Build, lease or colocate: how neoclouds and AI labs get to power fastest

Build vs lease vs colocate for neoclouds and AI labs: time to power, capital, control and risk at 5, 50 and 500 MW, and when to move from one to the next.

For a neocloud or AI lab, colocation gets you running fastest with the least capital, leasing a whole building or site gives you control at medium scale, and building on powered land gives the lowest long-run cost per MW but the longest wait and the most risk. The deciding variable is the date power is available, which is why the right choice changes with size: colocation below about 5 MW, a lease from about 5 to 50 MW, and building above that.

Before you start

  • Time to power usually beats price per kW. Idle GPUs cost far more than rent.
  • Building means owning the utility relationship, the large-load tariff and its minimum bill.
  • Leasing moves the power risk to the landlord, but only if the lease says so.
  • Many neoclouds do all three at once: colo for today, a lease for next year, land for 2028.

The trade-offs

ColocateLease a building or siteBuild on powered land
Typical sizeUp to about 10 MWAbout 5 to 100 MW50 MW to 1 GW+
Time to powerWeeks to monthsMonthsUsually 18 months or more
CapitalLowestFit-out and equipmentHighest
Control over designLowMediumFull
Who holds the power riskProviderLandlord, if the lease says soYou
Utility commitmentsNone directlyOften passed throughMinimum bill, term, security
Lawrence Berkeley National Laboratory and The Brattle Group

When building makes sense

Owning the power pays off once the cluster is big and long-lived enough to absorb a long utility term. New large-load tariffs set minimum bills near 80 to 85% of contract demand for 12 years or more, so you need the demand to fill it.Lawrence Berkeley National Laboratory and The Brattle GroupAEP Ohio

Building also means a utility study cycle. In Texas, large loads now go through ERCOT’s batch process; elsewhere, a load study can take months before construction starts.Willkie Farr & Gallagher

On-site generation as a shortcut

Some neoclouds bridge to grid power with on-site gas. It can work, but it has its own clock: turbines, air permits and gas supply. Cleanview counted only about 2 GW running out of some 90 GW of identified behind-the-meter projects.CleanviewUS EPA

More for neoclouds and AI labs

Questions that come up.

Should a neocloud build its own data center?

Usually only once it needs tens of MW or more for many years. Below that, colocation or leasing gets to power faster with less capital and less utility risk.

Is it faster to lease or build data center capacity?

Leasing an energized building or site is usually months; building on powered land is usually 18 months or more, set by the utility date and long-lead equipment.

What does it cost to commit to utility power for a data center?

Beyond construction, large-load tariffs set minimum bills near 80 to 85% of contract demand for 12 years or more.Lawrence Berkeley National Laboratory and The Brattle GroupAEP Ohio

Can Invariant help us decide?

Yes. Send the cluster plan and dates and we lay out the options we can source in each route.

Sources and references.

Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. CleanviewBehind-the-meter data centers: full report ↗
  2. Lawrence Berkeley National Laboratory and The Brattle GroupElectricity rate designs for large loads (August 2026) ↗
  3. Willkie Farr & GallagherERCOT approves new Batch Zero process for large load interconnections ↗
  4. AEP OhioData center tariff ↗
  5. US EPAWho has to obtain a Title V permit ↗