10 MW data center site: how to find powered land for a 10 MW AI or colocation build

Find a 10 MW data center site in the US: the utility service a 10 MW load needs, land and rack math, timelines for new service, and 10 MW sites available now.

10 MW is the most common first ask we hear from AI inference companies and neoclouds, and it sits on an awkward line. It is too big for most existing commercial services and too small for most utilities to prioritize like a hyperscale load. The sites that work at 10 MW are ones where the substation capacity already exists: built Tier III rooms, energized mining sites, hydro and plant-adjacent sites, and industrial brownfields. Invariant lists several now and finds others off-market.

Before you start

  • 10 MW at the meter is about 7.7 MW of IT at a PUE of 1.3, roughly 64 AI racks at 120 kW, about 4,600 GPUs.
  • Expect either two or more dedicated distribution feeders or a small customer substation on a 69 to 138 kV line.
  • The fastest 10 MW is a built facility or an energized site. New service often takes 12 to 24 months and longer where a substation is needed.
  • Land: 3 to 15 acres for most builds.

What 10 MW actually fits

Utilities sell facility load. Tenants buy IT load. At a PUE of 1.3, a 10 MW site leaves about 7.7 MW for IT. At about 120 kW per NVIDIA GB200 NVL72 rack, that is roughly 64 racks, or about 4,620 GPUs. Air-cooled designs at 30 to 50 kW per rack fit more racks and fewer GPUs per MW. Typical buyers at this size are a GPU inference cluster, a regional colocation facility, a neocloud pod or a mining operation.eeNews EuropeUptime Institute

10 MW siteWhat to expect
IT load at PUE 1.3About 7.7 MW
AI racks at 120 kWAbout 64
Utility serviceDedicated 12.47 to 34.5 kV feeders, or a customer substation on a 69 to 138 kV line.
LandAbout 3 to 15 acres, depending on stories, cooling type and generator yards.
Time to powerNow for built or energized sites. 12 to 24 months is common for new service where the substation has room, more where it does not.
Documents to ask forA will-serve letter naming MW and a point of service at minimum; a load study or service agreement for anything you plan to finance.

These ranges are Invariant’s working figures from sites we have screened. They are not published standards, and individual utilities and designs land outside them.

What a 10 MW buyer should screen for

Start with the substation. Ask the utility, or ask us, whether the station that would serve the site has 10 MW of withdrawal headroom today and under contingency. In a 2025 analysis of ERCOT, Paces found only about 17% of substations near suitable land had positive withdrawal headroom. Proximity alone means little.Paces

Then check redundancy. Many 10 MW sites have one feeder. That is fine for mining and risky for a customer contract with a service level. A second feeder from a different substation bus can cost more than the land.

Built facilities versus greenfield at 10 MW

Buying or leasing a built 10 MW facility skips the utility queue and most permitting. You pay for it in price per MW and in being stuck with the cooling design. Greenfield at 10 MW rarely pencils unless the power is already there. That is why most 10 MW deals we close start from an energized site or an existing building.

10 MW data center sites available now

These sites from Invariant’s current inventory fit a 10 MW requirement, either at that size today or with a phase that covers it. Specs are as marketed by the owner and are checked against utility documents before any introduction.

RegionPowerLandTiming
Oregon10 MW hydro, to 100 MW+Lease + land optionNow
US (3 facilities)Tier III data centers, 3.5 to 10 MWBuiltNow
KentuckySeven turnkey sites, 0.5 to 8 MWMostly ownedNow
North Dakota15 MW off-grid, managed containersVariousNow
Texas (Houston load zone)17 MW greenfield~2 acres4 to 6 months
US20 earlier listings, 0.25 to 30 MWVariousStatus on a call

Exact locations, the utility documents behind each MW figure and pricing are shared on a call. We also hold sites that are not listed publicly; owners ask for discretion and a site that is shopped everywhere loses value.

Browse data center sites by size and state

Questions that come up.

How much land does a 10 MW data center need?

Roughly 3 to 15 gross acres. Multi-story builds and liquid-cooled AI halls sit at the low end; single-story campuses with generator yards and buffers sit at the high end. A containerized mining site of 10 MW can fit on 2 to 5 acres.

How long does it take to get 10 MW of power for a data center?

If the site is energized or a built facility, immediately. For new service with substation headroom, 12 to 24 months is common. If the substation needs a new transformer or the line needs upgrades, expect longer.

How many GPUs can a 10 MW data center run?

About 4,600 Blackwell-class GPUs in GB200 NVL72 racks at a PUE of 1.3, or roughly 64 racks at 120 kW. Lower-density air-cooled designs fit fewer GPUs per MW.

How does Invariant help find a 10 MW data center site?

Invariant keeps a live inventory of US powered sites, screens each one against utility documents, and matches buyers to sites by MW, state and energization date. Book a call or call (628) 220-8972 with your 10 MW requirement and we send matching sites, including off-market ones.

Sources and references.

Site specifications are as marketed by the seller and are checked against utility documents before any introduction. Public sources checked on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. eeNews EuropeNvidia offers 120 kW liquid-cooled Blackwell rack as industry standard ↗
  2. PacesGrid planning for data centers and transmission investment ↗
  3. Uptime InstituteLarge data centers are mostly more efficient, analysis confirms ↗