Big Watt Digital and PowerHouse Data Centers announced up to 1 GW of capacity at Taylor Technology Campus, with first power targeted for the first half of 2028. Taylor City Council approved a development agreement on October 8, 2026. The agreement sets separate deadlines for the land and annexation process and for reclaimed-water infrastructure. A site team needs all three schedules before it can set a date for the first operating phase.
Before you start
- Track the first MW at the facility meter separately from the developer’s full campus capacity and first-power target.
- Request the complete preliminary plat application, the later annexation records, and evidence of land closing.
- The 1 million gallons per day plant design basis, the 150,000-gallon average daily campus service term, and the initial fill cap are three different figures.
What is the first-power target for Taylor Technology Campus?
The October 9 developer announcement describes dedicated behind-the-meter generation, meaning generation designed to serve the campus on site. It gives the first half of 2028 as a target for first power and up to 1 GW as the scale of the campus. The announcement leaves the first block’s net MW and the relationship between facility and critical IT load unspecified.Developer capacity and first-power target
For a leasing or acquisition decision, request the net electrical output at the facility meter by date. Ask what air authorization covers the equipment, when firm fuel can be delivered, and when the electrical plant can complete acceptance tests. Where a phase relies on grid import or export, get the separate agreement and operating limits for that connection.Developer capacity and first-power targetTaylor project records and council vote
What did Taylor approve and what deadlines follow?
The city lists Project Mustang as the former name. The earlier Employment Center Plan and annexation applications were withdrawn in September. The October vote approved a development agreement. The agreement calls for a plat application, a later voluntary annexation petition, and an annexation proceeding. Use the date of each action when checking the project’s legal status.Taylor project records and council voteWithdrawn Project Mustang noticePreliminary plat and annexation terms
| Land milestone | Published date or trigger | Record to request |
|---|---|---|
| Development agreement vote | October 8, 2026. Taylor reports a 5–0 vote for the agreement. | The agreement, amendments and records of any subsequent council action.Taylor project records and council vote |
| Complete preliminary plat application | Due April 8, 2027 under § 10.1. | The accepted application and the city’s plat decision.Preliminary plat and annexation terms |
| Voluntary annexation petition | Due within seven days of approval or conditional approval of the preliminary plat under § 10.2. | The filed petition and, once adopted, the annexation ordinance and effective date.Preliminary plat and annexation terms |
| Land closing milestone | Section 9.3(e) allows termination if the developer has yet to close by October 8, 2027. | Evidence of closing, or a written agreement covering any change to the deadline.Land closing and termination terms |
How much reclaimed water is allocated to the campus?
The Mustang Creek improvements use a 1 million gallons per day treatment design basis. For the campus itself, § 6.3(d) provides up to 150,000 gallons per day of reclaimed water on an average daily basis, plus a one-time HVAC fill of up to 1.575 million gallons across the buildings. Those service terms apply after completion and city acceptance of the required improvements.Treatment system and authorizationCampus water service terms
Section 6.1 requires state reclaimed-water authorization and a subsequent reclaimed-water contract. The stated construction deadline uses the later of two milestones. One is 24 months after the city receives a qualifying construction notice. The other is completion of the developer’s off-site reclaimed-water work. The agreement specifies conditions and possible extensions. For a readiness review, ask for the authorization, contract, notice, off-site completion and acceptance dates, and the fill schedule by building.Treatment system and authorizationReclaimed-water construction scheduleCampus water service terms
Taylor Technology Campus power, reclaimed water and approval milestones
Download 13 records with agreement sections and source hashes JSONCite dataset
Invariant (2026). Taylor Technology Campus power, reclaimed water and approval milestones [Data set]. https://invariant-ai.com/blog/taylor-technology-campus-power-water-approvals#dataset
Archived release v1.0.0 · 2026-11-26
What is the status of wastewater application WQ0016554001?
Section 6.4 names TCEQ application WQ0016554001 and calls for the developer to withdraw the application within five business days after issuance of the first site development permit, subject to the disannexation provision. The TCEQ list reviewed on November 26, 2026 still showed the application for the 487 Acre Taylor Tract Wastewater Treatment Plant. Check for the first site permit and an agency record of the withdrawal before closing that item.Wastewater permit withdrawal provisionTCEQ pending application list
The state notice describes a proposed discharge of up to 150,000 gallons per day on a daily-average basis. The city agreement’s 150,000-gallon average daily reclaimed-water figure describes incoming service to the campus. Track the proposed discharge and the water supply separately even though the two published figures match.TCEQ wastewater application noticeCampus water service terms
Questions that come up.
Is the Taylor Technology Campus first-power date confirmed?
The developers targeted the first half of 2028 in their October 9 announcement. Request the net MW, fuel and permit records and a dated commissioning schedule before using that target as an opening commitment.Developer capacity and first-power target
When is the Taylor Technology Campus annexation petition due?
The development agreement sets April 8, 2027 as the deadline for a complete preliminary plat application. The annexation petition is due within seven days after the city approves or conditionally approves the preliminary plat.Preliminary plat and annexation terms
How much reclaimed water is written into the Taylor agreement?
After the improvements are accepted, the campus term is up to 150,000 gallons per day on an average daily basis, plus up to 1.575 million gallons in one-time HVAC fill across the buildings. The treatment improvements use a separate 1 million gallons per day design basis.Campus water service termsTreatment system and authorization
Sources and references.
Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.
- City of TaylorTaylor Technology Campus project timeline and October 8, 2026 approval ↗
- City of TaylorWithdrawn Employment Center Plan notice, PZ 2026-2715 ↗
- Big Watt DigitalOctober 9, 2026 joint venture announcement with PowerHouse Data Centers ↗
- City of TaylorDevelopment agreement § 9.3(e)–(g), termination provisions, page 33 ↗
- City of TaylorDevelopment agreement §§ 10.1–10.3, preliminary plat and voluntary annexation, pages 35–36 ↗
- City of TaylorDevelopment agreement § 6.1(d), construction deadline and commencement conditions, pages 21–22 ↗
- City of TaylorDevelopment agreement § 6.3(d), post-acceptance utility service terms, page 29 ↗
- City of TaylorDevelopment agreement § 6.4, permit application WQ0016554001, pages 29–30 ↗
- Texas Commission on Environmental QualityPending TPDES applications, 487 Acre Taylor Tract Wastewater Treatment Plant ↗
- Texas Commission on Environmental QualityNotice of application and preliminary decision for WQ0016554001 ↗
Put the requirements to work
Bring the project.
Map the path to approval.
Connect the applicable requirements to the design, the evidence, and the people responsible for each decision.
Talk to an expert