document for each stage.
- MeanderX helps analyze interconnection opportunities and queue activity. Site Selection Group advises data center occupiers and developers and can handle real estate and incentive negotiations.
- At Plaza 500, the August 2025 state order specifies an October 2027 in-service date. Dominion’s project page lists Q2 2028 as its energization target. Keep both dates and ask which terms apply to customer service.
Which providers fit the decision?
Start with the work your team needs this month. A market shortlist needs consistent data across many parcels. A land option needs a site-specific path to utility service. An acquisition or colocation agreement also needs commercial terms and negotiation. The table reflects public descriptions of the offerings. Invariant publishes this guide. The Plaza 500 record review below is independent of the providers’ marketing.
| Provider | What it covers | What to ask to see |
|---|---|---|
| Invariant | Parcel and site screening through Invariant Earth, plus pre-application power studies for specific connection options. The published method covers AC power flow, contingencies, and indicative upgrade costs and schedules. | A cited parcel record and a study showing phase MW, binding constraints and the proposed work at each connection. Ask which assumptions need utility review.Open the Invariant Earth workflowRead the power study method |
| MeanderX | Interconnection intelligence built from utility records. Public examples emphasize renewable development, queue analysis and planned network changes. | A sample for importing load at the site. Ask whether the headroom number represents customer withdrawal or generation export, what year it covers and which upgrades it assumes.Read the MeanderX case study |
| Site Selection Group | Location advisory for greenfield, powered shell and colocation projects. Its services include infrastructure and power assessment, incentive negotiation and real estate transactions. | The dated diligence file supporting the shortlist, with serving utility, each site’s service assumptions and ownership of the remaining negotiations.See advisory services |
| Paces | Development pipeline tools and site diligence covering power, permitting and site constraints. | A report and the evidence behind each stage in the pipeline. Ask how a modeled connection becomes a utility application and how the team tracks subsequent changes.See the developer workflow |
| GridCARE | Grid modeling and utility collaboration for accelerating large customer connections. Its Portland General Electric announcement describes using load flexibility to study capacity. | Whether the serving utility can study that path and how the proposed firm and flexible load portions would be treated under the service terms.Read the utility collaboration |
| LandGate | Parcel and site screening with power, fiber, topography and exclusion layers, plus data center feasibility studies. | A buildable polygon and a named service point for the same candidate. Ask for the year and case behind the offtake estimate, then compare both with your phased service dates.LandGate |
| GE Vernova Consulting Services | Engineering and power economics consulting. Published data center siting work covers generation surplus, curtailment, congestion and site conditions. | A scoped study that connects the regional cost and reliability results to the specific facility’s point of delivery and operating profile.See the power consulting scope |
| GridUnity | Software for managing large-load connection requests, including application intake, study milestones and financial security deadlines. | Start with a phased load request. Ask which utility reviews it, who owns the next milestone, and which study or agreement records the proposed service date.GridUnity |
| Transect | Environmental feasibility reports with buildable area, local permitting context and site-level exclusion mapping. | Use the same candidate tract to reproduce excluded acres and check the permit triggers. Ask which utility records support a separate connection review.Transect |
MeanderX vs. Site Selection Group for data center siting
MeanderX is relevant when your decision depends on tracking queues and changes to the grid across a market. Its published case study describes turning unstructured utility documents into structured records, including plans for new transmission lines and substations. For data center power access, ask to see its load-side coverage for your serving utility and the evidence behind the import capacity estimate. A queue forecast can help prioritize a conversation with the utility.Read the MeanderX case study
Site Selection Group is relevant when you need a real estate advisor to identify locations, compare commercial terms and negotiate a transaction. Its March 2026 Central Virginia land acquisition announcement describes that work for a confidential hyperscale client. The announcement omits the site, requested MW and delivery date. Ask for a representative diligence package with those fields before relying on a shortlist.See advisory servicesRead the acquisition announcement
When you need repeatable data for a pipeline or an application, start with Invariant Earth’s documented site screening workflow. For a parcel you want to advance, scope a separate power study around the planned demand and target in-service dates. Use the same site and evidence requirements when asking an advisor or software vendor for a trial.Open the Invariant Earth workflowRead the power study method
What the Plaza 500 public records establish
Use 6295 Edsall Road, Alexandria, Virginia, and Fairfax County tax parcel 0812 01 0007 as the inputs. The Virginia State Corporation Commission hearing examiner links the customer’s planned campus to Plaza 500. Dominion told the commission that the existing Van Dorn Substation could not supply the initial bridging load as designed and that serving the full amount there would overload transformers by 2029. That assessment pertains to the design and load in the case record.Look up the tax parcelRead the report and load testimony
| Evidence | What the record establishes | What to verify before underwriting |
|---|---|---|
| February 2025 hearing examiner’s report | Dominion reported 176 MW in projected load requested for the planned campus. | The demand by phase and the amount the utility would deliver by each required date.Read the report and load testimony |
| August 2025 state order, PUR-2024-00135 | The SCC granted state authorization as provided in its order. Ordering paragraph 8 specifies October 1, 2027 as the in-service date and October 1, 2028 as the certificate sunset. | Any later order affecting the schedule, and the permits and site work still needed to construct the facilities.Read the final order |
| October 2027 virtual open house timeline and Q2 2028 utility project page | The virtual open house displays October 2027 for project energization. Dominion’s main Edsall project page displays Q2 2028. | Which revision governs the build schedule, whether the order has been amended, and which milestone supports each customer phase.Compare the open house timelineCheck the utility’s project timelineRead the final order |
| Fairfax County application 2232-2025-MA-00007 | As checked November 25, 2026, the county agenda scheduled the substation’s public hearing for December 2, 2026. | The county’s actual action and any conditions. The state order and the local substation review are separate records.Check the county hearing scheduleCheck the utility’s project timeline |
A report that shows one power date for Plaza 500 hides a scheduling discrepancy a buyer would need to resolve. Q2 2028 begins six months after the October 1, 2027 in-service date in the order. The October 1, 2028 sunset concerns the certificate. Ask for current utility documentation tying construction, commissioning and service at the meter to the intended load ramp.Read the final orderCheck the utility’s project timeline
The docket also records a $23.1 million conceptual project estimate in 2024 dollars. Carry the basis and scope with that number. For an investment decision, confirm current estimates, the customer’s cost obligations, security, and which upgrades the charging terms cover.Read the final order
Plaza 500 and Edsall power and permitting records
Download the Plaza 500 and Edsall evidence records CSVCite dataset
Invariant (2026). Plaza 500 and Edsall power and permitting records [Data set]. https://invariant-ai.com/blog/data-center-site-selection-platforms-and-advisors#dataset
How to run a trial on an actual site
Give every vendor the same parcel polygon and project brief. Include facility demand at the meter by phase, earliest and latest acceptable service dates, reliability requirements and the amount of load you can curtail. Note whether the request is for utility import, backup, export or a combination. Give the vendor a different parcel from your real pipeline after it shows a worked example.
- Ask for the exact parcel and evidence date. Have the provider account for usable area, land use, access, water and fiber where they drive your decision. Keep a mapped feature and a provider’s service offer in separate fields.
- Ask for the connection option and year. A credible load study names the limiting equipment, outages tested, competing loads and any upgrades that change the answer. Ask which model came from the utility and which was reconstructed.
- Ask for the contract or dated utility correspondence behind each phase. Track who owns the next decision, who pays for connection work, and whether key dates carry conditions.
- Ask the vendor to replay the Plaza 500 case. A usable answer retains the 176 MW request, the two ordered dates, the different published schedule and the pending local hearing in separate fields. A vendor should leave a field unresolved when its source cannot establish it.
Questions that come up.
What is the difference between MeanderX and Site Selection Group?
MeanderX provides grid and interconnection intelligence, with public examples focused on renewable projects and queue analysis. Site Selection Group provides location advisory, power and infrastructure diligence, and transaction services for data center buyers and developers. For a large new load, ask each for a sample grounded in the serving utility and proposed phase dates.Read the MeanderX case studySee advisory services
How much power did Plaza 500 request from Dominion?
Dominion reported 176 MW of projected requested load in the Virginia SCC proceeding. That is the total request recorded for the proposed campus. Verify any phase-specific service amount in the utility’s current records.Read the report and load testimonyRead the final order
When will the Edsall project energize?
As checked November 25, 2026, Dominion’s main project page listed Q2 2028 for project energization. Its virtual open house showed October 2027. The August 2025 SCC order separately set an October 1, 2027 in-service date and an October 1, 2028 certificate sunset. Confirm the current utility and regulatory schedule before carrying a date into a transaction.Check the utility’s project timelineCompare the open house timelineRead the final order
Sources and references.
Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.
- LandGateSite, solar, data center and battery storage analysis ↗
- Fairfax CountyFairfax County parcel detail for 6295 Edsall Road ↗
- Virginia State Corporation CommissionFebruary 14, 2025 examiner’s report, PUR-2024-00135 ↗
- Virginia State Corporation CommissionAugust 8, 2025 final order, PUR-2024-00135 ↗
- Fairfax CountyMason District land use agenda for Edsall Substation, 2232-2025-MA-00007 ↗
- Dominion EnergyEdsall Substation and Transmission Line Project timeline ↗
- Dominion EnergyEdsall virtual open house timeline ↗
- Google Cloud and MeanderXMeanderX interconnection and site screening case study ↗
- Site Selection GroupSite selection and transaction services for data centers ↗
- Site Selection GroupCentral Virginia land acquisition announcement, March 13, 2026 ↗
- PacesSiting and diligence services for data center developers ↗
- GridCAREAnnounced Portland General Electric collaboration ↗
- GE VernovaSmart data center site selection ↗
- Invariant EarthScreen a site with Invariant Earth ↗
- InvariantInvariant power study workflow and deliverables ↗
- GridUnityGridInterConnect for Large Load ↗
- TransectSite reports, buildable area and permit matrix ↗
Put the requirements to work
Bring the project.
Map the path to approval.
Connect the applicable requirements to the design, the evidence, and the people responsible for each decision.
Talk to an expert