Before assigning a first-power date to an Ohio data center that plans to generate its own power, verify the state siting certificate for the plant, the Ohio EPA air permit for the emissions units, and the local approvals for the data center buildings. On November 19, 2026, the Ohio Power Siting Board approved the 1,350 MW Fairfield and 800 MW Ashville generating facilities with conditions. The Fairfield air record reviewed here is an October 8 draft. In Ashville, the county’s unofficial tally shows voters rejected the village resolution backing the data center’s term summary.
Before you start
- Ohio’s 50 MW threshold applies to the state definition of a major generating facility. Air review looks at the equipment, emissions and location.
- At Fairfield, the October air draft and the November siting approval carry different IDs. Check each agency for its final record and conditions.
- At Ashville, the 800 MW plant certificate and the vote on a local development resolution cover different decisions.
- Fairfield and Ashville accounted for 2,150 MW out of 3,958.9 MW in the Board’s approved behind-the-meter category in the November snapshot. The Board separately listed 561.8 MW as operational.
What triggers Ohio siting and air review?
Ohio Revised Code 4906.01 includes generating plants designed for or capable of 50 MW or more in its definition of a major utility facility. Section 4906.04 requires a certificate before commencing construction of a covered facility. Start with the plant rating, associated facilities and proposed construction scope. Check the Board’s certificate and conditions for the precise work you plan to release.State of OhioState of Ohio
Ask Ohio EPA to review the planned fuel, hours, equipment and emissions controls. The air review is based on the source and its potential emissions. Confirm which state air permit and federal equipment standards apply, and whether a separate operating permit is required. Submit prime or bridge power as intended operation when that is how the units will run.State of OhioU.S. Environmental Protection Agency
| Decision | Record to get | What to match |
|---|---|---|
| Plant siting | Ohio Power Siting Board certificate and adopted conditions | Case number, applicant, approved configuration and conditions tied to construction.State of OhioState of Ohio |
| Air authorization | Ohio EPA final issued air permit and its unit schedule | Facility and permit IDs, covered units, use, conditions and effective date.State of OhioOhio EPA |
| Campus approvals | Current zoning, building permits and local decisions | Exact parcels, approved buildings and any later actions affecting the approval.Supreme Court of OhioOhio Power Siting Board |
What did Ohio approve at Fairfield and Ashville?
The Board’s November 19 announcement describes both plants as behind the meter, serving adjacent data centers without connecting to the electric grid. The announcement expressly limits the Board’s authority to the generation facilities. Read the applicable case for conditions and later proceedings before relying on the decision.Ohio Power Siting Board
| Project | November 19 siting decision | Separate record to track |
|---|---|---|
| Fairfield Energy Center, Millersport | 1,350 MW of generation and 1,040 MW of battery power. Case 26-0160-EL-BGN. The Board adopted 36 conditions. | Ohio EPA’s October 8 draft air permit P0140492 covers the proposed emissions units. The public comment period ran through November 12. Obtain the final issued version to establish its effective terms.Ohio Power Siting BoardOhio EPAOhio EPAFairfield Energy Center, LLC |
| Ashville Energy Center, Pickaway County | 800 MW of generation. Case 26-0196-EL-BGN. The Board adopted 41 conditions. | The November 3 vote concerned village Resolution 06-2026 and its development term summary. Establish which local approvals and agreements currently apply to the data center buildings.Ohio Power Siting BoardSupreme Court of OhioPickaway County Board of Elections |
The Board’s status table lists 3,958.9 MW of approved behind-the-meter generation in a category separate from the 561.8 MW reported as operational. The two November 19 approvals add up to 2,150 MW, about 54% of that approved category. The table covers gas generation and combined heat and power projects of 50 MW or more. Check the operating status at each specific plant before counting it as usable supply.Ohio Power Siting Board
Ohio siting, air permit and local approval records for Fairfield and Ashville
Download the dated Ohio power plant approval records CSVCite dataset
Invariant (2026). Ohio siting, air permit and local approval records for Fairfield and Ashville [Data set]. https://invariant-ai.com/blog/ohio-data-center-power-plant-air-permits#dataset
How to read Fairfield’s draft air permit P0140492
Use Ohio EPA facility ID 0123000448 and permit number P0140492 to find the air file. The October 8 draft cover letter says the document is for comment and leaves the effective date open for final issuance. The November 10 public meeting was part of Ohio EPA’s process. The project’s public notice records the meeting date. Ohio EPA’s comment docket now shows the period as closed. Final issuance remains unverified in the records reviewed for this guide.Ohio EPAOhio EPAFairfield Energy Center, LLCOhio EPA
The draft staff determination lists proposed annual potential emissions of 486 tons of nitrogen oxides and 686 tons of carbon monoxide. Its table also shows why a pollutant can require review below the project’s major-source threshold. Volatile organic compounds are listed at 221 tons per year, below 250 but above the 40 tons per year significance level the draft applies to that pollutant. These figures are the agency’s draft review inputs. Use the final table for enforceable requirements and operating reports for measured emissions.Ohio EPAState of Ohio
The draft describes 40 simple-cycle turbines. Adding the displayed unit ratings gives 1,338 MW. The siting application describes up to 1,350 MW of net generation, and the Board lists 1,040 MW of battery power separately. Keep the figures with their documents. Ask for the reconciled equipment schedule, the battery’s usable energy in MWh, and the plant’s guaranteed delivery at the data center intake before using any of the values for a tenant opening.Ohio EPAFairfield Energy Center, LLCOhio Power Siting Board
What did Ashville voters decide?
Ohio’s Supreme Court ordered Ashville’s fiscal officer to certify the referendum petition on Resolution 06-2026. The opinion describes a village-approved term summary for an agreement the parties planned to negotiate. Among its provisions was treatment of the project under the village’s data center moratorium. The county’s public tally lists 1,504 no votes and 339 yes votes, labeled unofficial in the version reviewed.Supreme Court of OhioPickaway County Board of Elections
The subsequent state power plant decision stayed within its own scope. For a land decision, check the village’s current records for the parcel and building phase, the adopted local rules, executed agreements and any subsequent decisions. Record the date and authority for each answer before issuing a schedule to a tenant.Ohio Power Siting BoardSupreme Court of Ohio
What to check before committing to first power
Put the case numbers and permits on one schedule. Assign an owner and due date to each condition that gates construction, startup or normal operations. Recheck the signed records when equipment counts, fuel, source boundaries or run hours change. Tie the gas delivery commitment, controls testing, net output guarantee and acceptance test to the same phase and requested service date.State of OhioState of OhioU.S. Environmental Protection Agency
Questions that come up.
Does a 50 MW Ohio power plant need the same permit as a data center?
Ohio uses 50 MW in the state definition of a major generating facility, for which the siting certificate governs construction. Air permits are handled separately by the air agency. Check the local approvals for the data center buildings with the local authority.State of OhioState of OhioState of OhioOhio Power Siting Board
Was Ohio EPA permit P0140492 final when the Board approved Fairfield?
The Ohio EPA version reviewed was the October 8 draft, with a comment period that ran through November 12. The November 19 Board action was the plant’s siting decision. Check Ohio EPA’s current records by facility ID 0123000448 and permit P0140492 for any later final action.Ohio EPAOhio EPAFairfield Energy Center, LLCOhio Power Siting BoardOhio EPA
Did Ohio approve the EdgeConneX Ashville data center with the 800 MW plant?
The November 19 state decision covers the 800 MW Ashville Energy Center. Ohio’s board said its authority extends to the power plant. The effect of the local resolution vote and the status of the data center buildings need separate local records.Ohio Power Siting BoardSupreme Court of OhioPickaway County Board of Elections
Sources and references.
Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.
- State of OhioOhio Revised Code 4906.01, major utility facility definition ↗
- State of OhioOhio Revised Code 4906.04, construction certificate ↗
- State of OhioOhio Administrative Code Chapter 3745-31, permits to install and operate ↗
- Ohio EPAOhio EPA air permit search and draft versus final guidance ↗
- Ohio Power Siting BoardNovember 19 siting decisions for Fairfield and Ashville ↗
- Ohio Power Siting BoardNovember 2026 gas generation and CHP case status, page 4 ↗
- Ohio EPADraft Fairfield Permit-to-Install P0140492, cover and staff determination ↗
- Ohio EPAOhio EPA public comment record for draft Fairfield permit P0140492 ↗
- Fairfield Energy Center, LLCFairfield application summary, air permit hearing and comment deadline ↗
- Supreme Court of OhioMcNamara-Smith v. Grube, 2026-Ohio-3035, paragraphs 6–8 and 41 ↗
- Pickaway County Board of ElectionsNovember 3 Ashville resolution vote, unofficial results updated November 19 ↗
- U.S. Environmental Protection AgencyFederal Clean Air Act resources for data centers ↗
Put the requirements to work
Bring the project.
Map the path to approval.
Connect the applicable requirements to the design, the evidence, and the people responsible for each decision.
Talk to an expert