U.S. Data Center Space for Lease

Find U.S. data center space for lease by IT load and delivery date. Compare powered shell and colocation listings and first-year rents from two SEC filings.

Brick industrial building with a modern mechanical annex in morning light.

Illustrated carrier hotel exterior. The locations in the guide are identified by their source records.

To lease a data center, start with the critical IT load you need in a specific hall and the date your equipment has to run. A broker may advertise power for the entire building or an expansion that still needs utility work. A lease should identify the capacity your team can use in its own space and how the landlord will demonstrate delivery.

Before you start

  • Use the listed power and dates to shortlist space. Ask for the uncommitted critical IT capacity in the offered hall and the equipment it includes.
  • Separate building access, utility energization, system acceptance and rent commencement. Record which party owns each milestone.
  • Normalize base rent using the contracted IT kilowatts and the same lease period. Compare electricity, fit-out and other charges separately.

Data center space marketed for lease

We checked these offerings on November 25 and 26, 2026. Ask the broker or owner to confirm current availability, the smallest block a tenant can take and the delivery terms for each phase.

Market and spaceReported powerWhat to ask for first
St. Louis, Missouri. Globe Building carrier hotel.Five 9s Digital and Romans Properties each advertise 7.5 MW. Their expansion targets differ.Have the landlord identify the hall and the uncommitted IT load it can allocate.Broker’s listing directoryGlobe Building listing from Romans
Dayton, Ohio. Equipped data center.Five 9s Digital says the ramp to 5 MW is underway and points to a possible expansion to 15 MW or more.Request the currently commissioned load and the utility and commissioning dates for 5 MW.Broker’s listing directory
Pittsburgh, Pennsylvania. Carrier hotel shell.Five 9s Digital advertises 15 MW with a four-month delivery claim.Confirm when the clock starts, the meter at delivery and the tenant’s fit-out scope.Broker’s listing directory
Orlando, Florida. Existing building marketed as a powered shell.Five 9s Digital targets 20 MW in April 2027.Confirm the street address, utility delivery point and date the tenant can put its equipment into service.Broker’s listing directory
Santa Teresa, New Mexico. Westpark build-to-suit.CBRE advertises 18 MW for the industrial park in Q3 2027.Request the allocation to your building and the construction milestones for that allocation.Westpark build-to-suit listing
Lincolnshire, Illinois. Building D at 4 Overlook Point.The owner lists 6 MW gross. Its current design figures are 4 MW of critical load at Tier I standards or 1.3 MW at Tier II standards.Ask for the critical load at your required redundancy, commissioning evidence and the work needed for 4 MW at Tier II standards.4 Overlook Point owner brochure, page 11

Where can you compare data center lease listings?

Start with the size and delivery terms you need. A listing for a whole building, a reserved block in an operating hall and future expansion can all show the same MW figure. Check the capacity basis and the date of the offer before comparing them.

SourceWhere to startWhat to confirm
InvariantRequest a shortlist for a specific market, critical IT load and handover date. Use the dated public evidence in this guide as a starting point.Share your phase schedule, fit-out needs and rack density so each lead can be checked against the same requirements.
Datacentres.comBrowse properties advertised for lease, including building and suite listings with reported power where provided.Confirm the meter and proposed delivery scope. Building area and electrical service labels can leave usable IT capacity open.Datacentres.com lease listings
Colocation ScoutBrowse operator-reported capacity by market, size and timeframe.Confirm the exact hall, current reservation status and whether the quoted capacity is available by your commissioning date.Colocation Scout capacity listings
DC HubCapacity Source describes a search and introduction service for land, shells, turnkey and colocation. Its public feed returned zero live listings on November 26, 2026.Check the feed for new listings. Use the introduction to verify the offered site, utility terms and current availability.DC Hub Capacity SourceDC Hub public listing feed

How much of a carrier hotel’s power can one tenant lease?

The Globe Building uses 710 N Tucker Boulevard in its leasing materials. The City of St. Louis records 710 as an alternate address for 700 N Tucker Boulevard on parcel 0841-9-010.000. The property owner describes multiple operators in the building. Match the brochure to the property, then ask which specific suite the offer covers.Property owner’s address and operator descriptionAssessor record and alternate addresses

SourcePower figureWhat it describes
Five 9s Digital7.5 MW marketed now, scalable to 20 MW in 12 monthsBroker’s offer and expansion claim.Broker’s listing directory
Romans Properties7.5 MW marketed now, near-term capacity of 30 MWBroker’s starting figure and a different expansion target.Globe Building listing from Romans
Datotel17.5 MW of redundant utility powerThe power Datotel reports serving the building when it published the description.Operator’s Globe Building power description

Ask which portion is already assigned, where the offered hall is metered, and how much IT load it sustains with a component out of service. Keep both broker expansion figures in your file until the landlord and utility identify the scope and timing for your block. Multiple providers quoting the same starting figure still leaves the suite allocation open.

Check the power label within the same brochure

A brochure for 360 S. Lake Destiny Drive calls 1.25 MW in-place critical load on its facility overview. Its utility expansion page calls 1.25 MW in-place utility load and separately describes ramps to 5.5 and 17.5 MW. Ask for a one-line electrical diagram, the meter definition and a recent test result to verify which load the equipment can support. The 20 MW Orlando shell in the listing table has no street address in that directory entry. Verify its identity before combining the two records.Orlando brochure, pages 2 and 5Broker’s listing directory

Globe Building and Lake Destiny Drive data center lease power claims

Download nine dated power claims and their source locations CSV
Cite dataset

Invariant (2026). Globe Building and Lake Destiny Drive data center lease power claims [Data set]. https://invariant-ai.com/blog/data-center-space-for-lease#dataset

Download citation (CSL JSON)

Check the power deadline for your first phase

What should the lease say about delivery and rent?

A powered shell generally leaves electrical and mechanical build-out with the tenant. A fitted wholesale hall or colocation agreement generally puts those systems with the facility provider. Compare the lease’s promised capacity, cooling and rack density, deployment scope, and metering basis. Rent may be tied to reserved kW while electricity is billed on measured use or allocated under a separate schedule.Lease structure and capacity units

MilestoneRecord to requestWhat it establishes
Early accessAccess letter and work scheduleWhen installation or fit-out can begin, and who bears the cost before handover.
Electrical serviceDated utility scope and the lease allocation exhibitWhere power is delivered, which work remains, and what the landlord assigns to the hall.
Ready for serviceCommissioning plan and signed acceptance packageWhich integrated tests the hall must pass at the contracted load, including electrical and cooling operation.
Rent commencementLease dates, notice requirements and delay clausesWhen charges start and what the remedies are for a late phase.

SB Energy’s SEC filing describes a Cosmos lease under which a phase’s rent date is structured around a specified calendar date and Ready for Service, with exceptions for certain delays. Ready for Service includes completion, acceptance conditions and commissioning. A separate Blackstone filing contains a form lease with target and deadline dates by phase and placeholders for rent credits. The documents illustrate why you should read the actual commencement and acceptance clauses together.SEC filing, Cosmos leaseSEC filing, form lease

How do you compare data center rent per kW per month?

Divide first-year base rent by 12 months and by the contracted critical IT load in kilowatts. Use the power reserved for the tenant’s equipment as the denominator. The facility’s gross MW can also serve cooling and other systems. For a phased lease, use the rent and capacity for the same phase and period.Lease structure and capacity units

Disclosed leaseFirst-year base rent basisContracted critical IT loadImplied base rent per IT kW per month
Host Digital Site I, northeast OklahomaAbout $67 million in year one43 MW$130Host Digital lease filingHost Digital rent and expense disclosure
TeraWulf La Lupa and Core42, Lake Mariner, New York$90 million across the first 12 months of each lease60 MW$125TeraWulf lease filing

Host’s 15-year Site I lease covers 43 MW of critical IT capacity at a site reported at 55 MW gross. Dividing about $67 million by 43,000 and by 12 gives about $130 per IT kW per month. The November filing projects handover in Q1 2027. Host reports a 3% annual rent increase and operating expenses, including electricity, payable by the tenant in addition to rent.Host Digital lease filing

TeraWulf says the $90 million prepayment represents the first 12 months of base rent across the Core42 leases. The prepayment offsets half of each month’s base rent until the credit runs out. That changes cash payment timing. The implied base rent is $125 per contracted IT kW per month across the leases, using each lease’s own first 12 months. TeraWulf reported the full 60 MW in service as of September 30, 2026.TeraWulf lease filing

For portfolio context, Digital Realty reported $284 per kW per month for new 0–1 MW leases in the Americas and $264 for new leases above 1 MW in the third quarter of 2026. Both are GAAP base rent figures at Digital Realty’s share. Compare them as measures of that quarter’s signed portfolio. Keep them separate from the first-year contractual rent for a specific hall.Digital Realty Q3 2026 lease signings

Use these signed leases to check the comparison method. For a current offer, ask for monthly base rent by hall and phase, billable IT kW, electricity charges, other operating expenses, escalators and credits. Confirm who pays for the work to bring each phase into service. Compare total cost over the same delivery and operating period.Lease structure and capacity units

First-year base rent per critical IT kW in two U.S. data center leases

Download both lease calculations and SEC filing references JSON
Cite dataset

Invariant (2026). First-year base rent per critical IT kW in two U.S. data center leases [Data set]. https://invariant-ai.com/blog/data-center-space-for-lease#dataset-wholesale-lease-rent-per-it-kw

Archived release v1.0.0 · 2026-11-26

Download citation (CSL JSON)

What to send when you request a lease shortlist

Send the markets you can use, your IT MW at first delivery, later ramp dates, rack density and cooling requirements, and whether your team can fit out a shell. Include network routes or carriers that affect where you can deploy. Ask each provider for the same information for each hall so you can compare offers on the load, date and scope you actually need.

Questions that come up.

How is data center lease rent per kW per month calculated?

Divide base rent for a particular hall or phase by the number of months and the contracted critical IT capacity in kilowatts. Start with the same period and scope for each offer, then compare electricity, tenant-paid work and other charges separately.Lease structure and capacity units

How do I find U.S. data center space for lease with available power?

Screen by market, critical IT load and the date your equipment needs to run. Ask the broker for the exact hall, uncommitted capacity at handover, and evidence of current availability. Verify expansion separately using the utility scope and the landlord’s commissioning plan.

What is a powered shell data center lease?

A powered shell lease usually covers the building and a defined path to power. The tenant handles some or all of the interior electrical and mechanical fit-out. The work letter defines the exact delivery boundary.Lease structure and capacity units

Is a 20 MW building the same as a 20 MW data hall?

A building-wide figure can include tenant loads, shared equipment and cooling. Ask for the critical IT capacity dedicated to the specific hall and valid under the agreed redundancy conditions.

What starts the rent on a data center lease?

The signed lease controls. It can tie payments to a calendar date, delivery, acceptance, or a combination, with separate dates for later phases. Review early access, Ready for Service conditions, notice and delays before comparing offers.SEC filing, Cosmos leaseSEC filing, form lease

Sources and references.

Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. Woodcrest Capital4 Overlook Point marketing brochure, Building D current configuration and upgrades, page 11 ↗
  2. Host Digital / SECHost Digital Form 10-Q, Site I lease, November 16, 2026 ↗
  3. Host Digital / SECHost Digital shareholder letter, first-year base rent and tenant expenses, September 29, 2026 ↗
  4. TeraWulf / SECTeraWulf Form 10-Q, Core42 lease prepayments and La Lupa capacity, November 6, 2026 ↗
  5. Digital Realty / SECExhibit 99.1, third-quarter 2026 new leasing by region and product size ↗
  6. Datacentres.comData centre properties marketed for lease and reported capacity ↗
  7. Colocation ScoutOperator-reported colocation availability by capacity, market and timeframe ↗
  8. DC HubCapacity Source listings and the introduction process ↗
  9. DC HubCapacity Source public listing feed ↗
  10. Five 9s DigitalAvailable data centers and powered land ↗
  11. Romans PropertiesFeatured lease properties, including the Globe Building ↗
  12. DatotelGlobe Building utility power and expansion ↗
  13. The Globe BuildingThe Globe Building address and operators ↗
  14. City of St. LouisAssessor and permit record for 700 N Tucker Blvd ↗
  15. Five 9s Digital and Romans Properties360 S. Lake Destiny Drive, facility overview and utility power stages ↗
  16. CBREWestpark Logistics Center, build-to-suit lease listing ↗
  17. CRE Finance CouncilData Center Primer, second edition, part 1 ↗
  18. SB EnergyForm S-1/A, Cosmos Technology Campus lease and Ready for Service terms ↗
  19. Blackstone Digital Infrastructure TrustExhibit 10.4, form of data center lease, sections 3.2 and 3.3 ↗

Request a data center site shortlist

Tell us the load you need at the meter, where you’re looking and when you need service. We’ll walk through the sites that match your requirements and the evidence behind their reported power.