How to Verify Rail Spur Service at an Industrial Site

Check whether an industrial rail spur can serve your facility. Compare recorded crossing rights, track inspection, carrier terms and the first delivered railcars.

A crossing reopened in Greensburg in December 2022. Union Pacific reported a completed track inspection in Pleasant Prairie on June 17, 2026. Seven railcars reached Sofidel in Inola on April 10, 2024.

Dates from the Indiana Department of Transportation, Union Pacific’s inspection record filed by Pleasant Prairie, and Tulsa Ports.

To verify rail spur service, give the serving railroad the facility address, the track ID and the legal name of the shipper or consignee. Ask the railroad to confirm in writing which track it can serve, which agreement covers your company and what must happen before the first delivery. Then match the route to the survey and recorded access rights. A recent switching record or shipment to the same track establishes past use. Current terms establish what your operation can schedule.

Before you start

  • Trace the route from the carrier’s line to the exact spot where the car will be unloaded.
  • Match ownership, operating rights and track maintenance to the correct agreement and segment.
  • Record crossing reopening, inspection, contract completion and accepted shipments as separate events.

What records prove a spur can serve your facility?

A spur is a track that branches from a railroad line to reach a facility. Tell the carrier what you want to ship, the type and loaded weight of each car, and the number of cars per switch. A switch is the carrier’s move that places or picks up cars at the facility. The carrier can then confirm the track, who performs that move and what capacity it will accept.Iowa DOT rail toolkit

CheckRecord to requestDecision it supports
Route and accessSurvey, track diagram, deeds and easements from the carrier’s line to the unloading spot.Identify each parcel and crossing the cars must pass through. Resolve any segment the seller cannot show the right to use.INDOT crossing historyIowa DOT rail toolkit
Shipper and serving carrierCurrent track agreement or other written authorization covering your operating entity, plus carrier confirmation of the track and spot.Establish who may receive cars and who is responsible for upkeep, access and repairs.Track Agreement Policy
Readiness at the unloading spotLatest track inspection, outstanding work, carrier acceptance of the car type and weight, and the switching schedule.Confirm what the carrier can handle once the operation begins.Iowa DOT rail toolkitUnion Pacific inspection
Recent operationsA dated switching record or a shipment record for the exact spot, with sensitive terms redacted as needed.Confirm prior use. Obtain your own service terms before promising a first shipment.Tulsa Ports shipment recordTrack Agreement Policy

Union Pacific’s policy covers new shipments to and from industrial tracks, including existing facilities used by other customers. It asks for an active agreement covering the shipper, consignee or other named party, or coverage under another customer’s agreement. Ask the serving carrier which rules apply to your facility and shipment.Track Agreement Policy

Greensburg shows why the deed must cover the crossing

During a 2019 review of State Road 3 near Greensburg, Indiana DOT found that both sides of a roughly 1¾-mile spur had been deeded to Central Railroad of Indiana. The deed omitted the road crossing. Indiana DOT reported that Conrail retained the crossing right-of-way and that the reinstalled crossing reopened in December 2022.INDOT crossing history

The federal crossing inventory lists SR-3/SR-46 as record 916452T. Its July 21, 2025 revision lists the crossing as open. The state note links the reopening to reconstruction of the crossing surface. Ask for the recorded rights that cover the crossing and the carrier’s authority to serve the shipper at its unloading spot. The inventory documents the crossing and its reported status.FRA crossing recordINDOT crossing history

Pleasant Prairie separates inspection from project completion

The Village of Pleasant Prairie’s June 2025 update described about 1,994 feet of proposed track for Balcan USA. It named That’s a Wrap (WI) LLC as landowner and Balcan as tenant, with the village managing procurement and holding the rail infrastructure under the grant terms until the conditions could be met. These are the roles and terms the village described when the project was advancing.Village project update

On June 17, 2026, Union Pacific reported that the industry tracks were complete and inspected. The grant completion certificate lists June 30 as the date the contract work finished. It carries the project engineer’s July 3 signature and the WisDOT project coordinator’s July 21 signature. The October 26 village minutes record approval of a letter-of-credit reduction. Each date relates to a different decision. To date the first shipment, ask for a carrier or shipper record that identifies the cars delivered to Balcan’s spot.Union Pacific inspectionWisDOT completion certificateVillage Board minutes

Inola records the first delivery to a named shipper

Tulsa Ports reports that construction of the Verdigris Southern project finished on March 29, 2024, and that the first delivery brought seven railcars of raw materials to Sofidel on April 10. The Railroad Retirement Board dates the start of Verdigris Southern operations to April 9. Watco identifies Union Pacific as the interchange carrier at Inola.Tulsa Ports shipment recordFederal operating recordWatco interchange profile

The port describes a 4.4-mile construction project. The federal decision identifies a leased operating segment of approximately 13,883 feet, from the Union Pacific connection to an endpoint west of the S 4200 crossing. Use the endpoints in the applicable agreement when checking the track that serves your property. To qualify a different building at the port, confirm its track and shipper with the operator.Tulsa Ports shipment recordFederal operating record

Industrial rail spur reopening, inspection and delivery milestones

Download the dated rail spur service milestones CSV
Cite dataset

Invariant (2026). Industrial rail spur reopening, inspection and delivery milestones [Data set]. https://invariant-ai.com/blog/verify-industrial-rail-spur-service#dataset

Archived release v1.0.1 · 2026-11-26

Download citation (CSL JSON)

Verify truck and rail access for a logistics site

Questions that come up.

How can I tell if an industrial property is rail-served?

Ask the serving carrier to identify the exact track and unloading spot, confirm your company is covered, and state what it can deliver and on which days. Verify that the route and rights cover the whole connection to the facility.Track Agreement PolicyIowa DOT rail toolkitINDOT crossing history

What does an open grade crossing establish?

An open crossing record identifies where a road and railroad intersect and gives the status reported to the inventory. Check the track rights and carrier’s authorization for your shipper separately.FRA crossing recordINDOT crossing historyTrack Agreement Policy

Can a new tenant use the previous occupant’s rail agreement?

Ask the carrier who is covered. Union Pacific applies its track agreement policy when a new customer begins shipping at an existing facility. It can recognize a customer covered as a user under another valid track agreement.Track Agreement Policy

Sources and references.

Primary sources checked for this guide on .

  1. InvariantScreen warehouse rail and truck access ↗
  2. Union PacificTrack Agreement Policy, industrial tracks and covered users ↗
  3. Iowa Department of TransportationDeveloping a rail-served facility ↗
  4. Indiana Department of TransportationReinstallation of the State Road 3 crossing in Greensburg ↗
  5. Federal Railroad AdministrationCrossing inventory Form 71, record 916452T ↗
  6. Village of Pleasant PrairieJune 9, 2025 Balcan rail spur project update ↗
  7. Union Pacific, filed with the Village of Pleasant PrairieJune 17, 2026 industrial-track inspection email, published with item 7.B ↗
  8. Wisconsin Department of Transportation, filed with the Village of Pleasant PrairieTEA project 3830-03-50 completion certificate, filed with item 7.B ↗
  9. Village of Pleasant PrairieOctober 26, 2026 Village Board minutes, items 7.A and 7.B ↗
  10. Tulsa Ports and Oklahoma Department of CommerceVerdigris Southern construction completion and first shipment ↗
  11. U.S. Railroad Retirement BoardVerdigris Southern employer status determination BCD 2024-29 ↗
  12. WatcoVerdigris Southern Railroad service profile and interchange ↗